The Cabinet considered a report of the Executive Director (Neighbourhoods and Environment) requesting that consideration be given to the new Highways Improvement Policy for the prioritisation and implementation of Highways Improvement Schemes.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1Following the major reorganisation of the Highways Department a review has been conducted by the Head of Service and relevant Service managers of how Highways Improvement Schemes are identified, prioritised and delivered.
1.2An outcome of this review has been the need for a new process for the proposal and prioritisation of the Highways Improvement Schemes that is clear, transparent, coordinated and sustainable and which aligns with the Administration’s priorities.
1.3This report concentrates on the overriding policy and its enabling implementation plans covering key issues and improvements across the borough.
Recommendations
2.1The Cabinet is asked to consider and agree the new Highway Improvements Policy for the prioritisation and implementation of Highways Improvement Schemes.
2.2In addition, Cabinet is asked to delegate authority to the Director of Highways to deliver the policy in accordance with agreed implementation plans for the various service area assets/issues.
1 3. Background
3.1Highways Improvement Schemes are changes to the existing highway infrastructure to improve the experience of the road user and/or community.
They can range from minor road junction or footway improvements to full resurfacing scheme, cycling schemes, traffic calming and public realm schemes.
3.2Highways Improvement Schemes are being received into the Highways Department on a daily basis with schemes also being identified through the Traffic Regulations Working Party (TRWP).
3.3Typically the type of improvement works can include pedestrian crossings, cycling facilities, new footways, school safety measures, traffic management and town enhancements, grass verge improvements, Traffic Regulation Orders (TRO) based solutions such as speed reduction and parking protection.
3.4Highways Improvement Schemes can be complex in nature consisting of activities such as consultations, legal orders, land acquisition, mobilising consultants and adhering to the terms of our Highways Term Contract, and for these reasons the delivery of schemes, once started, can typically take between 2 to 4 years.
3.5As there is currently no limit to the costs of schemes that can be proposed as priority, individual schemes on the list have ranged in value from several thousand pounds to several million pounds.
3.6In recent times there has been ad hoc requests for capital funding of individual schemes that has been available in total for these schemes and would normally take several years to address all the current priorities.
3.7With no formal borough-wide prioritisation, schemes have been delivered on a ‘first-come first-served’ basis, without demonstrating value for money, level of need or demand on resources.
3.8It should be noted that some highway schemes identified through grant funding and in s106 agreements are fully funded by developers and that the Borough has a legal obligation to deliver them. As the nature and cost of such schemes is prescribed in the s106 agreement, there is no discretion about how the funds can be spent. As schemes explicitly detailed in s106 agreements cannot be altered or changed and the agreement legally obligates Southend to deliver them they are therefore excluded from this process.
4. Proposal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.