- 1. That the extension for Porters Place Southend-on-Sea LLP budget period be approved until the revised Business Plan, budget and viability assessment is approved or 31st December 2022, whichever is the earlier. 2. That the LLP continue working with the Local Planning Authority on the Reserved Matters Application Phase 1a, until determination and thereafter until the revised Business Plan and updated viability assessment is approved on or before 31st December 2022, whichever is the earlier. 3. That the amended Annual Report and Financial Statements and auditors report for the LLP, year ending 31st March 2021 be noted and be submitted to Companies House, subject to no material changes being raised at the final audit sign-off. 4. That the Executive Director (Finance and Resources) be authorised to complete the South-East Local Enterprise Partnership (SELEP) back-to-back agreement with the LLP and authorise funds to be drawn from that grant to fund works in line with the current Business Plan. 5. That the progress of the Better Queensway project, including assurances relating to recent announcements by the Council’s partner, Swan ... view the full minutes text for item 836.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1This report seeks a time extension to the current Porters Place Southend-on- Sea LLP (“the LLP”) Budget which was previously extended following a report to the Shareholder Board on the 6th December 2021.
1.2This report seeks to approve a request from the LLP to continue with the Reserved Matters Application Phase 1a (RMA) beyond 31 st March 2022 to keep the Project on target.
1.3This report seeks approval of the LLP’s Annual Report and Financial Statements 2020/2021, in order that they can be filed by the LLP at Companies House by 31st March 2022 subject to no material adjustments at the final audit sign off.
1.4This report seeks to approve the signing of the South East Local Enterprise Partnership (SELEP) back-to-back agreement, between the Council and the LLP to enable funds to be drawn from this funding stream. This will hold the LLP accountable for funds drawn against the Getting Building Fund (GBF).
1.5This report also provides an update on progress of the Better Queensway project including assurances relating to recent announcements by the Council’s partner, Swan Housing Association.
Recommendations
2.1That approval is given for Porters Place Southend on Sea LLP (the LLP) to extend its budget period until the revised Business Plan, budget and viability assessment is approved, or 31st December 2022, whichever is the earlier.
2.2That approval is given to the LLP to continue working with the Local Planning Authority on the Reserved Matters Application Phase 1a, until determination and thereafter until the revised Business Plan and updated viability assessment is approved on or before 31 st December 2022, whichever is the earlier.
2.3That the Shareholder Board note the Annual Report and Financial Statements and auditors report for the LLP, year ending 31st March 2021 and agree they be submitted to Companies House subject to no material changes being raised at the final audit sign off.
2.4That the Executive Director of Finance & Resources be authorised to complete the South East Local Enterprise Partnership (SELEP) back-to- back agreement with the LLP and authorise funds to be drawn from that grant to fund works in line with the current Business Plan.
2.5That the Shareholder Board note the project update.
Background
3.1Economic Context
3.1.1 When the Shareholder Board recommended to Cabinet the previous extension to the budget in December 2021, it was with confidence that the revised Business Plan, budget and viability assessment would be ready by March 2022. However, across the world many larger infrastructure projects which were put on hold during the pandemic were finally given the green light during 2021. This has had a direct impact on all construction projects, including the Better Queensway project (“the Project”) as economic recovery fuelled the demand for raw materials which has resulted in constrained supplies as diminished inventories struggle to compete with strong demand elsewhere in the world.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.