That the preparation of a final clean suite of legal documents for the scheme, be approved. Reasons for Decision To enable the proposition to be presented clean, current documents for the funding market and to reduce procurement risk. Other Options The updated transaction could be documented by way of the approved variations but this is not considered to be optimal either in terms of managing risk or presentation to the funding market. Note: This is an Executive function Referred direct to Policy & Resources Scrutiny Committee for consideration Cabinet Member: Cllrs Gilbert and Collins
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
This report confirms that the updated Seaway Leisure legal documentation is now ready to exchange, following all the required due diligence, and enables the opportunity to be presented in the best light to the funding market.
The report identifies that there are no changes to the scheme arrangements, as previously approved by Members in November 2021, but merely to ensure the Council has a final clean suite of legal documents to effectively and swiftly proceed with the scheme.
Recommendation
That Cabinet approve the preparation of a final clean suite of legal documents for the Seaway Leisure scheme.
Background
3.1Cabinet agreed on 2 November 2021 (minute 417 refers) to vary the transaction with Turnstone Estates to enable an annuity lease structure to be put in place so that the development could be funded differently and delivery unlocked.
3.2The Council has appointed Pinsent Masons, the same lawyers who represented Colchester Borough Council on the very similar Northern Gateway transaction Seaway Leisure June 2022 1 of 4 Report Number: (now on site), to act on its behalf to document the transaction for the Seaway development.
3.3The Council has retained CBRE to advise on the property transaction and 31Ten to advise and review the proposition from a financial due diligence perspective.
3.4Collectively, the professional team and officers, following all the required due diligence, are comfortable and are ready to proceed to exchange. This will then enable Turnstone to proceed to the next stage (requiring a further c.£500k investment by them) and for the funding market to be approached following exchange of contracts with a view to funding the development in the autumn of 2022 for a start on site targeted for spring 2023.
3.5Given the increases in build costs arising principally from the increasing cost of inflation, it is estimated by Turnstone’s quantity surveyors that the total development cost is now likely to be in the order of £70m. The final cost of the scheme will be determined during Turnstone’s next stage which includes more detailed contractor engagement and procurement. It is important to note that the Council will only enter into a final agreement on the basis that the scheme is financially viable. Also that the increase in build costs being experienced has no impact on the level of the Council’s agreed ‘up to £10m’ enabling funding (minute 417 refers).
3.6The Cabinet decision in November 2021 provided for the existing transaction to be varied. The legal review and due diligence work which followed that decision has led to the conclusion that it would be significantly preferable for the Council to document the variation via a new document suite rather than a further variation of the existing suite however this was not provided for in the previous decision.
3.7The benefits of the new document suite are principally to remove redundant legacy drafting which is no longer required to mitigate procurement risk as the landscape has changed since the transaction was originally documented in December 2014, and to ensure that a professionally presented, concise and current set of drafting is presented to the funding market now to reduce the likelihood and extent of the need for document changes to secure the funding. Having recently worked with Colchester to fund the Northern Gateway, Pinsent Masons are very well placed to advise on the positioning of this documentation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.