Resourcing Better Outcomes - Finance and Corporate Performance Report 2022/23 - Period 6

Noted Executive 4 papers

Cabinet noted this item on Tuesday 8 November 2022. Below is the council's own wording, with the papers it was decided on.

Item453

Resolved

The Cabinet considered a report of the Executive Director (Finance and Resources) reviewing the Council’s financial performance. Recommended: That, in respect of the 2022/23 Revenue Budget Performance, as set out in Appendix 1 to the submitted report: 1. That the forecast outturn for 2022/23 for the General Fund and the Housing Revenue Account as at 30 September 2022, be noted. 2. That the management action taken and to be taken to reduce the forecast overspend of the Council’s revenue budget for 2022/23, be noted. 3. That the planned budget transfers (virements) of £400,000 from earmarked reserves, be approved. That, in respect of the 2022/23 Capital Budget Performance, as set out in Appendix 2 to the report: 4. That the expenditure to date and the forecast outturn as at 30 September 2022 and its financing, be noted. 5. That the requested changes to the capital investment programme for 2022/23 and future years, be approved. 6. That the Corporate Plan Performance Report as at 30 September 2022, as set out at Appendix 3 to the report, be noted. Reasons for recommendations: 1. The regular reporting of Revenue and Capital Budget Monitoring information provides detailed financial information to Councillors, senior officers and other interested parties on the financial performance of the Council. It sets out the key variances being reported by budget holders and the associated management action being implemented to address any identified issues. It also informs decision making to ensure that the Council’s priorities are delivered within the approved budget provision. 2. It is important that any adverse variances are addressed in order for the Council to remain within the approved budget provision or where this cannot be achieved by individual service management action, alternative proposals are developed and solutions proposed which will address the financial impact. Councillors will have a key role in approving any actions if the alternative proposals represent significant changes to the service delivery arrangements originally approved by them. 3. The challenge of delivering a balanced financial outturn for 2022/23 is significant. Some positive improvement has been achieved from Period 4 to 6, but further urgent action is needed to try to reduce all non-essential expenditure and/or generate extra income. This priority must be achieved whilst ensuring that our most vulnerable residents are looked after appropriately, and our statutory responsibilities are effectively discharged. Other options: The Council could choose to monitor its budgetary performance against an alternative timeframe, but it is considered that the current reporting schedule provides the appropriate balance to allow strategic oversight of the budget by Councillors and to also formally manage the Council’s exposure to financial risk. More frequent monitoring is undertaken by officers and considered by individual service Directors and the Council’s Corporate Management Team (CMT) including the implementation of any necessary remedial actions. Note: This is a Council Function Eligible for call-in to: Policy and Resources Scrutiny Committee Cabinet Members: Cllr George and Cllr Collins
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Cabinet

Purpose of report

The regular Resourcing Better Outcomes report is a key tool in scrutinising the Council’s overall finance and corporate performance. It is designed to provide an overview of progress to all relevant stakeholders at regular stages throughout the financial year. It is essential that the Council monitors its budgets and assesses its performance regularly to ensure that it is meeting its strategic objectives and providing value for money. This approach highlights where corrective action is necessary and reasonable mitigation is required to try to deliver a balanced financial position by the end of the year.

The recent series of events in Downing Street, the volatility of the current operating environment, combined with the significant increases experienced in both local service demand and unavoidable inflationary cost pressures arising from the global cost of living crisis has exacerbated an already incredibly challenging situation. Delivering a balanced budget in 2022/23 has potentially now got even more difficult to achieve. This period 6 report provides an update on the current year’s improved forecast outturn position and reinforces the need to continue to make some difficult choices and take decisive action.

Recommendations

That, in respect of the 2022/23 Revenue Budget Performance as set out in appendix 1 to this report, Cabinet:

2.1Note the forecast outturn for 2022/23 for the General Fund and the Housing Revenue Account as at 30 September 2022;

Resourcing Better Outcomes – Finance and Page 1 of 25 Report No: [number to be allocated] Corporate Performance Report 2022/23 – Period 6 2.2 Note the management action taken and to be taken to reduce the forecast overspend of the Council’s revenue budget for 2022/23;

2.3Approve the planned budget transfers (virements) of £400,000 from earmarked reserves, as set out in section 4.44.

That, in respect of the 2022/23 Capital Budget Performance as set out in appendix 2 of this report, Cabinet:

2.4Note the expenditure to date and the forecast outturn as at 30 September 2022 and its financing;

2.5Approve the requested changes to the capital investment programme for 2022/23 and future years, as set out in section 4 of appendix 2.

2.6Note the SCC Corporate Plan Performance Report as at 30 September 2022 set out in appendix 3.

3 Unprecedented Levels of Uncertainty and Financial Challenge Continues

3.1The finance and corporate performance report for period 4 highlighted the significant challenges facing the country, local government generally and within this context Southend-on-Sea City Council. Given the volatility and what have been described as once in a generation series of events including Brexit, the pandemic, the war in Ukraine, energy prices doubling and in some case tripling in cost, inflation at the highest level for decades. The recent developments in Downing Street have added further concern and uncertainty. Boris Johnson resigned on 7th July and Liz Truss was announced as the new Prime Minister on 6th September and on the same day installed Kwasi Kwarteng as the country’s new Chancellor of the Exchequer.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revenue Budget Performance: Period 6: September 2022Appendix 1 1.8 MB Download
PDF
Capital Investment Programme Performance: Period 6: September 2022Appendix 2 1.3 MB Download
PDF
SCC Corporate Plan Performance Report: Period 6 September 2022Appendix 3 450 KB Download
PDF
Resourcing Better Outcomes: Finance and Corporate Performance Report 2022/23: Period 6Report 271 KB DownloadRead as text

At this meeting

Whole meeting
448Apologies for AbsenceDecided 449Declarations of InterestDecided 450Minutes of the meeting held Tuesday, 26 July 2022Decided 451Minutes of the meeting held Wednesday 24 August 2022Decided 452Minutes of the Meeting held Thursday, 29 September 2022Decided
453Resourcing Better Outcomes - Finance and Corporate Performance Report 2022/23 - Period 6This decision
454Treasury Management Report - Mid Year 2022/23Decided 455Endorsement of Transport East Transport Strategy (Referred back from Place Scrutiny Committee, 10th October 2022)Noted 456Options for the Procurement of the Voluntary Sector Infrastructure Contract (Referred back from People Scrutiny Committee, 11th October 2022)Noted 457Refugee Resettlement and Asylum WorkDecided 458SEND StrategyDecided 459The Victoria Shopping Centre and Utilisation of Council BuildingsDecided 460Parking StrategyDecided 461City of Culture BidDecided 462Scrap Metal Dealers Licensing ConsultationDecided 463Annual Safeguarding ReportDecided 464Council Tenants Heating Charges Assessment 2022/23Decided 465Proposal to increase the allowances and fees for Southend in-house foster carersApproved 466Debt Management - Position to 30th September 2022Decided 467Minutes of the meeting of Public Protection Working Party held Thursday, 6 October 2022Noted 468Minutes of the meeting of The Shareholder Board held Wednesday, 12 October 2022Noted 469Minutes of the meeting of the Shareholder Board held Tuesday, 8 November 2022Decided 470SO46 ReportNoted 471Fair Cost of Care and Market Sustainability PlanDecided

Who was there

8 of 23 attended
SG
Councillor Stephen GeorgeChair, present
CM
Councillor Carole MulroneyVice-Chair, present
LB
Councillor Laurie BurtonCommittee Member, present
PC
Councillor Paul CollinsCommittee Member, present
IG
Councillor Ian GilbertCommittee Member, present
KM
Councillor Kay MitchellCommittee Member, present
MT
Councillor Martin TerryCommittee Member, present
SW
Councillor Steven WakefieldCommittee Member, present
MB
Michael BarnesOfficer, expected
MM
Michael MarksOfficer, in attendance
SB
Sarah BakerOfficer, expected
JC
Joe ChestertonOfficer, in attendance

All 23 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Resourcing Better Outcomes - Finance and Corporate Performance Report 2022/23 - Period 6This decision
  2. Resourcing Better Outcomes - Finance Performance Report for September 2023 (Period 6)Approved
  3. Resourcing Better Outcomes - Financial Performance Report for September 2023 (Period 6)Noted
  4. Resourcing Better Outcomes - Financial Performance Report For September 2023 (Period 6)Decided
  5. Resourcing Better Outcomes - Financial Performance Report for November 2022 (Period 8)Noted
  6. Resourcing Better Outcomes - Finance and Corporate Performance Report 2022/23 - Period 6Noted

More from Southend-on-Sea Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 Minutes of the Meeting held on Monday, 7 September 2026That the Minutes of the Meeting held on Monday 7 September 2026 be amended to correct the typographical error in minu... Decided Open
12 Oct 2026 Decisions taken by, or in consultation with, Cabinet MembersThat the decisions taken by, or in consultation with, the relevant Cabinet Members since the last Cabinet meeting be ... Noted Open
12 Oct 2026 Official Feed and Food Control Service Plan 2026-27That the achievements delivered against the Official Feed and Food Control Service Plan 2025/26 be noted. 2. That the... Noted Open
12 Oct 2026 Income Contract with Castle Point Borough Council for CCTV System ManagementThat it be agreed to enter into a contract with Castle Point Borough Council for the provision of CCTV Services to Ca... Agreed Open
12 Oct 2026 Procurement of a Stairlift Installation, Maintenance & Removal ServiceThat approval be given to undertake a procurement exercise to establish a Framework Agreement for the provision of a ... Approved Open