Housing and Pipeline Update

Noted Scrutiny 1 paper

Policy and Resources Scrutiny Committee noted this item on Wednesday 15 March 2023. Below is the council's own wording, with the papers it was decided on.

Item774

Resolved

That the following decisions of the Cabinet be noted: “1. That the progress made on the Housing Pipeline to date, be noted. 2. That the Council undertakes due diligence regarding the potential allocation of capital funds for Afghan and Ukrainian resettlement purposes from the Department of Levelling Up, Housing and Communities (DLUHC) Local Authority Housing Fund (LAHF) and that authority be delegated to the Executive Director (Finance and Resources) and the Executive Director (Growth and Housing), in consultation with the Cabinet Member for Economic Recovery, Regeneration and Housing, to reach agreement about any bid decisions and to pursue actions set out in the submitted report. 3. That the use of both Denton Avenue site and Bradford Bury garage site for the development of Passizhaus pilot projects utilising existing Section 106 funds and Right to Buy funds, be approved. 4. That the next steps for the Housing Pipeline set out below, be approved: · The development of a revolving investment fund to deliver the pipeline opportunities. The investment fund would work alongside other financing sources to deliver housing pipeline projects. · Sale of the Thorpedene Campus site via auction to secure full, quick capital receipt and mitigate holding and demolition costs, with the capital receipt ringfenced to help fund future Housing Pipeline development opportunities. · Sale of the Shorefield Gardens site via auction to secure a full, quick capital receipt with the capital receipt to be ringfenced to help fund future Housing Pipeline development opportunities. · Use existing funds or funds received from site sales for detailed feasibility works, cost planning and design works for the Hamlet Court Road, the Cattery and Civic 2 sites.” Note: This is an Executive Function Cabinet Member: Councillor I Gilbert
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Policy and Resources Scrutiny Committee

Purpose of report

1.1To update members on the work of the Housing Pipeline to date, detail future housing development opportunities across the city and set out recommendations for the proposed way forward.

Recommendations

2.1To note the progress made on the Housing Pipeline to date (paragraph 3.3)

2.2Agree that the council undertakes due diligence regarding the potential allocation of capital funds for Afghan and Ukrainian resettlement purposes from the Department of Levelling Up, Housing and Communities’ (DLUHC) Local Authority Housing Fund (LAHF) and that authority is delegated to the Executive Directors of Finance and Resources (s.151) & Growth and Housing in consultation with the Cabinet Member for Economic Recovery, Regeneration and Housing to reach agreement about any bid decisions and to pursue actions as set out in 3.10 (paragraphs 3.7-3.10)

2.3To agree to the use of both the Denton Avenue site & Bradford Bury garage site for the development of Passivhaus pilot projects utilising existing Section 106 (S106) funds and Right to Buy (RTB) funds (paragraphs 3.11- 3.14)

2.4To agree the next steps for the Housing Pipeline:

• The development of a revolving investment fund to deliver the pipeline opportunities. The investment fund would work alongside other financing sources to deliver housing pipeline projects. • Sale of the Thorpedene Campus site via auction to secure full, quick capital receipt and mitigate holding and demolition costs, with the capital receipt ringfenced to help fund future Housing Pipeline development opportunities. Housing Pipeline Update Report Number • Sale of the Shorefield Gardens site via auction to secure a full, quick capital receipt with the capital receipt to be ringfenced to help fund future Housing Pipeline development opportunities. (paragraphs 3.15-3.24) • Use existing funds or funds received from site sales for detailed feasibility works, cost planning and design works for the Hamlet Court Road, the Cattery and Civic 2 sites.

Background

3.1On 25th June 2019, Cabinet resolved to progress with developing a pipeline of housing and regeneration projects and proceed with the Acquisitions Programme for council housing.

3.2Cabinet also received further reports on 5th November 2019, 16th January 2020 and 25th February 2020 providing further updates on the progress of the Acquisitions Programme and PSP LLP resetting and rebranding.

Completed Housing Pipeline Schemes

3.3Since the establishment of the Housing Pipeline following the completion of the Hinguar School and Saxon Lodge developments (47 homes including 15 affordable homes), the Council has successfully delivered a range of housing development and acquisitions projects as detailed in the table below:

Project Name Outcomes Benefits

Project Outcomes 20-21

Acquisitions Programme 18 homes purchased from the private • c.£152k per year in rent to the (including Next Steps market to be converted to Council Housing Revenue Account (HRA) Accommodation Housing Programme (NSAP)) • c.£27k of Council Tax per year Use of Right to Buy for acquisitions to • 5 NSAP homes used for Housing avoid repayment of 1-4-1 receipts First for complex clients back to Treasury.

PSP Southend LLP - Development of 9 x private family • c.£20k of additional Council Tax per Friars Development homes completed as part of the PSP year & c£24,500 of Rent and Rates development in Shoeburyness • Regeneration of local area and provision of new 50-place nursery

Project Outcomes 21-22

Acquisitions Programme 23 homes purchased from the private • c.£170k in yearly rent to the HRA (including NSAP) market to be converted to Council Housing • c.£47k of Council Tax per year

• 13 NSAP homes used for Housing First for complex clients

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing and Pipeline UpdateReport 1.9 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 29 attended
DG
Councillor David GarstonChair, present
DN
Councillor Daniel NelsonVice-Chair, apologies, sent representative
BB
Councillor Brian BeggsCommittee Member, present as substitute
MB
Councillor Margaret BortonCommittee Member, present
DC
Councillor Daniel CowanCommittee Member, present
TC
Councillor Tricia CowdreyCommittee Member, apologies, sent representative
HB
Councillor Helen BoydCommittee Member, present
TC
Councillor Tony CoxCommittee Member, present as substitute
MD
Councillor Meg DavidsonCommittee Member, apologies, sent representative
FE
Councillor Fay EvansCommittee Member, present
KE
Councillor Keith EvansCommittee Member, present
AJ
Councillor Anne JonesCommittee Member, present

All 29 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Housing and Pipeline UpdateThis decision
  2. Next Stage of the Housing PipelineApproved
  3. Next Stage of the Housing PipelineNoted
  4. Housing and Pipeline UpdateNoted
  5. Housing and Pipeline UpdateDecided
  6. Housing & Development Pipeline UpdateDecided

More from Southend-on-Sea Policy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Minutes of the Meeting held on Thursday, 13th February 2025That the minutes of the meeting of the Committee held on Thursday, 13 th February 2025 be confirmed as a correct reco... Decided Open
31 Mar 2025 Additional Budget Considerations - 2025/26That the report to Cabinet be noted. Note: This is an Executive Function Cabinet Member: Councillor D Cowan (Leader o... Noted Open
13 Feb 2025 Minutes of the Meeting held on Thursday, 30th January 2025That the minutes of the meeting of the Committee held on Thursday, 30 th January 2025 be confirmed as a correct recor... Decided Open
13 Feb 2025 Corporate Performance Report Q3 2024/25 (October to December 2024) including Corporate Delivery Plan Actions update Q3 2024/25That the report to Cabinet be noted. Note: This is an Executive function Cabinet Member: Councillor D Cowan (Leader o... Noted Open
13 Feb 2025 Approval of the Annual Procurement Plan for 2025/26That the report to Cabinet be noted. Note: This is an Executive Function Cabinet Member: Councillor P Collins (Portfo... Noted Open