- (a) That the Council enter into a Planning Obligation by Deed of Variation under Section 106 of the Town and Country Planning Act 1990 (as amended) to allow the following modifications to the Deed of Agreement dated 30th June 2011 (as amended by Deeds of Variation dated 22nd June 2016 and 19th September 2018) pursuant to planning permission 10/02012/EXTM: (i.) Clause 3.1 of the Second Schedule – Education Contribution payable prior to first occupation of any of the residential units provided by the planning permission (ii.) Clause 6.1 of the Second Schedule – Bus Infrastructure Contribution payable prior to first occupation of any of the residential units provided by the planning permission (iii.) Definitions, Clause 7 of the Second Schedule, Clause 1.1 and 1.3 of the Third Schedule – Warrior Square Contribution – amend the definition and terms to ‘Local Play Contribution’ to be spent within 10 years of receipt and to be spent on ‘the provision of new play equipment within the vicinity of the Site’ (b) That the Executive Director (Growth and Housing), Director of Planning or Service Manager for Development Control be DELEGATED to AGREE A MODIFICATION OF THE PLANNING OBLIGATION dated 30th June 2011 (as amended by Deeds of Variation dated 22nd June 2016 and 19th September 2018) pursuant to planning permission 10/02012/EXTM referred to above. (c) That the cancellation of the associated invoice no. 771452 dated 4th July 2019 be authorised, including Bus Infrastructure Contribution (£30,739.80) and Education Contribution (£27,165.67); as well as ceasing any debt recovery proceedings in relation to this outstanding invoice as the payments would no longer be due at this stage.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
Application Type: Deed of Variation (application S106A(3))
Ward: Milton
Proposal: Modification of Section 106 agreement dated 30/06/2011 (as amended by Deeds of Variation dated 22/06/2016 and 19/09/2018) pursuant to planning permission 10/02012/EXTM, to extend the payment provisions in relation to the Education, Bus Infrastructure and Warrior Square Contributions.
Address: Part Of Former Keddies Building And Maitland House, Chichester Road, Southend-On-Sea, Essex
Applicant: [name removed] of Broadway Estates Ltd
Agent: [name removed] of Hobbs Parker Property Consultants LLP
Consultation Expiry: 02.02.2023
Expiry Date: 05.05.2023
Case Officer: Amanda Rogers
Plan Nos: n/a
Supporting information: Letter from Hobbs Parker dated 7th December 2022
Recommendation: DELEGATE to the Executive Director (Growth and Housing), Director of Planning or Service Manager - Development Control to AGREE A MODIFICATION OF THE PLANNING OBLIGATION dated 30th June 2011 (as amended by Deeds of Variation dated 22nd June 2016 and 19th September 2018) pursuant to planning permission 10/02012/EXTM and enter into a Planning Obligation by Deed of Variation to allow the modifications set out in paragraph 8.1. 1 Site and Surroundings
1.1The application site is within the town centre and includes offices, a hotel and other commercial floorspace.
1.2Development surrounding the site is mixed and comprises residential, offices, retail and other commercial uses. The site lies opposite Warrior Square Gardens and Conservation Area.
1.3The existing development comprises a 4 storey and an 11-storey building. The development to which this Section 106 (S106) agreement relates is for an additional 11 storeys over the existing 4 storey building and an additional two floors over the existing 11 storey building.
2 The Proposal
2.1Planning permission was granted on 30th June 2011 (10/02012/EXTM) to extend the time limit for permission 07/01276/FULM, to erect an 11-storey extension over the existing 4 storey building, erect 2 floors over the existing 11 storey building and convert the extended building into 98 self-contained flats (“2011 permission”).
2.2A technical start, including preparation works to allow the installation of a canopy over the ground floor entrance, was made on the development following approval of pre- commencement conditions on 27th June 2014, thus the development is considered to have commenced. However, the applicant advises that due to viability issues the development has not proceeded beyond the entrance canopy installation. They advise that complex structural considerations relating to extending above the existing building have significant financial implications; the applicant has confirmed that they are now looking to dispose of the site due to ongoing viability difficulties with the proposed development.
2.3The 2011 permission was subject to a S106 agreement 30th June 2011. This agreement has been modified twice by Deeds of Variation dated 22nd June 2016 and 19th September 2018. The S106 (as amended) secures the following:
• Bus Infrastructure Contribution – outstanding invoice for £30,739.80 dated 4th July 2019 (interest to be added at 4% above base lending rate of Barclays Bank Plc from date due to date of payment) • Education Contribution – outstanding invoice for £27,165.67 dated 4th July 2019 (interest to be added at 4% above base lending rate of Barclays Bank Plc from date due to date of payment) • Warrior Square Contribution – £38,988.00 paid 28/09/2018 as agreed as part of the terms of the 2018 Deed of Variation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.