The Cabinet considered a report of the Executive Director (Environment and Place) presenting information to enable the Council to decide on revoking its decision to charge for parking between the hours of 6pm and 9pm in Zone 1A; which Budget Council took in February 2023. The Cabinet was informed that the wording in paragraphs 2.6 and 5.3 of the submitted report was incorrect. The revocation of the hours of enforcement related to the pay and display bays in Zone 1A only and that other contraventions would still be enforced.” With reference to the proposed introduction of the on-street parking bays in Hartington Road, Pleasant Road, Beach Road and Burdett Road, the Leader and Cabinet Member for Highways, Transport and Parking gave assurances that the proposals were to introduce additional shared use bays and that there would be no loss of the existing capacity for residents in those roads. The Ward Councillors would also be consulted on the proposals prior to the statutory consultation process.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1This report provides background information to enable the Council to decide on revoking its decision to charge for parking between the hours of 6pm and 9pm in Zone 1A; which Budget Council took in February 2023.
1.2The full year budget assumption of additional parking income for charging between the hours of 6pm and 9pm was £250k per annum.
1.3It is expected that the reduction in revenue will be more than offset by increasing the number of sea front parking spaces. The creation of these spaces will require a capital investment of £175k per annum for two years.
1.4The creation of these additional spaces will take circa of 1 - 9 months due to the potential for physical works as well as the creation of new traffic regulation orders. It is anticipated that there will be no additional revenue forecast within 2023/24 as any revenue will first be off set against the balance of the required saving of £250k and then secondly against implementation costs. However, it is expected that additional revenue is expected in 2024/25 (dependant on driver behaviours).
1.5Various concerns have been expressed about the economic effect on the city, and most notably the sea front economy, of the recently implemented 6-9pm charging tariffs. This recommendation is aimed at overcoming those concerns and raising additional revenue by the provision of extra parking facilities. 2. Recommendations
It is recommended that Cabinet:
2.1Agree to revoke the decision made at Budget Council in February 2023 and remove the 6pm to 9pm charging arrangements considering the financial implications as set out in Section 5;
2.2Agree the temporary cessation of charges for 6pm to 9pm during the summer school holidays pending the relevant activity required by the service, as set out in section 3 below;
2.3Agree the new parking bays to be introduced as set out in Section 4;
2.4Agree a one-off budget of £40k (paragraph 5.7) to be allocated to the parking service for the required changes to be implemented and initially funded from the Business Transformation Reserve and then reimbursed from the additional parking income;
2.5Note there will be capital investment of circa £175k and initially funded from reprioritised highways schemes and then reimbursed by the additional parking income;
2.6Note that there will be no Civil Enforcement Officer presence in Zone 1A after 6pm.
3. Tariff change process
3.1If Cabinet agree to reverse the decision and make the changes, the service is required to: • Go through a statutory process (which is a minimum of 21 days) to advertise the new charges on a Traffic Regulation Order and map- based order. • Order new signage, including the inserts for pay and display machines. This may require a procurement exercise and time required to complete (unless waiver is granted by Procurement team). • Work with our third-party providers to change tariffs: ▪ 2 different providers for pay and display machines. ▪ 2 providers for cashless parking ▪ 1 provider for virtual permits • User Acceptance Test (UAT) for all digital platforms i.e. cashless parking and parking permit system. This is to confirm the changes are reflecting correctly. • Information update on MySouthend – this will be collaborative work with colleagues from customer services. • Information update on the Council’s website – this will be a collaborative work with colleagues in communications team. • Review existing terms and conditions for permits and parking areas. 4. Timescales
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.