That the current contract for Transitional Supported Housing be extended for 7 months until 31 st January 2026, subject to all necessary steps being undertaken to negotiate and finalise the extension of these contracts. Reasons for decision: 1. To extend the current contract for Transitional Supported Housing. Following review of service performance and feedback, the commissioning team are satisfied with delivery against the service objectives. The providers have also suitably engaged with the Council with contract meetings and reviews throughout the entirety of the contract to date. There have been no concerns raised regarding the provision they are offering. 2. The extension will align the expiration date of the contract with future commissioning ambitions for improving children’s placements, which could then award any following contract via a suitably coproduced competitive procurement exercise. Other options: 1. Decommission or do not extend the current contract.This is not recommended. Southend City Council has a statutory duty to support all children currently residing in the current commissioned service. The absence of service will affect the outcomes of young people currently supported significantly. 2. Go out to tender for a new service specification by 30 th June 2025. This is not recommended as the current provider is performing well and going out to tender at this time risks destabilising service delivery. This would not allow time to fully co-produce and plan future service specification and contracts. Note: This is an Executive Function Not eligible for call-in Cabinet Member: Cllr Burton
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1The current contract for Transitional Supported Housing for Young People in Southend is due to expire on 30th June 2025 and is costed at £393,967 per annum at a fixed price rate.
1.2There are currently two providers delivering this service: YMCA and Sanctuary.
1.3The commissioning team have undertaken a review of these services and recommend that the service contract is extended for a period of seven months to enable adequate time to effectively co-produce a new service specification.
Recommendations
It is recommended that Cabinet:
2.1Agree to extend the current Transitional Supported Housing contract for 7 months until 31st January 2026 subject to all necessary steps being undertaken to negotiate and finalise the extension of these contracts.
Background
3.1Following a procurement exercise in 2022, YMCA and Sanctuary were awarded the contract for Transitional Supported Housing.
3.2The Transitional Supported Housing service is split over three contracts across the two providers. The services support children and young people aged 16-25 that have a need for accommodation, are young parents, or facing homelessness. 3.3. The current contracts were initially put in place for two years (01/7/22 - 30/6/24) Terms and conditions allow the contracts to be extended up to 30 June 2025, the contracts were extended by four months to 31 October 2024, and then by a further extension until 30 June 2025. A tender exemption will be needed for the additional requested period.
Annual Average Client Support hours/ No. of contract annual cost / group week placements cost placement 16-25 and young 396 80 £393,967 £4,924.59 parents
4. Reasons for Decisions 4.1. Following review of service performance and feedback, the commissioning team are satisfied with delivery against the service objectives. The providers have also suitably engaged with the Council with contract meetings and reviews throughout the entirety of the contract to date. There have been no concerns raised regarding the provision they are offering.
4.2This extension will align the expiration date of the contract with future commissioning ambitions for improving children’s placements, which could then award any following contract via a suitably coproduced competitive procurement exercise.
4.3The council would be unlikely to complete a full procurement in line with the current contract end date without this extension. Extending the Transitional Support Housing contract would allow time to fully co-produce and plan future service specification and contracts.
4.4Extending the contract by a period of seven months will also allow full review of service specifications and contracts to review changes requested by children’s services.
5. Other Options
5.1Decommission or do not extend the current contract- This is not recommended. Southend City Council has a statutory duty to support all children currently residing in the current commissioned service. The absence of service will affect the outcomes of young people currently supported significantly.
5.2Go out to tender for a new service specification by 30th June 2025 - This is not recommended as the current provider is performing well and going out to tender at this time risks destabilising service delivery. This would not allow time to fully co-produce and plan future service specification and contracts. 6. Financial Implications
6.1The service is currently funded at £393,967 per annum due to expire 30th June 2025. The service is currently contracted at a fixed rate. This annual sum is contained within the existing budget of the Children’s Service.
Legal implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.