The Cabinet considered a report of the Executive Director (Environment and Place) concerning the closure of Chalkwell Ramp in March 2025 on public safety grounds and the proposal to demolish the current structure and replace with a temporary structure to return access from the station/highway to the beach for all users. This would enable the Council to work longer term on a permanent replacement structure, without removing further access.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1Following the closure of Chalkwell Ramp in March 2025 on public safety grounds, the council is committed to demolishing the current structure and replacing with a temporary structure to return access from the station/highway to the beach for all users.
1.2This will enable the council to then work longer term on a permanent replacement structure, without removing further access.
1.3The value of this work exceeds £500,000 and therefore makes it a key decision.
1.4Due to the proximity of the ramp to the railway, track possessions (closure of the railway and suspension of train services) are required in order to carry out the work. The limited availability of track possessions (September 2025 only) means we have a very narrow window within which to carry out the work and therefore the only available option to achieve this is to utilise the contractor who is currently undertaking adjacent works to c2c’s Chalkwell Station as part of Network Rail’s national Access For All (AFA) project.
1.5An urgent decision is required to progress this matter, primarily due to these works requiring the utilisation of two full weekend track possessions to complete both elements (demolition and construction of temporary replacement structure). The only available possessions remaining this year are in September 2025. To enable the progression of works and subsequent approvals from Network Rail to meet these tight deadlines, is to facilitate a
Page 1 of 7 direct award to the contractor currently working on the Chalkwell Station AfA project and who is already occupying these possessions and undertaking similar works.
Recommendations
It is recommended that Cabinet:
2.1Agrees that a contract be directly awarded to c2c’s current Chalkwell station AFA works contractor, Octavius Infrastructure Limited, in order to undertake works including the demolition of the current structure and installation of a temporary access ramp.
2.2In awarding the contract Cabinet acknowledges the decision is being taken as an urgent decision outside of the budget framework in accordance with Part 2, Section 5 of the Constitution for the reasons set out within the report and will report to Council on the addition of £0.766M to the 2025/26 capital investment programme funded by borrowing for the demolition of Chalkwell Ramp and its replacement with a temporary access structure.
2.3Delegates Authority to the Executive Director of Environment and Place, in consultation with the Leader, to finalise the contract terms.
2.4Notes that, in accordance with Part 5 Section 4 (Call-in and Urgency) of the Council’s Constitution, the call-in provisions shall not apply as the decision being taken is urgent for the reasons set out within the report
Background
3.1Chalkwell Ramp is an ageing structure, nearly 115 years old and is now considered life expired. The level of deterioration, which has been monitored for several years, is such that it was no longer an acceptable risk to keep open and in public use. It was therefore closed on public safety grounds in March 2025.
3.2This has been met with public and member dissatisfaction due in the main to the lack of alternative access provision between the highway/railway station (from The Ridgeway) to Chalkwell beach and promenade area. This is a popular destination area for swimmers, water sports, families, school outings, as well as providing easy access to local businesses.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.