Resolved
The Cabinet considered a report of the Executive Director (Environment and Place) that sought approval to the proposed extension of the highways term contract for a period of 8 months to 31 st March 2026.
Cabinet approved this item on Monday 21 July 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
The Cabinet considered a report of the Executive Director (Environment and Place) that sought approval to the proposed extension of the highways term contract for a period of 8 months to 31 st March 2026.
1.1The current highway term service maintenance contract comes to its contractual end on 31st July 2025.
1.2The Council has already commenced the tender process to award a new contract, starting from 1st August 2025 and is currently at the Expression of Interest Stage before formal issue of the Invitation to Tender.
1.3However, due the additional level of scope to be included within one overall contract (e.g. the inclusion of additional elements like gully emptying/winter maintenance), the finalisation of suitable contract documents delayed the initial planned release of the tender documents.
1.4In addition, recent developments in Devolution and Local Government Reorganisation (LGR) dramatically change the potential future direction of the authority and officers must ensure that a robust contract is in place to cover likely future changes.
1.5Therefore, on that basis and to ensure sufficient time for a robust procurement process and mobilisation of the new contract, approval is sought to extend the existing highways term contract to 31st March 2026, a period of 8 months. This is a Key Decision primarily due to the value of the contract extension being above the threshold. 2. Recommendations
It is recommended that Cabinet:
2.1Approves the extension of the current highways term maintenance contract from the 31st July 2025 to 31st March 2026 for the reasons stated in this document.
3.1The current highways contract was for a 7 year term, with the contractual option of a 3-year extension, based on KPI results, which were achieved and the extension activated. Therefore this contract comes to an end on 31st July 2025.
3.2The current incumbent contractor is Marlborough Highways Ltd.
3.3During the early market engagement for the new contract, it was clear that a 7-year term would deliver the best efficiencies from key elements like vehicle/plant depreciation etc.
3.4Therefore, for the new contract it is proposed to procure a 7 plus 7-year contract term, with the extension based on contract performance and KPI outcomes.
3.5In addition, all elements of highway and coastal works should be delivered via one contractor. We believe this option would deliver improved efficiencies and quality of service, help contract management and further help to reduce disruption to the network by being able to effectively deliver multiple services at the same time when appropriate.
3.6The additional options include gully emptying, winter maintenance, verge maintenance, and an extended level of potential professional services.
4. Reasons for Decisions
4.1The increased scope and developments with Devolution and LGR require a robust contract to cover these elements, and a contract extension is therefore required to ensure that this can be achieved through a robust procurement process allowing sufficient time for mobilisation.
4.2Any extension needs to cover the winter maintenance season, from October to March hence the recommendation to extend to end of March 2026. Changing a highway contract part way through the winter season introduces a high degree of risk and is not considered industry best practice.
4.3The contract extension would also align more effectively with financial year requirements and allow the contractor to start with a clear understanding of their full annual budget allocation and that all the previous contract works could be completed and invoiced to ensure the effective closing out and demobilisation of that contract in alignment with the end of the financial year.
5. Other Options
5.1Alternative options are limited for the reasons outlined for the decision in section 4.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Extension of current Highway Term Service ContractReport | 107 KB | DownloadRead as text |
Follow Cabinet at Southend-on-Sea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2026 | Minutes of the Meeting held on Monday, 7 September 2026That the Minutes of the Meeting held on Monday 7 September 2026 be amended to correct the typographical error in minu... | Decided | Open |
| 12 Oct 2026 | Decisions taken by, or in consultation with, Cabinet MembersThat the decisions taken by, or in consultation with, the relevant Cabinet Members since the last Cabinet meeting be ... | Noted | Open |
| 12 Oct 2026 | Official Feed and Food Control Service Plan 2026-27That the achievements delivered against the Official Feed and Food Control Service Plan 2025/26 be noted. 2. That the... | Noted | Open |
| 12 Oct 2026 | Income Contract with Castle Point Borough Council for CCTV System ManagementThat it be agreed to enter into a contract with Castle Point Borough Council for the provision of CCTV Services to Ca... | Agreed | Open |
| 12 Oct 2026 | Procurement of a Stairlift Installation, Maintenance & Removal ServiceThat approval be given to undertake a procurement exercise to establish a Framework Agreement for the provision of a ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.