- That ENFORCEMENT ACTION be AUTHORISED to include, as necessary, the service of an Enforcement Notice under Section 172 of the Act and the pursuance of proceedings whether by prosecution or injunction to secure compliance with the requirements of the Enforcement Notice to require those issued with a copy of the Enforcement Notice to: a. Remove the uPVC windows from the ground and first floor, south-facing, front elevation of the dwelling. AND b. Reinstate within the dwelling’s south-facing front elevation windows with identical design and material as those that were in situ immediately before the breach took place OR install alternative windows that are in full accordance with a planning permission that has previously been obtained; AND c. Remove from site all materials resulting from compliance with a) and b) above. With time for compliance of Six (6) calendar months. For the following reason(s): 01. The unauthorised uPVC windows, due to their unsympathetic design and materials, cause less than substantial, albeit significant, harm to the character and appearance of the dwelling and thereby to the contribution made by this dwelling to the character and significance of the Leigh Cliff Conservation Area. The public benefits of the development do not outweigh this harm. The unauthorised development is therefore contrary to the National Planning Policy Framework (2024), Policies KP2 and CP4 of the Core Strategy (2007), Policies DM1, DM3 and DM5 of the Development Management Document (2015) and the advice contained within the National Design Guide (2021), the Southend-on-Sea Design and Townscape Guide (2009) and the Leigh Cliff Conservation Area Appraisal (2021).
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
Southend-on-Sea City Council Director of Planning and Economy (Environment and Place): Kevin Waters Civic Centre, Victoria Avenue, Southend-on-Sea, Essex SS2 6ER 01702 215000 www.southend.gov.uk
Dear [name removed] and Country Planning Act 1990 as amended.
Alleged Breach: Replacement of windows in conservation area with uPVC Address: 33 Cliff Parade, Leigh-on-Sea, Essex, SS9 1BB
Further to the letter sent to you on the 4th of June 2025, the Council are in receipt of information with regards to a breach of planning control that has taken place at the above address. The information relates to the replacement of windows with uPVC along the front elevation of the dwellinghouse, within a Conservation Area.
As stated in the aforementioned letter, I can confirm that a breach of planning control has been identified.
The property at the above address falls within the Leigh Cliff Conservation Area and is under Article 4 Direction, for which certain permitted development rights have been removed, including for the replacement of windows, therefore express planning permission is required for this development. As no such permission exists for the replacement of the windows along the front elevation, a breach of planning control has been identified.
Also, the replacement of the windows with uPVC is an unsympathetic design within the Conservation Area and therefore unlikely to be approved by the Local Planning Authority. Please review the Leigh Cliff Conversation Area Appraisal and the Leigh Cliff Article 4 Direction via the following link for more information on replacements and alterations within the Conservation Area, this includes what would be considered a sympathetic design - https://www.southend.gov.uk/conservation-areas/leigh-cliff-conservation-area
With the above in mind, to remedy the identified breach of planning control, please submit a planning application for a new design that is sympathetic to the Conservation Area, using the advice in the Leigh Cliff Conservation Area Appraisal (please note I am unable to state whether or not such an application would be approved).
Planning applications can be submitted via the Planning Portal (www.planningportal.co.uk).
The application forms and guidance about how to apply for planning permission can be accessed at this link: http://www.southend.gov.uk/info/200416/make_a_planning_application
@southendCityC | SouthendCCOfficial | southend-city-council | southendcityc Although the right to submit an application to retain the uPVC windows in their current form remains, I would not advise you to seek planning permission retrospectively, as it would be unlikely that such an application would be successful.
This letter is the final warning, if action is not taken to remedy the identified breach within 28 days of the date of this letter, the Local Planning Authority will have no choice but to consider the expediency of formal enforcement action.
I would be grateful if you could inform me of your intentions via email within 7 days of the date of this letter.
I hope to have your co-operation in this matter. If further information is required, please do not hesitate to contact me.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.