Financial Performance Report for September 2025 (Period 6)

Noted Scrutiny 4 papers

AI summarySouthend scrutiny committee notes mid-year finance report showing £6.385M forecast revenue overspend, with £1.67M in budget virements and £17.56M of capital programme changes set for Cabinet approval.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedReport to be forwarded to Cabinet
Money£6.385M forecast overspendNet General Fund revenue overspend for 2025/26
What happens nextPeriod 8 report to January 2026 CabinetNext financial performance update
Who it affectsChildren's Services and adult social careMain drivers of forecast overspend

What was decided

The committee noted the report being forwarded to Cabinet, covering the Period 6 financial performance for 2025/26.

Cabinet is recommended to note the £6.385M General Fund overspend and £0.803M HRA overspend, and to approve £1,667,996 of budget virements. Report 2.1, 2.2, 2.3, 5.1, 6.2, 5.69, P121

Cabinet is recommended to approve requested changes to the capital investment programme totalling £17.562M, including £14.437M of budget carry-forwards. Report 1.4, 2.5, P150

Why

The overspend is driven mainly by Children's Services (£7.974M) and adult social care (£2.304M), reflecting complex demand and cost pressures in statutory services. Report 5.17, 5.34, 5.58

Around 67.6% of the Council's budget goes on statutory services, which account for 100% of the reported service overspend. Report 4.2

Targeted management action has cut the forecast overspend by £0.057M since Period 4, with stricter recruitment controls, capital challenge sessions and Leader-led focus groups in place. Report 5.1, 5.12, 5.13

What happens next

A Period 8 update covering the position to end of November 2025 will go to January 2026 Cabinet. Report 1.1

The Chief Executive and Executive Director (Finance & Resources) will continue exploring further mitigation options outside their delegated powers. Report 2.2

A further capital challenge session is planned for December 2025, with resulting changes included in the Period 8 report. Report 7.12

The money

  • £6.385M Forecast General Fund revenue overspend for 2025/26 Report 5.1
  • £165.059M Approved General Fund Revenue Budget for 2025/26 Report 5.1
  • £1,667,996 Budget virements for Cabinet approval Report 2.3, 5.69, P121
  • £17.562M Requested changes to capital investment programme budgets Report 1.4
  • £14.437M 2025/26 capital scheme budgets proposed for carry-forward Report P150
  • £62.636M Estimated 2025/26 capital outturn as at end of September Report 7.17
  • £79.4M Revised 2025/26 capital investment programme budget Report 7.6
  • £0.803M Forecast HRA overspend for 2025/26 Report 6.2
  • £3.590M Approved new savings and income generation initiatives for 2025/26 Report 5.14
  • £7.974M Children's Services forecast overspend Report 5.34
  • £2.304M Adult social care forecast overspend Report 5.58

Options considered

  • Chosen: Note the report and forward to Cabinet. Standard scrutiny process for executive reports
  • Rejected: Monitor budgetary performance against an alternative timeframe. Current schedule provides appropriate strategic oversight and risk management Report 9.1

Implications

  • Financial: Council must take corrective action to address a £6.385M forecast overspend and approach a balanced 2025/26 budget. Report 5.1
  • Financial: Capital programme requires re-profiling with £14.437M of 2025/26 budgets to be carried into future years. Report P150
  • Legal: Reporting complies with section 151 Local Government Act 1972 and section 28 Local Government Act 2003 on budget monitoring. Report 11.3
  • Legal: Supports the Council's best value duty under section 3 of the Local Government Act 1999. Report 11.2
  • Equalities: Some proposed actions may have equality and diversity implications, to be considered through normal equalities impact assessments. Report 13.1
  • Risk: Budget gap for 2026/27 could range from £6.5M to £10M depending on Fair Funding Review 2.0 and business rates reform impacts. Report 5.9
  • Staffing: Tighter controls on permanent recruitment and a Workforce Panel now oversee agency staff spend. Report 5.12

Who and where

  • Children, Learning and SEND service users and staff Report 5.34, 5.36
  • Adult social care service users and providers Report 5.58, 5.61
  • Council housing tenants (HRA service) Report 6.1, 6.2
  • Local authority staff subject to recruitment controls Report 5.12
  • Temporary accommodation users Report 5.27, 5.13

Timeline

  • 30 September 2025: Period 6 financial position reported Report 5.1
  • October 2025: Capital challenge sessions covering all schemes held with Leader and Cabinet Member for Finance Report 7.12
  • November 2025: Government-run public consultation on Greater Essex devolution and reorganisation expected Report 3.6
  • 26 November 2025: Chancellor's budget speech Report 5.9
  • December 2025: Further capital challenge session planned; 2026/27 provisional financial settlement expected mid/late December Report 5.9, 7.12
  • January 2026: Period 8 financial performance report to Cabinet Report 1.1
  • Early 2026: Decision by Secretary of State on Greater Essex devolution and reorganisation expected Report 3.6

Plain English for the jargon

  • General Fund: The main revenue account for a council's day-to-day spending on services other than council housing.
  • HRA: Housing Revenue Account, the ring-fenced account for income and spending on council housing.
  • Virement: A budget transfer between headings within a council's approved budget, with no net change to total spending.
  • Period 6: Mid-year financial reporting point covering the six months to the end of September 2025.
  • FFR2.0: The Fair Funding Review 2.0, a Government consultation published 20 June 2025 on redistributing funding to local authorities.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item48

Resolved

That the report to Cabinet, be noted. Note: This is an Executive Function Cabinet Member: Cllr Cowan
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Policy and Resources Overview & Scrutiny Committee

Executive summary

1.1This is the second financial performance report for 2025/26 and presents a key update of the Council’s financial position to all relevant stakeholders at this mid- point of the year. A further update will be presented to the January 2026 Cabinet meeting, for the position as at the end of November 2025 (Period 8). The Council reviews its budgets and assesses its performance regularly to ensure that it is meeting its strategic objectives and providing value for money. This approach follows recommended best practice, this report highlights variances from approved spending plans, proposes corrective action where necessary and forecasts the scale of mitigation required to try to deliver a balanced financial position by the end of the year.

1.2In recent years many Local Authorities have declared significant financial distress and concerns over their future sustainability, driven by significant increases in service demand and unavoidable inflationary cost pressures. This is particularly found within upper tier local authorities responsible for providing statutory service provision for social care. The Government have promised significant change in funding distribution methodology and a commitment to a multi-year future financial settlement for the sector from 2026/27.

Finance Performance Report - September 2025-26 - Period 66 Page 1 of 23 1.3 The overall revenue forecast overspend position for 2025/26 is currently £6.385M, driven by continuing complex service demands in social care and Children’s Services. Targeted action continues to mitigate this forecast overspend but additional new demand and complex social care cases continue to present significant financial challenges. The Council is doing all it can to get as close as possible to a balanced budget by the end of the financial year.

1.4This report seeks approval for £17.562M of requested changes to the capital investment programme budgets. Capital budgets will be further revised in-year for affordability and deliverability of the programme This is normal good practice and demonstrates strong financial management of capital projects.

Recommendations

That, in respect of the 2025/26 Revenue Budget Performance as set out in appendix 1 to this report, Cabinet:

2.1Notes the forecast outturn for 2025/26 for the General Fund and the Housing Revenue Account as at 30 September 2025.

2.2Notes the proposals for reducing the forecast overspend of the Council’s revenue budget for 2025/26 and requests that the Chief Executive and Executive Director (Finance & Resources) continue to explore all opportunities outside of their delegated powers and authority to improve the financial position by the year-end (section 5), in consultation with the relevant portfolio holders and the Leader.

2.3Approves the budget transfers (virements) of £1,667,996, as set out in paragraph 5.69 of this report.

That, in respect of the 2025/26 Capital Budget Performance as set out in appendix 2 of this report, Cabinet:

2.4Notes the expenditure to date and the forecast outturn as at 30 September 2025 including how this will be financed.

2.5Approves the requested changes to the capital investment programme for 2025/26 and future years, as set out in section 4 of appendix 2.

Finance Performance Report - September 2025-26 - Period 66 Page 2 of 23 3 Southend-on-Sea City Council’s financial situation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Period 6: September 2025 Revenue Budget Performance 2025-26Appendix 1 906 KB Download
PDF
Period 6: September 2025 Capital Investment ProgrammeAppendix 2 580 KB Download
PDF
SummaryHeadlinesOfPlannedGovernmentReviewsAndReformsAppendix 3 74 KB Download
PDF
Financial Performance Report for September 2025 (Period 6)Report 564 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 21 attended
RW
Councillor Ron WoodleyChair, present
IF
Councillor Irene FergusonVice-Chair, present
SA
Councillor Sam AllenCommittee Member, present
JC
Councillor James CourtenayCommittee Member, present
TC
Councillor Tony CoxCommittee Member, apologies, sent representative
IG
Councillor Ian GilbertCommittee Member, present
RM
Councillor Robert McMullanCommittee Member, present
JM
Councillor James MoyiesCommittee Member, present
CW
Councillor Chris WebsterCommittee Member, present
JM
Councillor Judith McMahonCommittee Member, present as substitute
SC
Stephanie CoxOfficer, expected
RH
Robert HarrisOfficer, in attendance

All 21 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Financial Performance Report for September 2025 (Period 6)This decision
  2. Financial Performance Report for July 2026 (Period 4)Agreed
  3. Financial Performance Report for July 2026 (Period 4)Noted
  4. Financial Performance Report for November 2025 (Period 8)Noted
  5. Financial Performance Report 2025/26 to end of November 2025 (Period 8)Noted
  6. Financial Performance Report for September 2025 (Period 6) - Changes to the Capital Investment ProgrammeApproved

More from Southend-on-Sea Policy and Resources Overview & Scrutiny Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Minutes of the meeting held on Thursday, 9 July 2026That the minutes of the meeting held on 9 July 2026 be confirmed as a correct record. Decided Open
2 Sep 2026 Southend-on-Sea Council Corporate Performance Report – Quarter 1That the report to Cabinet, be noted. Noted Open
2 Sep 2026 Adults and Children's Social Care - Finance and Budget PressuresThat the report and presentations outlining budget pressures and challenges within Children's Social Care and Adult S... Noted Open
2 Sep 2026 Debt Management – Position to 31st July 2026That the report to Cabinet, be noted. Noted Open
2 Sep 2026 Financial Performance Report for July 2026 (Period 4)That the report to Cabinet, be noted. Noted Open