CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Southend-on-Sea Borough Council
Place Overview & Scrutiny Committee, Tuesday 10 February 2026 at 6.30pm

LEVI Project Progress Update

Noted Scrutiny 3 papers

AI summarySouthend Place Scrutiny Committee notes progress on 15-year electric vehicle chargepoint contract with Zest Eco Ltd, set to deliver over 1,100 on-street residential chargers with no council investment.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo decisions or recommendations required
MoneyNot stated
What happens nextPhase 1 installations from launchEarly focus on priority and high-demand areas
Who it affectsResidents without drivewaysPlus existing council car park charger users

What was decided

The committee noted the LEVI Project Progress Update report, with no decisions or recommendations required at this stage. Report P5

Why

The council applied for government LEVI funding in November 2023 and £1,448k was approved in April 2024 to install residential EV infrastructure for households without driveways. Report P6, 3.2

A 15-year contract was signed with chargepoint operator Zest Eco Ltd in November 2025 following procurement that concluded in April 2025, with the project officially launching in December 2025. Report P9, 3.5, 4.2

What happens next

Phase 1 will deliver 900 chargers within the first two years, with Phases 2, 3 and 4 adding approximately 600, 750 and 750 chargepoints respectively over years 2 to 10. Report 5.2

Early Phase 1 will prioritise residents who have already expressed interest, install in high-demand areas, and replace existing EV car park chargers, with engagement of ward councillors planned. Report 6.1

The money

  • £381 million Government Local Electric Vehicle Infrastructure Fund announced March 2023
  • £1,448k LEVI funding approved for the council in April 2024 Report 3.2
  • £1.488m LEVI Grant funding invested in the project Report 7.2
  • c.£38m Investment from chargepoint operator Zest Report 7.2
  • c.£80m Total lifetime contract value Report 7.2
  • estimated £6m Income to the Council in revenue over the full contract period, dependent on utilisation Report 7.2

Options considered

  • Chosen: Note the report. Officers stated no decisions or recommendations were required at this stage Report P5

Implications

  • Financial: No financial investment from the Council; the council will receive an estimated £6m revenue share over the contract life, wholly dependent on utilisation, and this income will maintain the EV team resource. Report P20, 4.4
  • Legal: External legal firm Trowers and Hamlins LLP supported the procurement, funded by the LEVI capability grant; no specific legal implications arise from the report. Report P23
  • Climate: The contract supports the council's wider environmental objectives by providing reliable on-street EV charging and upgrading existing car park chargepoints. Report 4.3
  • Risk: Revenue income to the council of an estimated £6m over the full contract period is wholly dependent upon utilisation of the chargepoints. Report 7.2

Who and where

  • Residents without access to a driveway who need on-street EV charging Report 4.3
  • Users of existing EV chargers in council car parks, which will be replaced and expanded Report 4.2
  • Ward councillors, who will be engaged in the project delivery
  • Chargepoint operator Zest Eco Ltd, contracted for 15 years Report 4.2, P9
  • The council's EV team, whose resource will be funded by revenue from the chargepoints Report 4.4

Timeline

  • March 2023: Government announced £381 million LEVI fund
  • November 2023: Council applied for LEVI funding Report 3.2
  • April 2024: £1,448k LEVI funding approved alongside 4 years of resource funding Report 3.2
  • March to December 2024: Tender documentation prepared and procurement launched Report 3.3
  • April 2025: Procurement concluded with preferred bidder Zest Report P9
  • May 2025: Cabinet Member sign off of preferred bidder Report P9
  • November 2025: Contract signed and sealed with Zest Report P9
  • December 2025: Project officially launched with press release and social media announcements Report 3.5
  • End of 2027: Phase 1 expected to complete with 900 chargers installed in the first two years Report 5.2
  • Years 2 to 10 of the contract: Phases 2, 3 and 4 delivered progressively with approximately 600, 750 and 750 chargepoints respectively Report 5.2
  • September 2026: Draft Phase 1 delivery timetable extends to this date (see Appendix 2) Report 5.3

Plain English for the jargon

  • LEVI: Local Electric Vehicle Infrastructure Fund, a £381 million UK government fund for local authority EV charging infrastructure
  • CPO: Chargepoint Operator, the company that installs, operates and maintains EV charging points
  • EV: Electric Vehicle
  • Phase 1: The first two years of the contract, targeting installation of 900 on-street chargepoints
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item54

Resolved

That the report be noted.
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Place Overview & Scrutiny Committee

Agenda Item No.

Meeting: Place Overview & Scrutiny Committee Date: 10th February 2026 Classification: Part 1 Key Decision: No Title of Report: LEVI Project Progress Update

Report Author: Gemma Webb, EV Programme Manager and Oshuwa Adaramola, EV Solution Project Support Officer Executive Director: Alan Richards, Executive Director for Environment and Place

1. Purpose of Report 1.1 This report updates on the EV Project process since the In-Depth Scrutiny Report was presented to Place Scrutiny, People Scrutiny and Policy & Resources Scrutiny on 10th, 11th and 12th July 2023. 1.2 Within this report is a background of what has happened since 2023 and the future plans for Southend's EV Infrastructure.

2. Recommendation 2.1 No recommendations/decisions required at this stage.

3. Background summary 3.1 In March 2023 the Government announced the £381 million Local Electric Vehicle Infrastructure Fund (LEVI), giving local authorities across England the opportunity to apply for dedicated electric vehicle (ev) infrastructure and resource funding. The funding is predominantly for installing a reliable residential infrastructure network aimed at households with no access to a driveway.

3.2The Council applied for funding in November 2023 and £1,448k was approved in April 2024 alongside resource funding for 4 years.

3.3From March to December 2024 the project team prepared tender documentation with guidance and support from the LEVI Support Body (Energy Saving Trust, Cenex and PA Consulting) navigating the new funding with other LA’s and completed the LEVI sign off process to launch its procurement to the market in December 2024, being in the first tranche and within the top 10 to launch.

1 3.4 The procurement concluded in April 2025 with preferred bidder, Zest and Cabinet Member sign off took place in May. Mobilisation of contract, including final sign off from the LEVI funding body concluded with signing and sealing the contract with Zest in November 2025.

3.5In December 2025 the project officially launched with a press release and announcements made across social media platforms.

4. Contract Summary 4.1 The table in Appendix 1 shows the Council’s specification objectives as presented during the procurement process alongside the corresponding objectives provided by the winning bidder Zest, by way of summary;

4.2The Council has entered a 15-year contract with the chargepoint operator (CPO) Zest Eco Ltd for the installation, operation, and maintenance of a minimum of 1,100 on-street residential chargepoints across the city. The contract has also incorporated a replacement programme for the existing ev car park chargers with an increase to the current provision.

4.3This partnership will provide residents with reliable on-street charging facilities, upgrade existing chargepoints in Council car parks, significantly increase the overall number of chargepoints available and contribute to the Council’s wider environmental objectives.

4.4In addition, the Council will benefit financially by receiving a share of the revenue generated from the operation of these chargepoints. This revenue will maintain the EV team resource to manage the contract and once established, provide a yearly income to the council.

5. Programme Delivery and Timeline 5.1 Since the launch of the project in December 2025, the EV team have been sharing datasets, public consultation data, existing charger information, licencing and process information for Zest to analyse. The EV team have also been setting up the Governance and contract management for the project, hosting meetings and with Zest discussing an overall programme plan that begins with the installation of 900 chargers within the first two years of the contract.

5.2Following the completion of Phase 1 at the end of 2027, Phases 2, 3 and 4 will be delivered progressively throughout years 2 to 10 of the contract. The Phases are expected to deploy approximately 600, 750, and 750 Chargepoints respectively.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SCC Objectives- Zest contractual commitmentAppendix 1 54 KB Download
PDF
EV Project Phase1 Activities draftAppendix 2 195 KB Download
PDF
LEVI Project Progress UpdateReport 111 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 19 attended
CM
Councillor Carole MulroneyChair, present
KB
Councillor Kevin BuckVice-Chair, apologies, sent representative
SB
Councillor Susan BadgerCommittee Member, apologies, sent representative
MB
Councillor Margaret BortonCommittee Member, present
JC
Councillor James CourtenayCommittee Member, present as substitute
TC
Councillor Tony CoxCommittee Member, present as substitute
SH
Councillor Stephen HabermelCommittee Member, present
RL
Councillor Richard LongstaffCommittee Member, present
JM
Councillor Judith McMahonCommittee Member, apologies, sent representative
SN
Councillor Shahid NadeemCommittee Member, apologies, sent representative
MO
Councillor Mandy O'ConnorCommittee Member, present as substitute
CN
Councillor Cheryl NevinCommittee Member, present

All 19 on the meeting page

More from Southend-on-Sea Place Overview & Scrutiny Committee

All decisions
MeetingDecisionOutcome
18 Jun 2026 Minutes of the Meeting held on Tuesday, 10th February, 2026That the Minutes of the meeting held on Tuesday, 10 February 2026 be confirmed as a correct record. Decided Open
18 Jun 2026 Better Queensway Underpass Closure Impact Assessment UpdateThat the update on the closure of the Better Queensway underpass and associated impact assessment, be noted. Note: Th... Noted Open
18 Jun 2026 Parks and Playgrounds UpdateThat the parks and playgrounds update be noted. Noted Open
18 Jun 2026 Work Programme 2026/27That the work programme of the Committee be noted. This is a Scrutiny function. Noted Open
10 Feb 2026 Minutes of the Meeting held on Tuesday, 2nd December, 2025That the Minutes of the meeting held on Tuesday 2 nd December 2025 be confirmed and signed as a correct record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies