CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Southend-on-Sea Borough Council
Health & Wellbeing Board, Monday 9 March 2026 at 5.00pm

S.75 Deed of Variation with ECC, Thurrock and the ICB in relation to Joint Learning Disability Commissioning Services

Noted Committee 1 paper

AI summarySouthend Health and Wellbeing Board approves varying the Section 75 joint commissioning agreement for learning disability services with Essex, Thurrock and the new Essex ICB, in effect from 1 April 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedDeed of Variation to joint learning disability commissioning agreement
MoneyNone extra for SouthendNo new financial responsibilities for Southend City Council
What happens next1 April 2026Revised Section 75 in force with new Essex ICB
Who it affectsAdults with learning disabilitiesPeople with learning disabilities or autism across Southend Essex Thurrock

What was decided

The Board noted the progress update on the independent review of the partnership. Report 2.1

The Board approved the principle of using a Deed of Variation to update the 2018 Section 75 Partnership Agreement, and delegated authority to the Executive Director Adult and Communities to agree the final wording with the Cabinet Member for Social Care and Healthier Communities. Report 2.2, 2.3

The Section 75 Agreement will be reviewed at least every two years, with financial schedules refreshed annually. Report 2.4

Why

The current Section 75 Agreement, not materially updated since 2020, is significantly out of date and no longer fit for purpose, which poses a risk to the partnership and its constituent bodies. Report P27, 4.1

An independent review found the system governance for Learning Disabilities and Autism had become duplicative and confusing, with no clear accountability. Report P16

A financial stocktake revealed an accumulated partnership underspend of £8.1m as of December 2025, and lack of clarity about overall finances, which partners agreed to address. Report P33, P35

What happens next

The Joint Executive Committee of the three existing ICBs (on behalf of the new Essex ICB) and Essex, Southend and Thurrock Councils are all being asked to agree the Deed of Variation in March 2026, so it can come into force on 1 April 2026. Report P31

A new governance structure, including a Partnership Board, a new monthly Programme Board and a Finance subgroup, is planned to start on 1 April 2026, with some existing groups stood down from the end of March. Report P17, P19, P20, P21, P22

An extraordinary meeting of the Partnership Board is scheduled for 18 March 2026 to consider and sign off the integrated annual plan for 2026/27, including proposed new headline targets. Report P48, P50, P51

The money

  • £8.1m Accumulated programme underspend as of December 2025 Report P35
  • £980k SNEE ICB funding shortfall for 2024/25 being made good Report P36
  • £20.8m Current annual investment by partners in specialist learning disability adult and children contracts with HPFT and EPUT Report P38
  • £1.26m Annual NHS England contribution under the Transforming Care funding formula Report P41
  • £3.2m Actual 2024/25 cost of the original Transforming Care cohort Report P42
  • £1.94m Recurrent shortfall between the NHS England formula contribution and actual cost, funded by SET partners Report P42
  • £3.4m 2024/25 cost of the new (non Transforming Care) cohort, largely met by ICBs Report P43
  • £1.05m Total 2024/25 cost of the joint Health Equality team, above budgeted level and to be rebased from 2026/27 Report P45

Options considered

  • Rejected: Withdraw from the Section 75 Agreement. Would leave Southend City Council separate from the strategic commissioning opportunities the joint arrangements enable, and would split funding streams from the ICB and Southend City Council away from the small cohort of individuals Southend Adult services is responsible for. Report 5.1

Implications

  • Financial: There are no additional financial responsibilities for Southend City Council triggered by this review; the joint team budget is to be rebased from 2026/27. Report 6.1, P45
  • Legal: A Section 75 agreement under the National Health Service Act 2006 is needed to underpin joint commissioning and delegated responsibilities; without one, there would be risk around governance, decision making, financial oversight and care delivery. Report 7.1, P26
  • Equalities: The pooled approach supports the Health Inequalities team's work to address historical inequalities in access to good quality health care and independent living for people with a learning disability. Report 8.1
  • Risk: An out of date Section 75 poses a risk to the partnership and its constituent bodies, including a recurring funding shortfall on the original Transforming Care cohort. Report P27, P42
  • Other: Governance is being streamlined to remove duplication, with the existing Delivery Board and Assurance Delivery Group stood down from the end of March 2026. Report P16, P22

Who and where

  • People with learning disabilities and/or autism across Southend, Essex and Thurrock, including children and young people Report 3.1, P20
  • The Health Equality joint team hosted by Essex County Council, about 14 WTE (17 individuals) Report P44
  • Specialist learning disability service providers HPFT and EPUT, whose contracts expire in October 2027 Report P38, P39
  • The cohort funded under the original Transforming Care Programme and the newer follow me cohort, whose costs exceed the NHS England formula contribution Report P41, P42, P43

Timeline

  • 2018: Section 75 Partnership Agreement developed and agreed by all partners Report 3.2, P26
  • Early 2025: Partners agreed to commission an independent review of the Section 75 and wider partnership arrangements Report 3.3
  • June 2025: First phase of the independent review (stocktake) concluded Report 3.4
  • December 2025: Position used for the financial stocktake showing an £8.1m accumulated programme underspend Report P35
  • March 2026: Joint Executive Committee of the three ICBs and Essex, Southend and Thurrock Councils to agree the Deed of Variation Report P31
  • 18 March 2026: Extraordinary meeting of the Partnership Board scheduled to sign off the integrated plan for 2026/27 Report P48
  • 1 April 2026: New governance arrangements and revised Section 75 Agreement to come into force alongside the new Essex ICB Report P17, P31
  • October 2027: Specialist learning disability adult and children contracts with HPFT and EPUT expire, triggering a commissioning and procurement strategy Report P39

Plain English for the jargon

  • Section 75 (S75) Agreement: A legally binding agreement under the National Health Service Act 2006 that lets NHS bodies and local authorities pool funds and delegate functions for joint commissioning.
  • ICB: Integrated Care Board, the NHS body responsible for commissioning healthcare services in an area; replaces the former Clinical Commissioning Groups (CCGs).
  • LDA: Learning Disabilities and/or Autism.
  • Transforming Care Programme: National policy programme focused on supporting adults with a learning disability to move out of long term hospital settings into community based care; provides an annual NHS England formula contribution to the partnership.
  • SDF: Strategic Development Fund, the ICB funding stream that provides the bulk of the partnership's programme funding.
  • WTE: Whole Time Equivalent, a standard measure of staffing levels.
  • HPFT and EPUT: Hertfordshire Partnership University NHS Foundation Trust and Essex Partnership University NHS Foundation Trust, the consortium providing specialist learning disability services.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item33

Resolved

- 1. That the progress update included in this report be noted. 2. That the principle of using a Deed of Variation to the Section 75 Partnership Agreement be approved. 3. That the Executive Director Adult & Communities be delegated authority to agree the final Deed of Variation to the revised Section 75 Agreement in consultation with the Cabinet Member for Social Care and Healthier Communities. 4. That the Section 75 Agreement be reviewed at least every two years, as well as annually refreshing the financial schedules.
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Health & Wellbeing Board

Executive summary

1.1The purpose of this report is to: (a) update the Board on progress with the independent review; and (b) seek agreement to the amended Section 75 partnership agreement for Learning Disabilities and Autism joint services between Southend on Sea City Council, Thurrock Council, Essex Council and Essex ICB.

1.2The paper is for discussion and agreement.

Recommendations

2.1That the progress update included in this report be noted.

2.2That the principle of using a Deed of Variation to the Section 75 Partnership Agreement be approved.

2.3That the Executive Director Adult & Communities be delegated authority to agree the final Deed of Variation to the revised Section 75 Agreement in consultation with the Cabinet Member for Social Care and Healthier Communities

2.4That the Section 75 Agreement be reviewed at least every two years, as well as annually refreshing the financial schedules.

3. Context and Background

3.1Planning and delivering comprehensive, integrated health and care services to people with learning disabilities and/or autism (LDA) will always pose some challenges, given the number of partners involved. This is particularly true in Southend, Essex and Thurrock where there are (until April 2026) three ICBs, three upper tier local authorities and multiple providers and VCSEs.

3.2Partly to address this complexity and to attempt to streamline arrangements, a Section 75 Agreement was developed and agreed by all partners in 2018 and has been in place ever since.

3.3As there had not been a review of either the S75 itself, or the wider partnership arrangements, for some time, in early 2025 partners agreed to commission an independent review. The review had two main elements:

(i) A first phase, which was a stocktake of the existing arrangements. (ii) A second phase, which focuses on progressing a small number of priority areas, in order to help address some of the issues identified.

3.4The first phase concluded in June 2025, and the main conclusions have been widely discussed across the system.

3.5The second phase, progressing a small number of priority areas, is now nearing completion, and is the focus of this report. This includes:

(i) System governance (ii) Revised Section 75 Agreement (iii) Financial Stocktake (iv) Planning for 2026/27

3.6System governance

3.6.1 One of the key findings from the first phase of the review was that the system’s governance for LDA has evolved over a long period of time to a point where it is no longer fully effective. A number of new groups have been established, which as well as causing duplication tends to confuse decision making and accountability.

3.6.2 To address this, as part of the second phase of the project a review of governance has been undertaken and a revised, more streamlined process has been developed and agreed. The new arrangements are planned to commence on 1 April 2026, to coincide with the establishment of the new Essex ICB.

3.6.3 The overview is set out below, and the key elements to note include:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
S.75 Deed of Variation with ECC, Thurrock and the ICB in relation to Joint Learning Disability Commissioning ServicesReport 173 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 25 attended
JG
Jose Garcia-LoberaVice-Chair, present
MA
Maggie AtkinsonOfficer, expected
ME
Margaret Eni-OlotuOfficer, expected
JG
Jane GardnerNon-elected, non-voting, expected
AK
Alex KhaldiNon-elected, non-voting, expected
JC
Jo CrippsNon-elected, non-voting, expected
RJ
Rebecca JarvisCo-Optee, expected
KR
Krishna RamkhelawonCo-Optee, in attendance
CM
Caroline McCarronCo-Optee, apologies
SM
Sophia MorrisOfficer, expected
ER
Emma RichardsonOfficer, expected
PS
Paul ScottNon-elected, non-voting, expected

All 25 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. S.75 Deed of Variation with ECC, Thurrock and the ICB in relation to Joint Learning Disability Commissioning ServicesThis decision
  2. Better Care Fund - Update and Section 75 Agreement (Deed of Variation)Approved

More from Southend-on-Sea Health & Wellbeing Board

All decisions
MeetingDecisionOutcome
16 Jun 2026 Minutes of the Meeting held on Monday, 9th March, 2026That the Minutes of the Meeting held on Monday, 9 th March 2026 be confirmed as a correct record. Decided Open
16 Jun 2026 NHS Essex ICB UpdateThat the NHS Essex ICB update, be noted. Noted Open
16 Jun 2026 Greater Essex Health Determinants Research Collaboration Progress UpdateThat the HDRC progress update be noted. Noted Open
16 Jun 2026 Canvey & Southend Coastal Navigator Network - Launch & Proposed prioritiesThat the update on the Canvey & Southend Coastal Navigator Network, be noted. Noted Open
16 Jun 2026 Drug and Alcohol Service - CQC review and outcomeThat the report be noted. Noted Open