Southend-on-Sea Borough Council
Audit & Governance Committee, Tuesday 21 April 2026 at 6.30pm

Internal Audit Service Quarterly Performance Report

Noted Finance 7 papers

AI summarySouthend Audit & Governance Committee noted progress on the 2025/26 Internal Audit Plan, confirmed sufficient resources and compliance with the Global Internal Audit Standards.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFour recommendations all noted, including compliance
MoneyWithin approved budgetNo specific figure given
What happens nextJuly 2026 meetingOutstanding recommendations progress report due
Who it affectsInternal audit serviceAuditees and Council governance arrangements

What was decided

The Committee noted progress made in delivering the 2025/26 Internal Audit Strategy and Plan. Report 2.1

The Committee noted that sufficient resources remain available to complete the remainder of the plan and the annual opinion for 2025/26. Report 2.1

The Committee noted that the internal audit service is compliant with the Global Internal Audit Standards, and noted assurance levels and management acceptance of audit findings. Report 2.1, 5.4

Why

Internal audit is an assurance function supporting the Committee in discharging its Terms of Reference, including assurance over the Annual Governance Statement. Report 6.1, 9.2

The Accounts and Audit Regulations 2015 require the Council to undertake an effective internal audit, and the Public Sector Internal Audit Standards require the Committee to receive regular updates on plan delivery. Report 3.1, 9.1, 9.2

What happens next

Cyber Security Incident Management and Homelessness audits have been deferred into 2026/27, with follow up of actions arising from NCSC and MHCLG work respectively.

The HR People Vision and Staff Pay follow up audits have been changed to advice and support work tied to absence management changes in Business World.

A report on progress with implementation of audit recommendations, including the payroll impact of absence management through Business World, is being prioritised for the July 2026 meeting. Report 5.6

Options considered

  • Chosen: Note the four recommendations as set out in the report Report 2.1
  • Rejected: Review of the internal audit delivery model as part of the Council's transformation programme. To be considered separately and reported back to the Committee Report 7.1

Implications

  • Financial: The Audit Plan will be delivered within the approved budget, though four vacant posts are being covered using their salaries to buy in external accountancy support. Report 8.1
  • Legal: The Council must meet the Accounts and Audit Regulations 2015 and UK Public Sector Internal Audit Standards; the report supports those duties. Report 9.1, 9.2
  • Staffing: The team has four vacancies and an Audit Manager on maternity leave until June 2026, with the other Audit Manager recruited in July 2025. Report 15.2
  • Risk: Key risks managed include loss of in-house staff, limited management capacity, external supplier delivery, and maintaining client relationships during service development. Report 15.2
  • Climate: The team uses electronic working papers, public transport where possible, remote meetings and operates across Council and Castle Point sites in private vehicles. Report 11.1, 11.2
  • Equalities: All officers have completed Equality and Diversity training and the team complies with the Equality Act 2010 and the Human Rights Act 1998. Report 12.2

Who and where

  • Southend-on-Sea Borough Council internal audit team and its auditees Report 3.2
  • Council services with audits deferred or amended, including ICT, Housing and HR
  • Castle Point Borough Council, where the team also operates Report 11.1

Timeline

  • April 2025: Audit Plan for 2025/26 originally reported to the Committee.
  • 1 April 2025 to March 2026: Reporting period for the 2025/26 audit plan, with 24% of audits finalised, 39% at draft stage and 12% deferred or amended. Report 4.1, 5.3
  • July 2025: Vacant Audit Manager post recruited. Report 15.2
  • January 2026: Last progress report to the Committee.
  • March 2026: Date for status of audit work in Appendix 1. Report 4.1
  • 21 April 2026: Date of this Committee meeting.
  • June 2026: Audit Manager due back from maternity leave. Report 15.2
  • July 2026: Next Committee meeting, to receive outstanding audit recommendations progress report and annual reporting items. Report 5.6

Plain English for the jargon

  • Global Internal Audit Standards (GIAS): The professional standards governing internal audit practice, against which the service has been assessed as compliant.
  • Accounts and Audit Regulations 2015: The regulations that require the Council to maintain an effective internal audit of its risk management, control and governance.
  • Public Sector Internal Audit Standards: The UK application of GIAS, which sets the duties of the Audit Committee in relation to the annual Internal Audit Plan.
  • Business World: The Council's system through which absence management has been introduced, creating additional payroll assurance work.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item39

Resolved

That the progress made in delivering the 2025/26 Internal Audit Strategy and Plan, be noted. 2. That it be noted that sufficient resources remain available at this time to complete the remainder of the plan, and the annual opinion for 2025/26. 3. That it be noted that the internal audit service is compliant with the Global Internal Audit Standards. 4. That the levels of assurances given on the work completed during this reporting period and that management have accepted the findings of the audits and have set reasonable time scales to implement the recommendations, be noted. Reasons for decision: Internal audit is an assurance function providing assurance to assist the Committee to effectively discharge its responsibilities as per its Terms of Reference. The delivery of the internal audit plan will assist the Committee with obtaining assurance that the Annual Governance Statement for the year appropriately reflects the conditions at the Council.
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Audit & Governance Committee

Executive summary

1.1The purpose of this report is to update the Audit & Governance Committee on the progress made in delivering the Internal Audit Strategy and Plan for 2025/26.

Recommendations

2.1That the Audit Committee receives the assurance about: • the progress made in delivering the 2025/26 Internal Audit Strategy and Plan • sufficient resources remaining available at this time to complete the remainder of the plan, and to provide the annual opinion for 2025/26 • the internal audit service being compliant with the Global Internal Audit Standards • the levels of assurances given on the work completed during this reporting period and that management have accepted the findings of the audits and have set reasonable time scales to implement the recommendations.

Background

3.1The Accounts and Audit Regulations 2015 require the Council to undertake an effective internal audit to evaluate the effectiveness of its risk management, internal control and governance processes, taking into account public sector internal auditing standards or guidance.

3.2The Council’s internal audit team is in place to meet that requirement.

4. Internal Audit Plan Status

4.1Appendix 1 sets out the current status of the audit work planned for the year as at 31s March 2026. 4.2 Appendices 2a to 2e set out the results of the work completed since the last progress report to the Audit & Governance Committee in January 2026. 4.3 To ensure that our work remains focussed on the areas of greatest risk to the Council, we continue to consider our Audit Plan for 2025/26 that was reported to the Committee in April 2025. Providing appropriate support and assurance in respect of Local Government Reorganisation in Essex is under consideration with management. There have been further changes since the last report to the Committee with the: • Planned work on Cyber Security Incident Management being deferred following assurance being obtained from an assessment of arrangements undertaken with the National Cyber Security Centre (NCSC) that the ICT service are currently implementing the actions arising from. Therefore internal audit will follow up the delivery of those actions during 2026/27. • Planned work on Homelessness has been deferred following a deep dive assessment of the Council’s approach undertaken by the Ministry for Housing, Communities and Local Government (MHCLG) that the Housing service are currently implementing the actions arising from. Therefore internal audit will follow up the delivery of those actions during 2026/27. • HR People Vision and Staff Pay follow up planned audits being amended to advice and support work to support the amendments to the approaches being developed by HR to update the Council’s arrangements, and the changes required to payroll arrangements as a result of the implementation of absence management through Business World.

5. Performance Targets and Resourcing

5.1As outlined in the Strategy presented to the April 2025 Audit & Governance Committee, the team will be reporting on a more limited set of indicators this year given the amount of work that is still being contracted out.

5.2For the period since 1 April 2025 the team has had an average of 1.25 days of sickness absence. This figure is an improvement on the average of 5.7 days sickness absence in the equivalent period last year.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App 1- Internal Audit Plan 25-26 Apr 2026Appendix 172 KB Download
PDF
App 2a Opinion and Themes HighAppendix 55 KB Download
PDF
App 2b Opinion and Themes SatisfactoryAppendix 119 KB Download
PDF
App 2c Opinion and Themes PartialAppendix 64 KB Download
PDF
App 2d Opinions and Themes Audits RevisitedAppendix 65 KB Download
PDF
App 2e Opinion and Themes other audit and grantsAppendix 66 KB Download
PDF
Internal Audit Service Quarterly Performance ReportReport 118 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 22 attended
JC
Joe ChestertonOfficer, expected
RH
Robert HarrisOfficer, in attendance
RM
Councillor Robert McMullanChair, present
MO
Councillor Mandy O'ConnorVice-Chair, present
SA
Councillor Sam AllenCommittee Member, present
JC
Councillor James CourtenayCommittee Member, present
MD
Councillor Meg DavidsonCommittee Member, present
IG
Councillor Ian GilbertCommittee Member, present
JM
Councillor Judith McMahonCommittee Member, apologies
RW
Councillor Ron WoodleyCommittee Member, present
PM
Paula MillsCo-Optee, present
DC
Councillor Daniel CowanCouncillor, expected

All 22 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Internal Audit Service Quarterly Performance ReportThis decision
  2. Internal Audit Service Mandate & Charter, Strategy and 2026/27 PlanApproved
  3. Internal Audit Service Quarterly Performance ReportNoted
  4. Internal Audit Service Quarterly Performance ReportNoted
  5. Head of Internal Audit Annual Report 2024/25Decided
  6. Internal Audit Service Quarterly Performance ReportNoted

More from Southend-on-Sea Audit & Governance Committee

All decisions
MeetingDecisionOutcome
21 Apr 2026 Minutes of the meeting held 20 January 2026That the minutes of the meeting held on 20 January 2026 be confirmed as a correct record. Decided Open
21 Apr 2026 KPMG: External Audit Risks Early Reflections - 2025/26That the KPMG’s External Audit Risks Early Reflections 2025/26 report, be accepted. Reasons for decision: The Council... Decided Open
21 Apr 2026 CIPFA's Financial Management Code Self-Assessment Update ReportThat the Council’s annual review against the expectations of CPIFA’s Financial Management Code, be noted and takes as... Noted Open
21 Apr 2026 Counter Fraud & Investigation Team Quarterly Performance ReportThat the performance of the Counter Fraud & Investigation Team over the last three months, be noted. 2. That the Work... Noted Open
21 Apr 2026 Internal Audit Service Mandate & Charter, Strategy and 2026/27 PlanThat the Internal Audit Mandate and Charter, Strategy and Audit Plan for 2026/27, be approved. Reasons for decision: ... Approved Open