Community Council Highways Capital Investment 2013 - 2014
ApprovedCommittee4 papers
Peckham and Nunhead Community Council approved this item on Monday 30 September 2013. Below is the council's own wording, with the papers it was decided on.
That allocation of community council highways capital investment funding for the following applications be approved: Proposal Amount · Homeleigh Road £19,000 · Lyndhurst Way – Chadwick to Hollydale Road £43,566 · Montpelier Road (West side only) £17, 678 · Denman Road £40,078 · Willowbrook Road £40,000 · Limesford Road £33,989 · Oakdale Road £6,000 · Kelvington Road £36,973 Total: £200,311 Note: £19,920 over budget, officers suggested the Homeleigh Road scheme be dropped. 2. A further report on the highways capital investment funding will be referred to the next meeting to readdress the highways budget and schemes.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Peckham and Nunhead Community Council, 2 pages
Recommendations
1. To agree the works to be funded from the proposed schemes in the Peckham and Nunhead community council area as set out in Appendix 1 of the report.
2. To agree alternative schemes subject to officer investigation and feasibility.
3. As part of the approved Highways Capital Investment programme for 2013 – 2014, each community council receives a proportion of £800,000, as published in Appendix 5 of the Highways Capital Investment programme for 2013 – 2014 dated 20 March 2013. The allocations are in Appendix 3. The Schemes that were approved and delivered in 2012 – 2013 financial year ended 31 March 2013 are presented in Appendix 2 for information.
4. This money can be spent on any asset renewal or replacement project selected by the community council with the caveats that it cannot be spent on traffic safety or parking schemes, non functional or decorative installations and / or non-essential works. In addition to the resurfacing selections provided it, the money (or part thereof) could be spent on minor patching and pothole repairs should a community council wish to do so.
BACKGROUND INFORMATION
5. Peckham and Nunhead community council was allocated £171,430 to be used for its highways surface improvements (carriageway or footway) of their choice. The budget can be spent on any non-principal road on the area. The overall budget available to the community council is £180,391 (£171,430 plus £8,961 of under spend). The overall available funding is set out in paragraph 6 below and in Appendix 1.
6. A report was presented to the community council with officer recommended candidate schemes for consideration as set out in Appendix 1 of this report in June 2013. The community council deferred its decision for further consideration of the roads to be funded.
KEY ISSUES FOR CONSIDERATION
7. Following the community council meeting on 19 June 2013 council officers wrote to all ward councillors and requested alternative ideas or proposals for 2013 – 2014 allocation. Three further proposals have been received and a revised list of recommended schemes is shown in Appendix 1.
8. Original officer recommendations were based on a number of factors, principally asset condition surveys undertaken last year.
9. These recommendations are mainly roads which are not of sufficient priority because of their condition or use to justify use of corporate Non-Principal Road Maintenance funding as per the Highways Capital Investment programme report agreed 20 March 2013. Delivery
10. Once the community council has made their selections by the method of their choice they will be designed and delivered as soon as possible in 2013/14. Any under spends or projected overspends will be reported back to Peckham and Nunhead community council for resolution or reallocation. Depending on the timing of decisions, it may not be possible to complete all works within the financial year. If this is the case the funding will be rolled forward to next financial year and the works completed then.
Community Impact Statement
11. There are no specific community impact issues arising from the recommendations.
BACKGROUND DOCUMENTS
Background Papers Held At Contact Highways Capital 160 Tooley Street Franklin Uwakaneme 0207525 Investment Programme PO Box 64529 2207 or Matthew Hill 020 7525 Decision 20 March 2013 Southwark Council 3541 London SE1P 5LX
Appendices
No. Title Appendix 1 Candidate Schemes for 2013/14 Appendix 2 Summary update of the schemes approved for implementation in 2012/13 for financial year ended 31 March 2013. Appendix 3 Extract from Appendix 5 of the Highways C apital I nvestment programme for 2013/14 - Community Council Investment Allocations
AUDIT TRAIL
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes from the previous meetingThat the minutes be deferred until the next meeting in order to make amendments to the following: Item 7, Allocation ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.