Resolved
That the installation of the cycle hire docking station on Doddington Grove be approved, subject to the outcome of necessary statutory procedures. 7.40pm
Borough, Bankside and Walworth Community Council approved this item on Wednesday 2 October 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
That the installation of the cycle hire docking station on Doddington Grove be approved, subject to the outcome of necessary statutory procedures. 7.40pm
1. That the community council approves the installation of the cycle hire docking station on Doddington Grove, subject to the outcome of necessary statutory procedures
BACKGROUND INFORMATION
2. Part 3H paragraph 16 and 17 of the Southwark Constitution delegates decision making for local non-strategic traffic management matters to the Community Council
3. Boris Johnson, Mayor of London, stated in his manifesto; “I want London to be a genuinely cycle friendly city. I will introduce a central London Cycle Hire scheme, so that Londoners will be able to hire a bike at convenient locations across central London. This will provide a genuinely sustainable alternative to the car and encourage more Londoners to cycle”. TfL has implemented the scheme on behalf of the Mayor.
4. The Mayor recently announced that the Cycle Hire Expansion and Intensification (CHEI) project will provide more docking stations before the end of 2013. He has always seen cycle hire as an expanding programme and has asked TfL to look at ways to expand and improve the scheme in a sustainable way.
5. Cycle Hire has been very successful since its launch in 2010, resulting in over 14 million cycle hires by members and 6 million hires by casual users. There are now over 8,300 cycles within the system that operate from over 580 docking stations across the capital.
6. Phase 3 includes plans to increase the number of Cycle Hire docking stations where Southwark Council is the traffic authority with the general objective of intensifying the density of docking stations within the zone 1 area.
. KEY ISSUES FOR CONSIDERATION
7. The Proposal is for the introduction of 36 new Cycle Hire docking stations on Doddington Grove as outlined at Appendix A. 8. The scheme will not affect the existing controlled parking provisions or waiting/loading restrictions in the area.
9. A public consultation was carried out and no representation was received during the public consultation process.
10. It is noted that all cycle hire locations are subject to planning permission. The site has already been granted planning permission (Planning Reference Number 11-AP- 2748). Nonetheless it requires approval from the Community Council in order to implement the necessary Traffic Management Order.
11. Due to the widening of existing refuge island to accommodate the docking station, adjacent advisory cycle lane on Doddington Grove will be replaced with cycle logos.
Policy Implications
12. The recommendations contained within this report are consistent with the polices of the Transport Plan 2011, particularly:
Policy 1.1 – pursue overall traffic reduction Policy 2.3 – promote and encourage sustainable travel choices in the borough Policy 4.2 – create places that people can enjoy Policy 5.1 – improve safety on our roads and to help make all modes of transport safer
Community impact statement
13. The implementation of any transport project creates a range of community impacts. All transport schemes aim to improve the safety and security of vulnerable groups and support economic development by improving the overall transport system and access to it.
14. This scheme is intended to encourage the use of sustainable modes of transport.
Resource implications
15. The project is wholly funded by Transport for London.
16. Works would be implemented by Transport for London and are expected to be carried out in autumn 2013.
17. Ward members were consulted prior to commencement of the public consultation.
18. Consultation documents for the Cycle Hire Scheme were delivered to 83 residents, mainly on Doddington Grove (see Appendix B).
19. No representations were received to the public consultation.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Doddington Grove Cycle Hire docking station plan & letter to residentsAppendix A | 2 pages | Download |
PDF |
Consultation area (Residents area )Appendix B | 1 pages | Download |
PDF |
Report: Doddington Grove Cycle Hire SchemeReport | 3 pages | DownloadRead as text |
Follow Borough, Bankside and Walworth Community Council at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Feb 2019 | MinutesThat the minutes of the meeting held on 9 July 2018 be agreed as a correct record of the meeting, and signed by the c... | Agreed | Open |
| 9 Feb 2019 | Cleaner Greener Safer: Funding ReallocationThat the reallocation of a total of £61,640 as part of the 2019-20 Cleaner Greener Safer (CGS) programme be approved. | Approved | Open |
| 9 Feb 2019 | Cleaner Greener Safer 2019-20: Capital Funding AllocationThat the following allocations of funds for the 2019-20 Cleaner Greener Safer (CGS) capital programmes in the Borough... | Approved | Open |
| 9 Feb 2019 | Borough, Bankside and Walworth Community Council Highways Capital Investment 2019-2020That the following allocations of funds for the 2019-20 Community Council Highways Capital Investment programmes in t... | Approved | Open |
| 9 Feb 2019 | Allocation of Neighbourhoods Fund 2019-20That the following allocations of funds from Neighbourhoods Fund 2019-20 in the Borough, Bankside and Walworth Commun... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.