Parking changes resulting from the Silwood Phase 4B development
ApprovedCommittee3 papers
Bermondsey and Rotherhithe Community Council approved this item on Wednesday 4 December 2013. Below is the council's own wording, with the papers it was decided on.
That the following local parking amendments, detailed in the appendices to the report, be approved for implementation, subject to the outcome of any necessary statutory procedures: · Silwood Street – The relocation of existing residents’ permit parking bays and introduction of double yellow line waiting restrictions. · Debnams Road – The removal of one short stay bay. The relocation of existing residential permit bays and provision of three additional residential permit bays. The introduction of double yellow lines. · Corbett’s Lane – introduction of double yellow waiting restrictions. · Corbett’s Lane (south) – provision of four new resident permit bays and introduction of yellow line waiting restrictions at the junction with Silwood Street. MEETING BREAK: During the meeting break there was a performance of festive songs sung by the Rotherhithe and Bermondsey Choral Society Choir. 8.55pm
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Bermondsey and Rotherhithe Community Council, 5 pages
Recommendation
1. It is recommended that the following local parking amendments are approved for implementation subject to the outcome of any necessary statutory procedures:
• Silwood Street – relocation of existing residents permit parking bays and introduction of double yellow line waiting restrictions
• Debnams Road – Removal of 1 short stay bay, relocation of existing and provision of 3 additional residential permit bays. Introduction of double yellow line waiting restrictions.
• Corbett’s Lane – introduction of double yellow waiting restrictions.
• Corbett’s Lane (south) – provision of 4 new resident permit bays and introduction of double yellow line waiting restrictions at the junction with Silwood Street
BACKGROUND INFORMATION
3. Silwood street Phase 4B is the last phase in the Silwood Estate redevelopment.
4. The redevelopment of the estate has resulted in highways works to the surrounding roads which have been completed by the Developer at their expense under a S278 Highways Agreement. These highways works have resulted in changes to the parking layout and numbers of spaces.
5. The s106 Agreement for the development requires provision of an additional six on street residential parking spaces. Six properties on Debnams Road will be eligible for residential parking permits.
6. Part 3H of the Southwark Constitution delegates decision making for local non- strategic traffic management matters to the Community Council. KEY ISSUES FOR CONSIDERATION
7. The development was granted planning consent in May 2011 under reference 11-AP/0139 for the demolition of existing buildings and construction of new building providing 127 residential units. Construction works are largely completed on site.
8. 44 private on site parking spaces are being provided as part of the development. An additional 7 on street parking spaces have also been created through works to Denhams Road. Six new houses on Debnams Road will be eligible for one residential parking permit each as outlined in the s106 agreement.
9. This development is located within Controlled Parking Zone N.
Silwood Street
10. Large mature trees used to be located along the western footway of Silwood Street. These created pinch points in the footway and trip hazards and it was agreed at planning that these could be removed and replaced with new planting. As part of the highways works the developer agreed to provide planting beds within the carriageway.
11. A new access to the private off street parking area has been constructed at the southern end of Silwood St and two new dropped kerbs have been constructed to provide access for bin stores located on Silwood Street.
12. These three changes have resulted in alterations to the location of parking bays on the western side of Silwood St. In order to ensure no net loss in parking spaces changes have also been make to maximise the parking layout on the eastern side of Silwood Street.
13. ‘Fire brigade access’ markings exist on Silwood Street on which will be removed and replaced with double yellow lines and parking bays. These markings do not comply with the Traffic Signs Regulations and General Directions order. Auto tracking drawings have been run to confirm that fire tender access is still available to the George Walter Housing Court. The Fire Brigade have been consulted on these changes and have no objections.
Corbett’s Lane
14. Corbett’s Lane is currently subject to single yellow waiting restrictions which are in force for the same time as the CPZ (8am – 6.30pm). Corbett’s Lane previously was a no through road. This now provides access to the off street private car park servicing the development and weekly access for the biomass tanker and refuse collection vehicles.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Bermondsey and Rotherhithe Community Council at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.