That the re-allocation of a total of £57,147 to seven projects be approved one in 2012/2013 Cleaner Greener Safer capital programme and six in the 2014/2015 Cleaner Greener Safer capital programme; and as part of the 2015/2016 programme, as set out in Appendix 1 of the report. 2. That the partial change of scope for project Albert Barnes House sheds / yard project reference [106280], be approved. 3.20 pm
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Borough, Bankside and Walworth Community Council, 6 pages
Recommendations
1. That Borough, Bankside and Walworth Community Council approve the re- allocation of a total of £57,147to seven projects – one in 2012/2013 Cleaner Greener Safer capital programme and six in the 2014/2015 Cleaner Greener Safer capital programme; and as part of the 2015/2016 programme, as set out in Appendix 1.
2. That Borough, Bankside and Walworth Community Council approve the partial change of scope for project Albert Barnes House sheds / yard project reference [106280].
BACKGROUND INFORMATION
3. Cleaner Greener Safer (CGS) is part of the London Borough of Southwark’s capital programme. Between 2003 and 2014, £7,62m has been been made available to local residents in Borough, Bankside and Walworth Community Council area,to apply for awards to make their local area a better place to live. The programme attracts hundreds of proposals ranging from a few hundred pounds for bulb planting to brighten up open spaces to tens of thousands of pounds to create community gardens. These projects often introduce new ideas such as outdoor gyms in public spaces, community gardens, public art and energy saving projects which not only make the borough cleaner, greener and safer but greatly contribute to a sustainable public realm by involving residents in the funding process and in the delivery of projects.
KEY ISSUES FOR CONSIDERATION
4. Appendix 1 highlights10projects which have a total under spend of £57,147.
5. It is recommended that under spend of £4,200 from the GMH dog gym, project reference [106277], is reallocated to projects where additional funding is required.
6. It is recommended that under spend of £1,700 from More table tennis tables in Newington Gardens, project reference [106292], is reallocated to a project where funding is required.
7. It is recommended that under spend of £1,100 from Octavia Hill estate hanging baskets phase 1, project reference [106394], is reallocated to projects where additional funding is required.
8. It is recommended that under spend of £5,200 from Chapter Road improvements, project reference [105450], is reallocated to projects where additional funding is required.
9. It is recommended that under spend of £6,500 from Pelier estate brighter view, project reference [106400], is reallocated to projects where additional funding is required.
10. It is recommended that Walcorde Avenue bin stores, project reference [106030], is cancelled and the funding of £7,000 is reallocated to projects where additional funding is required. The cleansing department would be unable to adopt these stores and regular cleaning and possible future maintenance or repairs would not be carried out.
11. It is recommended that East Walworth conservation area improvement (Wansey Street), project reference [105990], is cancelled and the funding of £10,000 is reallocated to projects where additional funding is required. The cleansing department would be unable to adopt these stores and regular cleaning and possible future maintenance or repairs would not be carried out.
12. It is recommended that Aylesbury Youth Club lighting, project reference [106053], is cancelled and the award of £8000 is reallocated to projects where additional funding is required. The Youth Club building has closed and the funding is no longer required.
13. It is recommended that New Church Road cycle safety, project reference [106402], is cancelled and the award of £8,947 is reallocated to projects where additional funding is required. Since the award, the Parks department has secured separate funding and will undertake the work at this location.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Borough, Bankside and Walworth Community Council at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.