Resolved
That the following scheme be approved for capital funding investment: · Morocco Street carriageway resurfacing £28,160
Bermondsey and Rotherhithe Community Council approved this item on Monday 23 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the following scheme be approved for capital funding investment: · Morocco Street carriageway resurfacing £28,160
1. To agree the funding of the proposed schemes for the Bermondsey and Rotherhithe Community Council set out in Appendix 1.
BACKGROUND INFORMATION
2. The Council’s non-principal road investment programme prioritises works on non- principal roads on a borough-wide basis and this investment forms the largest part of the annual investment programme.
3. In August 2011 and the cabinet member for transport, environment and recycling committed to the provision of an allocation of £100,000 (£800,000 total) to each community council for local investment selections in highways surfacing. This is drawn from and not in addition to the £5.05 million available for 2014/15.
4. Community councils are allocated a devolved fund each year to spend on their own priorities for highway renewal and maintenance that may not be prioritised as part of the borough-wide programme. The financial provision for each community councils is pro-rata by ward, as published in the highways capital Investment programme 2014/15, see Appendix 2 of this report.
5. Bermondsey and Rotherhithe Community Council is allocated £209,525 in 2014/15. On 29 November 2014 Bermondsey and Rotherhithe Community Council agreed an allocation of £170,075 to a number of projects as set out in Appendix 1. Although Grange and Livesey wards chose to defer decision – leaving £37,293 unallocated.
KEY ISSUES FOR CONSIDERATION
6. Officers recommend, following feedback from Grange/Livesey ward councillors, that funds be allocated to Morocco Street carriageway resurfacing. As outlined in Appendix 1, the estimated cost is £28,160. This would leave £9,133 unallocated which can be rolled forward to 2015/16.
Community council selections
7. This money can be spent on any asset renewal or replacement project selected by the community council with the caveats that it cannot be spent on traffic safety or parking schemes, non- functional or decorative installations and / or non-essential works. In addition to the resurfacing selections provided it, the money (or part thereof) could be spent on minor patching and pothole repairs should a community council wish to do so.
Delivery
8. Once the community council has made its selections by the method of its choice they will be designed and delivered as soon as possible in 2015/16. Any under spends or projected overspends will be reported back to community council for resolution or reallocation.
Community impact statement
9. There are no specific community impact issues arising from the recommendations. REASONS FOR LATENESS
10. Feasibility and costing work on councillor recommendations needed to be completed before the report could be finalised. REASONS FOR URGENCY
11. Completion of the allocations will allow the whole programme to be delivered. Long lead in times relating to streetworks permits and materials mean that the remaining scheme in the programme needs to be agreed as soon as possible. The next community council will not take place until late June 2015 and the rest of the programme is awaiting decision on this single scheme.
BACKGROUND DOCUMENTS
Background Papers Held At Contact Highways Capital 160 Tooley Street Himanshu Jansari Investment Programme PO Box 64529 Tel. 020 7525 3291 Decision 12 December 2013 Southwark Council or Matthew Hill London SE1P 5LX Tel. 020 7525 3541 http://moderngov.southwa rk.gov.uk/documents/s430 81/Report.pdf#search=%22 highways%20capital%20inv estment%20programme%2 02014%22
No. Title Appendix 1 Approved schemes list for 2014-15 Appendix 2 Extract from the Highways C apital I nvestment programme for 2014/15 - Community Council Investment Allocations AUDIT TRAIL
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 1 pages | Download |
PDF |
Appendix 2Appendix 2 | 1 pages | Download |
PDF |
Report Highways Capital InvestmentReport | 3 pages | DownloadRead as text |
Follow Bermondsey and Rotherhithe Community Council at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Jun 2018 | MinutesThat the minutes of the meeting held on 21 March 2018 be agreed as a correct record of that meeting. | Agreed | Open |
| 25 Jun 2018 | Cleaner Greener Safer 2018-19: Capital Funding AllocationThat the following allocations of funds for the cleaner greener safer (CGS) capital programme in the Bermondsey and R... | Approved | Open |
| 25 Jun 2018 | Community council highways capital investment 2018-19That the following allocations to projects under the community council highways capital investment programme be appro... | Approved | Open |
| 21 Mar 2018 | MinutesThat the minutes of the meeting held on 10 January 2018 be agreed as a correct record of that meeting. | Agreed | Open |
| 21 Mar 2018 | Cleaner greener safer 2018-19: capital funding allocationThat the following allocations of funds for the cleaner greener safer (CGS) capital programme in the Bermondsey and R... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.