CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Southwark
Bermondsey and Rotherhithe Community Council, Wednesday 27 January 2016 at 7.00pm

Curlew Street - Introduction of a loading bay with time and day restrictions

Deferred Committee 5 papers

Bermondsey and Rotherhithe Community Council deferred this item on Wednesday 27 January 2016. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

That the Curlew Street parking report be deferred due to an error in the report that requires amendment prior to consideration of the item.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Bermondsey and Rotherhithe Community Council, 5 pages

Recommendation

1. It is recommended that the following non-strategic parking arrangements, detailed in the drawings attached to this report, are approved for implementation subject to any necessary statutory procedures:

Curlew Street New loading bay opposite 21-23 • Amend the existing traffic management order to relocate 1 car club bay from Curlew St onto Queen Elizabeth Street. • Relocate four existing permit holder bays approximately 2m further north up Curlew Street • Introduce single yellow lines for a distance of 12m between the permit holder bays and the double yellow lines at the junction. • There would be no net loss in permit holder parking due to the implementation of this scheme

BACKGROUND INFORMATION

2. Part 3H of the Southwark constitution delegates decision making for non- strategic traffic management matters to the community council.

3. Paragraph 15 of Part 3H of the Southwark constitution sets out that the community council will take decisions on the following local non-strategic matters:

• the introduction of single traffic signs • the introduction of short lengths of waiting and loading restrictions • the introduction of road markings • the setting of consultation boundaries for consultation on traffic schemes

4. This report gives recommendations to introduce a section of single yellow line, which will operate in accordance with the controlled parking zone (08:30-18:30), relocate an existing car club bay and alter the operation of two existing on-street parking bays in Curlew Street, near the junction with Queen Elizabeth Street, to set them aside for use .

5. The origin and reasons for the recommendations are discussed within the key issues section of this report. KEY ISSUES FOR CONSIDERATION

6. The proposal made is related to the re-development at Units 13-16, The Circle, Queen Elizabeth Street, which was given planning permission (14/AP/4094) on 6 March 2015.

7. Two parking surveys have been carried out and they both indicate that the peak demand for parking is around the middle of the day.

Parking matters

8. The development is located within Bermondsey G parking zone.

9. Documents submitted with the planning application set limits for the size of vehicle and hours of delivery. These restrictions will be further reinforced by condition 6 of the planning approval, which requires a delivery and servicing management plan to be submitted prior to the site coming into operation.

10. The proposed loading area is to ensure an acceptable form of development and to maintain pedestrian and highway safety in accordance with policy 5.2 and policy 5.3 of the Transport Plan 2011. The loading area is designed to provide safer access for daily deliveries to the re-developed site.

11. Loading in the proposed section of yellow line will be limited to 40 minutes.

Policy implications

12. The recommendations contained within this report are consistent with the policies of the Transport Plan 2011, particularly:

Policy 1.6 – Seek to support loading requirements in CPZ areas.

Community impact statement

13. The policies within the transport plan upheld within this report have been subject to an equality analysis.

14. Limiting loading with regards to length of time will benefit the residents in the vicinity.

15. The recommendations are not considered to have a disproportionate effect on any community or group.

16. The recommendations support the council’s equalities and human rights policies and promote social inclusion by:

• Improving road safety by removing the need for delivery vehicles to load and unload in undesignated areas to make deliveries.

Resource implications

17. All costs arising from implementing the recommendations will be fully met by the developer. Legal implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 6 pages Download
PDF
Appendix 2Appendix 2 1 pages Download
PDF
Appendix 3Appendix 3 1 pages Download
PDF
Appendix 4Appendix 4 6 pages Download
PDF
Report Curlew StreetReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Southwark

Search all
  1. Curlew Street - Introduction of a loading bay with time and day restrictionsThis decision
  2. 29 Curlew Street, London SE1 2NDDecided

More from Southwark Bermondsey and Rotherhithe Community Council

All decisions
MeetingDecisionOutcome
25 Jun 2018 MinutesThat the minutes of the meeting held on 21 March 2018 be agreed as a correct record of that meeting. Agreed Open
25 Jun 2018 Cleaner Greener Safer 2018-19: Capital Funding AllocationThat the following allocations of funds for the cleaner greener safer (CGS) capital programme in the Bermondsey and R... Approved Open
25 Jun 2018 Community council highways capital investment 2018-19That the following allocations to projects under the community council highways capital investment programme be appro... Approved Open
21 Mar 2018 MinutesThat the minutes of the meeting held on 10 January 2018 be agreed as a correct record of that meeting. Agreed Open
21 Mar 2018 Cleaner greener safer 2018-19: capital funding allocationThat the following allocations of funds for the cleaner greener safer (CGS) capital programme in the Bermondsey and R... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies