Local Traffic and Parking Amendments

Approved Committee 6 papers

Bermondsey and Rotherhithe Community Council approved this item on Wednesday 22 June 2016. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

That the following local traffic and parking amendments be approved for implementation, as detailed in the appendices to the report, subject to the outcome of any necessary statutory procedures: · Snowsfields – To install new contraflow cycle infrastructure at the eastern end of Snowsfields (Bermondsey Street junction), and remove existing permit parking bays. · Surrey Quays Road – To install double yellow lines on the southeast side to improve traffic flow and to prevent obstructive parking at any time. · Elephant Lane – To install a single yellow line on the east side adjacent to The Ship public house to provide a loading facility. · Varcoe Road – To install double yellow lines adjacent to No.2 Varcoe Road to provide access at any time. · Bermondsey Street – To convert existing single yellow lines to double yellow lines from No.176 to White Cube Gallery to maintain traffic flow and access at any time. · Garter Way – To install double yellow lines to prevent dangerous parking and maintain traffic flow and access at any time. · Canada Water / Surrey Quays Road – To install a taxi rank in a loading bay on Surrey Quays Road on the southbound approach to Canada Water station. The taxi rank would operate outside of the permitted loading times. · Linsey Street / Alexis Street – To install new ‘no stopping on entrance markings’ on Linsey Street and to remove and install new no stopping on entrance markings in Alexis Street adjacent to St James’ CE Primary School. 2. That the following local traffic and parking amendments be deferred for further discussions to take place prior to a decision: · Rotherhithe Street – reject objections and proceed to install double yellow lines to provide unrestricted access to the entrance of No.135. · Rotherhithe Street – reject objections and proceed to install double yellow lines to provide unrestricted access to the garages at Columbus Court and along Rotherhithe Street between Brunel Road and Clarence Mews. · Snowsfields – reject objections and proceed to convert Snowsfields to one-way working (eastbound) with a cycling contraflow and to formalise the two zebra crossings at the western end of Snowsfields and the northern end of Crosby Row.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Bermondsey and Rotherhithe Community Council, 7 pages

Recommendations

1. It is recommended that the following local traffic and parking amendments, detailed in the appendices to this report, are approved for implementation subject to the outcome of any necessary statutory consultation and procedures:

1.1Snowsfields – to install new contraflow cycle infrastructure at the eastern end of Snowsfields (Bermondsey Street junction), and remove existing permit parking bays.

1.2Surrey Quays Road – To install double yellow lines on the southeast side to improve traffic flow and to prevent obstructive parking at any time.

1.3Elephant Lane – To install a single yellow line on the east side adjacent to The Ship public house to provide a loading facility.

1.4Varcoe Road – To install double yellow lines adjacent to No.2 Varcoe Road to provide access at any time.

1.5Bermondsey Street – To convert exiting single yellow lines to double yellow line from No.176 to White Cube Gallery to maintain traffic flow and access at any time.

1.6Garter Way - To install double yellow lines to prevent dangerous parking and maintain traffic flow and access at any time.

1.7Canada Water / Surrey Quays Road – To install a taxi rank in a loading bay on Surrey Quays Road on the southbound approach to Canada Water station. The taxi rank would operate outside of the permitted loading times.

1.8Linsey Street / Alexis Street - To install new ‘no stopping on entrance markings’ on Linsey Street and to remove and install new no stopping on entrance markings in Alexis Street adjacent to St James’ CE Primary School.

2. It is recommended that the objections received against a non-strategic traffic management order are considered and determined as follows: 2.1 Rotherhithe Street – reject objections and proceed to install double yellow lines to provide unrestricted access to the entrances of No.135.

2.2Rotherhithe Street – reject objections and proceed to install double yellow lines to provide unrestricted access to the garages at Columbus Court and along Rotherhithe Street between Brunel Road and Clarence Mews.

2.3Snowsfields – reject objections and proceed to convert Snowsfields to one- way working (eastbound) with a cycling contraflow and to formalise the two zebra crossings at the western end of Snowsfields and the northern end of Crosby Row.

BACKGROUND INFORMATION

3. Paragraph 15 of Part 3H of the Southwark constitution sets out that the community council will take decisions on the following local non-strategic matters:  the introduction of single traffic signs  the introduction of short lengths of waiting and loading restrictions  the introduction of road markings  the setting of consultation boundaries for consultation on traffic schemes  the introduction of destination disabled parking bays  statutory objections to origin disabled parking bays  determination of objections to traffic management orders that do not relate to strategic or borough-wide issues.

4. This report gives recommendations for local traffic and parking amendments, involving traffic signs, waiting restrictions and road markings and determination of objections to a proposed traffic management order.

5. The origins and reasons for the recommendations are discussed within the key issues section of this report.

KEY ISSUES FOR CONSIDERATION

6. A local parking amendment (LPA) is small project to change an existing parking restriction or to introduce a new one.

7. These tend to be carried out in locations where we have had a request to look at dangerous or obstructive parking and where small lengths of restrictions could provide a solution.

8. Local parking amendments are batched together and carried through a quarterly programme. During the first quarter of 2016-17, the council is proposing eight LPA’s as summarised in figure 1.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 3 pages Download
PDF
Appendix 2Appendix 2 2 pages Download
PDF
Appendix 3Appendix 3 3 pages Download
PDF
Appendix 4Appendix 4 3 pages Download
PDF
Appendix 5Appendix 5 3 pages Download
PDF
Report Local Traffic and Parking AmendmentsReport 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Southwark

Search all
  1. Local Traffic and Parking AmendmentsThis decision
  2. Local traffic and parking amendments: Great Guilford Street - introduction of loading bay, relocation of pay and display baysApproved
  3. Local traffic and parking amendments (Borough wide junction protection project)Approved
  4. Local parking and traffic reportApproved
  5. Local traffic and parking amendmentsApproved
  6. Local Traffic and Parking AmendmentsApproved

More from Southwark Bermondsey and Rotherhithe Community Council

All decisions
MeetingDecisionOutcome
25 Jun 2018 MinutesThat the minutes of the meeting held on 21 March 2018 be agreed as a correct record of that meeting. Agreed Open
25 Jun 2018 Cleaner Greener Safer 2018-19: Capital Funding AllocationThat the following allocations of funds for the cleaner greener safer (CGS) capital programme in the Bermondsey and R... Approved Open
25 Jun 2018 Community council highways capital investment 2018-19That the following allocations to projects under the community council highways capital investment programme be appro... Approved Open
21 Mar 2018 MinutesThat the minutes of the meeting held on 10 January 2018 be agreed as a correct record of that meeting. Agreed Open
21 Mar 2018 Cleaner greener safer 2018-19: capital funding allocationThat the following allocations of funds for the cleaner greener safer (CGS) capital programme in the Bermondsey and R... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies