Controlled Parking Zone (CPZ) studies in Queens Road and Peckham Road south
AgreedCommittee4 papers
Peckham and Nunhead Community Council agreed this item on Wednesday 29 June 2016. Below is the council's own wording, with the papers it was decided on.
That the community council agreed to the proposed consultation boundary and methods to review the parking arrangements: · Within a network of streets to the south of Peckham Road between the existing location of controlled parking zones and to the north of the railway line. · Within a network of streets around Queen’s Road, bounded by Meeting House Lane and Clifton Crescent to the north, Brayards Road to the south, Pomeroy Street and Lausanne Road to the east and the existing zone B CPZ to the west. 2. That the following suggestions were agreed at the meeting: a. That the community council would encourage a faster timetable for the Queens Road consultation, as it seemed unreasonable that the consultation would not happen for another seven or more months. b. That officers should also consider moving Harders Road and Gordon Road into the Queens Road CPZ consultation, as it might be more appropriate in the future than inclusion in the town centre CPZ, which includes restrictions on Saturday. c. That the community council recommend that officers should also consult residents around Nunhead Station about a CPZ for that area as well. 8.40 pm
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Peckham and Nunhead Community Council, 5 pages
Recommendation
1. That the community council comment upon the proposed consultation boundary and methods to review parking arrangements:
within a network of streets to the south of Peckham Road between the existing ‘B’, ‘L’ and ‘LG’ CPZs and to the north of the railway line; and
within a network of streets around Queen’s Road, bounded by Meeting House Lane and Clifton Crescent to the north, Brayards Road to the south, Pomeroy Street and Lausanne Road to the east and the existing Zone ‘B’ CPZ to the west.
BACKGROUND INFORMATION
2. Part 3H of the council’s constitution provides that community councils should be consulted on strategic traffic management matters such as whether to change the times of operation of a parking zone and the related method of consultation.
Peckham Road South area
3. The last parking zone consultation in this area took place in 2012. A new CPZ was rejected at this time. However, the project did result in the implementation of double yellow lines on all road junctions in the study area.
4. Requests for a new CPZ have been raised via local members and directly from residents. Since 2012, we have received 55 individual requests, this includes 27 which have been received between January 2016 – June 2016. There is a social media campaign, via twitter, calling for the introduction of a new CPZ and a petition has been submitted to the council.
5. It should be noted that the study area covers both Camberwell and Peckham and Nunhead community council areas.
6. Further information regarding the proposed Peckham Road south consultation can be found in Appendix 1.
Queen’s Road area
7. The area around Queen’s Road is regularly visited by the council to implement yellow line restrictions to prevent obstructive, inconsiderate and dangerous parking, particularly close to road junctions; this indicates a high level of parking demand. For example, additional parking restrictions have been introduced in recent years into Astbury Road, Kings Grove and Wood Road.
8. The area as a whole was last consulted in 2002, with no resulting CPZ being implemented. A smaller section of streets within the area were consulted more recently in 2010, which resulted in the extension of the existing Zone B CPZ to Gordon’s Road and Harders Road. This has caused some parking displacement to streets to the east of the zone.
Further information regarding the proposed Queen’s Road CPZ consultation can be found in Appendix 2.
KEY ISSUES FOR CONSIDERATION
9. The consultation methods for the CPZ studies are detailed in Appendix 1 for the Peckham Road south area and in Appendix 2 for the Queen’s Road area. Each appendix includes a plan showing proposed the study boundary.
10. Before a final decision is taken, the community council will again be consulted. The procedure is summarised in the table below and full details on the process are contained within Appendix 3.
11. It is intended to stagger the consultations to enable the parking design team to resource and deliver the projects.
Phase Expected dates Expected dates Peckham Road Queens Road Survey & Parking surveys Autumn 2016 Early 2017 consultation Consultation pack and questionnaire to all residents, businesses and stakeholders Public exhibition Decision Draft report to community council Early 2017 Spring 2017 making Final report to Cabinet Member for Environment and the Public Realm Delivery Statutory consultation and Spring 2017 Summer 2017 Implementation
Policy implications
12. The recommendations contained within this report are consistent with the polices of the Transport Plan 2011, particularly
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes from the previous meetingThat the minutes be deferred until the next meeting in order to make amendments to the following: Item 7, Allocation ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.