Audit, Governance and Standards Committee noted this item on Wednesday 14 September 2016. Below is the council's own wording, with the papers it was decided on.
That the progress and future plans of the council’s school building programme 2016-17 be noted. 2. That figures relating to the balance of costs vs. savings incurred due to delays in some schemes that were part of the council’s school building programme be sent to the committee. 3. That figures showing the proportion of Education Funding Agency (EFA) funding compared to that of the council, in relation to the school building programme, be sent to the committee. 4. That cost figures for the two contractors ( Galliford Try and Morgan Sindall ), and details of comparative costs with other school building programmes elsewhere in inner London, be sent to the committee.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Audit, Governance and Standards Committee, 2 pages
SOUTHWARK SCHOOL BUILDING PROGRAMME 2016/17 FACT SHEET
Investment Approx £180m. Funded mainly by EFA capital grant, council capital with Section 106 support and school contributions.
2 new primary school rebuilds (GW2 approved) Albion: redevelopment and regeneration -May 2018 Bellenden: new 2FE on new site –December 2017
8 major primary school expansions for academic years 2016 -2017. (**GW2 approved) Ivydale –June 2017 Grange –September 2017 *Crawford - October 2016 Keyworth – February 2017 *Phoenix – Sept 2016 Robert Browning – May 2017 Charles Dickens – June 2017. (**Awaiting GW2 approval) *Redriff -To be confirmed. (**GW1 required)
2 new free schools *Belham -August 2017 (GW2 approved) *Galleywall (not delivered by the council) September 2016/17
14FE in additional primary school places including works to refurbish existing areas to modern day standards,
Special school New Cherry Gardens School- Sept 2018 (GW2 required Rebuilding of Southwark Inclusive Learning Service (SILS3)- Dec 2019 (GW1 approved) New age 5-16 special school, Southampton Way site. Awaiting DfE decision
Primary School Regeneration schemes *Angel Oak – redevelopment of the site with new housing. SRPP. Cabinet Sept 2017 Potential redevelopment of Rotherhithe School School regeneration and site disposals governed by Secretary State approval under Schedule 1 of the Academies Act and Section 77 regulations (disposal, change of use and playing fields
Secondary *The Charter School East Dulwich. New 8FE school delivered by the council. Sept 2018 Temp opening in Southampton Way premises in September 2016. GW2 November 2016 *Haberdasher Aske’s Borough Academy (not delivered by the council) *St Michael’s Catholic college – 1FE expansion (part funded by the council) –Sept 2017
Planned Maintenance 8 live projects. Repairs about £3m a year to LA schools. (Academies and free schools are funded directly for repairs)
*Academies/free schools Governance and risk management
Capital Programme and Place Planning Board. Chaired by Director of Education with representation from Head of Regeneration, and two Programme Managers, Head of Pupil Access, Head of Standards, School Place Planning Manager Gateway reports to Children’s and Adult Services Board. Decision taker: Strategic Director of Children’s and Adults. Weekly meetings with Employers Agent (Mace). Monthly risk reports. Weekly meetings with QS. Monthly formal site meetings QS valuation meetings Site monitoring meetings as required Clerk of Work’s reports Programme Monitor and monthly updates to Cabinet Members
Consultants Mace. Employers Agent and technical advisers QS advice: Keegans and Rex Proctor for the secondary school Faithful &Gould for planned maintenance Planning and surveys: internal consultancy and external consultants eg right of light, ecology, transport as required
Contractors and procurement Galliford Try and Morgan Sindall for primary school expansion programme, through through iESE programme Other schemes competitively tendered using price and quality, MEAT criteria.
Key project programme risks - mitigation
Rising construction prices and labour shortages- competitive tendering from a wide range of suppliers, secure priced schedule in first stage of two stage tendering, robust commercial approach to procurement. Unknown ground conditions and asbestos etc- detailed surveys prior to procurement Planning risks- careful structured consultation with all stakeholders in stages. Pre app advice sought as schemes develop. Property risks- research on title, party walls, network rail, statutory services etc Programme slippage- structured project management, lessons learnt and forward planning for worst case scenarios. Client changes – progressive sign off designs. EFA and academies impact- forward planning of strategy and Schedule 1 and 77 implications. Avoiding delays in development and funding agreements.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Audit, Governance and Standards Committee at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.