Highways Capital Investment for 2015/16 and 2016/17
AgreedCommittee1 paper
Peckham and Nunhead Community Council agreed this item on Wednesday 21 September 2016. Below is the council's own wording, with the papers it was decided on.
That the following proposed funding schemes from the Highways Capital Investment for 2015/16 and 2016/17 be agreed: Nunhead ward Cost Astbury Road/ Colls Road Footway £19,000 Crewys Road Footway £29,000 Lulworth Road Footway £23,800 Total allocation £71,800 2. That the Highways Capital Investment allocations for local wards: The Lane, Peckham Rye, Peckham and part Livesey will be considered at a future community council meeting. 9.25 pm
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Peckham and Nunhead Community Council, 6 pages
Recommendation
1. To agree the funding of proposed schemes for ward members for Peckham and Nunhead Community Council, as set out in Appendix 1; or to agree alternative schemes subject to officer investigation and feasibility.
BACKGROUND INFORMATION
2. The declining quality of public highway combined with extreme weather events has led to further deterioration in recent years – with some non principal, unclassified roads being particularly affected. Given the nature of these roads and the lower level of traffic flows it is unlikely that such locations will feature in any major resurfacing programme. Without the necessary capital allocation to attend to such locations, complaints of poor road surfaces can only be dealt with through the council’s reactive maintenance programme.
3. The council’s non-principal road investment programme prioritises works on non- principal roads on a borough-wide basis and this investment forms the largest part of the annual investment programme.
4. Since 2011/12, each community council has received devolved funding to implement local priorities that would not be a corporate priority for funding.
5. The financial provision for each community council is pro-rata by ward, as published in Highways Capital Investment Programme 2014/15 dated 12 December 2013 (Appendix 4) and can also be found at: http://moderngov.southwark.gov.uk/documents/s43081/Report.pdf#search=% 22highways%20capital%20investment%20programme%202014%22
6. Peckham and Nunhead Community Council has been allocated £342,860 for highway improvement works (carriageway and footways) of its choice. This is a combined allocation for financial years 2015/16 and 2016/17 and it can be spent on any non- principal road in the area. This is in addition to £49,471 of underspend from previous years giving a total available of £392,331.
7. It is hoped that enough works will be proposed and implemented to fully spend the allocation to bring yearly allocations and works up-to-date. This report contains proposals from Nunhead ward. No proposals received from Livesey, Peckham Rye and The Lane wards. Officers have proposed a scheme in Peckham ward for consideration. KEY ISSUES FOR CONSIDERATION
8. The overall combined two year budget available to Peckham & Nunhead Community Council including underspend from the previous year is £392,331. The total estimate for proposals received so far comes to £158,777 excluding implementation fees as detailed in Appendix 1. Based on the proposals received so far there is a projected unallocated budget of £199,268.
9. The commencement and completion of the schemes within the current financial year will depend upon the decision by the community council, subject to any adverse weather conditions later in the winter months.
Community council selections
10. This money can be spent on any asset renewal or replacement project selected by the community council with the caveats that it cannot be spent on traffic safety or parking schemes, non-functional or decorative installations and / or non-essential works. In addition to the resurfacing selections provided it, the money (or part thereof) could be spent on minor patching and pothole repairs should a community council wish to do so.
Delivery
11. Once the community council has made its selections by the method of its choice they will be designed and delivered as soon as possible in 2016/17. Any under spends or projected overspends will be reported back to community council for resolution or reallocation.
Community impact statement
12. There are no specific community impact issues arising from the recommendations.
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes from the previous meetingThat the minutes be deferred until the next meeting in order to make amendments to the following: Item 7, Allocation ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.