That the work being undertaken across commissioners and providers on winter preparedness be noted. 2. That the messaging to local residents on the use of local services to help ensure that people are informed over which services are available to support them, whatever their health and care needs be noted and approved. 3. That it be noted that winter planning, performance and assurance will be overseen by the newly formed Lambeth and Southwark A&E Delivery Board.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Item No. Classification: Date: Meeting Name: 8. Open 4 October 2016 Health and Wellbeing Board
Report title: Urgent Care Resilience
Ward(s) or groups affected: All
From: Andrew Bland – Chief Officer, Southwark CCG Caroline Gilmartin – Director of Integrated Commissioning, Southwark CCG David Smith – Head of System Performance, Southwark CCG
RECOMMENDATION(S)
1. The board is requested to:
Note the work being undertaken across commissioners and providers on winter preparedness Note and approve the messaging to local residents on the use of local services to help ensure that people are informed over which services are available to support them, whatever their health and care needs Note that winter planning, performance and assurance will be overseen by the newly formed Lambeth and Southwark A&E Delivery Board.
BACKGROUND INFORMATION
2. Winter preparedness is a crucial part of the annual planning cycle. Although attendances at Emergency Departments (EDs) are often lower than during the spring or summer, admissions and levels of acuity tend to be higher. This can lead to bed occupancy levels at acute hospitals rising to at, or near, 100% which can consequently lead to overcrowding of EDs as patients wait for beds to become available prior to being admitted.
3. In addition, winter can often see outbreaks of flu and of norovirus, which causes diarrhea and vomiting. Whilst both viruses can occur at any time of year, they are most common in winter, with special precautions needed to help prevent spread amongst vulnerable groups such as pregnant women and the frail elderly.
4. It is also noted that performance against the 4 hour standard for patients to be assessed, treated, admitted or discharged from EDs has not been consistently met at either St Thomas’ or King’s College Hospital (Denmark Hill) during 16/17. This indicates that the health and care system as a whole is running ‘hot’ and is under sustained pressure. As such, there is an even greater focus that usual on winter preparedness to ensure that corrective measures and performance improvement plans continue to be driven at pace to avoid any further deterioration in quality and performance.
1 KEY ISSUES FOR CONSIDERATION
5. The below outlines some of the key steps that are being taken to prepare for winter:
6. Introduction of A&E Delivery Boards - In line with the national guidance issued by NHS England and NHS Improvement in July to help strengthen financial performance and accountability, partners across SE London are in the process of setting up A&E Delivery Boards. These groups are successors to System Resilience Groups, and bring together senior representatives from across health and social care to help deliver improvement across the urgent and emergency care pathway. In line with our Sustainability and Transformation Plans, there will be a SE London wide group providing overarching strategic oversight, supported by a Lambeth and Southwark A&E Delivery Board which will focus on local delivery. The Lambeth and Southwark A&E Delivery Board will also oversee the disbursement of £4.234m of winter resilience funding to support all system partners (including social care and the voluntary sector) implement a range of winter pressure schemes.
7. Re-specified Urgent Care Centre at Denmark Hill – The Urgent Care Centre (UCC) at Denmark Hill provides treatment for patients with minor illnesses and injuries. Whilst there is general agreement across the local health economy that the UCC has supported more effective management of minors demand, the CCG has sought to revise the specification in order to further ease pressure on the ED and reduce the level of minors’ breaches. Minors’ breaches can number in excess of 100 per week, with particularly high levels in the overnight period, which is considerably higher than other UCCs in London.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.