Community Council Highways Capital Investment for 2015-16 and 2016-17
AgreedCommittee2 papers
Borough, Bankside and Walworth Community Council agreed this item on Wednesday 5 October 2016. Below is the council's own wording, with the papers it was decided on.
That the following schemes outlined in Appendix 1 of the report be agreed: Cathedrals ward Dodson Street – carriageway £23,850 Dodson Street – footway £19,850 Burrell Street – carriageway £24,862 Note: Councillors specified that the above allocations were subject to the costings being confirmed. The funding for Burrell Street is also subject to it being spent on the residential end of the street. Chaucer ward Cole Street – footway £22,870 Cole Street – carriageway £19,578 Bowling Green Place – carriageway £30,891 East Walworth ward Funding decisions deferred awaiting costings from officers. Faraday ward Blackwood Street – carriageway £7,483 Walworth Place – carriageway £17,235 Note: Councillors were minded to allocate funding to Liverpool Grove – footway (in the conservation area only), but are awaiting details about which materials will be used for the repaving. Newington ward Funding decision deferred to allow for the residents’ survey around traffic management and road quality in the Kennington area to be completed.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Borough, Bankside and Walworth Community Council, 7 pages
Recommendation
1. To agree the funding of schemes proposed by ward members for Borough, Bankside and Walworth Community Council as set out in Appendix 1; or to agree alternative schemes subject to officer investigation and feasibility.
BACKGROUND INFORMATION
2. The declining quality of public highway combined with extreme weather events has led to further deterioration in recent years – with some non principal, unclassified roads being particularly affected. Given the nature of these roads and the lower level of traffic flows it is unlikely that such locations will feature in any major resurfacing programme. Without the necessary capital allocation to attend to such locations, complaints of poor road surfaces can only be dealt with through the council’s reactive maintenance programme.
3. The council’s non-principal road investment programme prioritises works on non- principal roads on a borough-wide basis and this investment forms the largest part of the annual investment programme.
4. Since 2011-12, each community council has received devolved funding to implement local priorities that would not be a corporate priority for funding.
5. The financial provision for each community council is pro-rata by ward, as published in Highways Capital Investment Programme 2014-15 dated 12 December 2013 and can also be found at: http://moderngov.southwark.gov.uk/documents/s43081/Report.pdf#search=% 22highways%20capital%20investment%20programme%202014%22
6. Borough, Bankside and Walworth Community Council have been allocated £380,950 for highway improvement works (carriageway and footways) of its choice. This is a combined allocation for financial years 2015-16 and 2016-17 and it can be spent on any non-principal road in the area. This is in addition to £21,270 of underspend from previous years giving a total available of £402,220. It is hoped that enough works will be proposed and implemented to fully spend the allocation to bring yearly allocations and works up-to-date.
7. This report contains proposals from all five wards (Cathedrals, Chaucer, East Walworth, Faraday, & Newington), which are yet to be approved at the forthcoming Borough, Bankside and Walworth meeting. KEY ISSUES FOR CONSIDERATION
8. Following the last Borough, Bankside and Walworth Community Council meeting, officers wrote to all wards to request for outstanding and additional proposals. Refer to Appendix 1 for a summary of the proposals received so far for each ward. These and any other proposal needs to be approved at the forthcoming Borough, Bankside and Walworth Community Council meeting to allow works to start.
9. The overall remaining budget available to Borough, Bankside and Walworth Community Council including underspend from 2014-15 is £402,220, assuming that the Community Council supports all the proposals put forward so far as detailed in Appendix 1. Funds remaining unallocated after this meeting will be allocated to further proposals from ward members and agreed at a future meeting or carried over into the 2017-18 programme for allocation.
10. The commencement and completion of the schemes within the current financial year will depend upon the decision by the community council, subject to any adverse weather conditions later in the winter months.
Community council selections
11. This money can be spent on any asset renewal or replacement project selected by the community council with the caveats that it cannot be spent on traffic safety or parking schemes, non-functional or decorative installations and / or non-essential works. In addition to the resurfacing selections provided it, the money (or part thereof) could be spent on minor patching and pothole repairs should a community council wish to do so.
Delivery
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Borough, Bankside and Walworth Community Council at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.