Peckham and Nunhead Community Council decided this item on Saturday 28 January 2017. Below is the council's own wording, with the papers it was decided on.
That a total of £73,412 be reallocated as part of the 2017/18 cleaner greener safer funding programme set out in Appendix 1 of the report. Also that additional funding be allocated to the following projects: Peckham ward Project Amount (additional funding) 106920 Jowett Street park/ Surrey Canal CCTV £3,000 105869 Bells Gardens Community garden £2,000 1.25 pm
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Peckham and Nunhead Community Council, 7 pages
Recommendation
1. That Peckham and Nunhead Community Council approve the re-allocation of a total of £73,412 to two existing projects and as part of the 2017/2018 programme, as set out in Appendix 1.
BACKGROUND INFORMATION
2. Cleaner Greener Safer (CGS) is part of the London Borough of Southwark’s capital programme. Between 2003 and 2016 £8.7m has been made available local residents in Peckham and Nunhead to apply for awards to make their local area a better place to live. The programme attracts hundreds of proposals ranging from a few hundred pounds for bulb planting to brighten up open spaces to tens of thousands of pounds to create community gardens. These projects often introduce new ideas such as outdoor gyms in public spaces, community gardens, public art and energy saving projects which not only make the borough cleaner, greener and safer but contribute to a sustainable public realm by involving residents in the funding process and in the delivery of projects.
KEY ISSUES FOR CONSIDERATION
3. Appendix 1 highlights seventeen projects which have a total under spend of £65,752.
4. Appendix 1 also details £7,660 funding from the 2016/2017 CGS programme which remains unallocated.
5. It is recommended that the under spend of £10,429 from Solomon's Passage Community Safety and Environmental Improvements, project reference [001431], is returned to community council for reallocation.
6. It is recommended that the under spend of £3,700 from Rowan and Pear Court garden, project reference [106373], is returned to community council for reallocation.
7. It is recommended that the under spend of £2,300 from Lewes House recycling bin area, project reference [106609], is returned to community council for reallocation.
8. It is recommended that Bradfield Club solar energy, project reference [106608], is cancelled and the remaining £23,063 is returned to community council for reallocation. The proposal to install solar panels on the roof of the club will not take the weight of the necessary structure.
9. It is recommended that the under spend of £1,400 from Peckham Square notice board, project reference [106612], is returned to community council for reallocation.
10. It is recommended that the under spend of £2,800 from Honor Oak recreation play ground, project reference [106814], is returned to community council for reallocation.
11. It is recommended that the under spend of £1,700 from Credenhill House staggered gates, project reference [106919], is returned to community council for reallocation.
12. It is recommended that the under spend of £5,560 from Caroline Gardens benches Phase II, project reference [106922], is returned to community council for reallocation.
13. It is recommended that the under spend of £2,300 from Friary Estate football pitch resurfacing, project reference [106924], is returned to community council for reallocation.
14. It is recommended that the under spend of £2,900 from Bells Gardens outdoor gym, project reference [106916], is returned to community council for reallocation.
15. It is recommended that the under spend of £1,500 from Jowett Street lighting, project reference [106923], is returned to community council for reallocation.
16. It is recommended that the under spend of £3,500 from Garnies Close gates and fencing, project reference [106917], is returned to community council for reallocation.
17. It is recommended that the under spend of £1,000 from Honiton lighting, project reference [107040], is returned to community council for reallocation.
18. It is recommended that the under spend of £850 from Light up Clifton Way and Montague, project reference [107065], is returned to community council for reallocation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.