Revised work programme for 2017-18

Noted Finance 1 paper

Audit, Governance and Standards Committee noted this item on Tuesday 9 May 2017. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

That the proposed revised work programme for 2017-18, including planned coverage of governance topics for the year as set out below, be noted: · 2016-17 outturn and budget recovery board – July 2017 · Equalities impacts on the council – September 2017 · Human Resources update - November 2017 · Information Technology update - February 2018. 2. That the work programme for 2017-18 be agreed subject to scheduling of the item ‘Informing the audit risk assessment for the council (including pension fund)’ being permanently amended from May to February each year.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Audit, Governance and Standards Committee, 11 pages

Recommendations

1. That the audit, governance and standards committee consider the proposed revised work programme for 2017-18, including scheduling of governance topics for the year and also whether they would wish to make any other amendments.

2. That the audit, governance and standards committee, subject to any requested changes, agree the work programme set out in Appendix 1 for 2017-18.

BACKGROUND INFORMATION

3. At their meeting on 27 February 2017, the committee considered and agreed a work programme for 2017-18 and requested that various changes be made to the plan, details of which are set out below.

KEY ISSUES FOR CONSIDERATION

4. Members agreed that they would continue to examine particular governance issues by identifying a number of areas for consideration at future meetings.

5. The committee indicated that they would be minded to invite representatives from the IT improvement and shared services boards to a future meeting of the committee, and expressed an interest in hearing from children’s and adults’ services (particularly in relation to learning disability and transitional arrangements) in the future. Members also suggested that IT, modernisation and human resources should continue to be monitored throughout the year and therefore also included in the governance work of the committee for 2017-18.

6. The work programme has been updated to take account of these requests, and the committee is asked to indicate at which meetings they would like to consider each governance topic.

7. A new standing item, budget challenge and governance, has been added to the committee’s work plan; members will receive updates from officers throughout the year on the preparation of the council’s budget for 2018-19.

8. In the interest of efficient use of resources, including officer and councillor time, it was agreed at the February meeting that the appointment of non-voting co-opted members of the civic awards sub-committee for 2017-18 would be undertaken by the committee; the work plan has been amended accordingly. 9. Following the departure of the Head of Anti-Fraud and Internal Audit (who was the council’s designated Chief Audit Executive), the Director of Finance assumed responsibility for these functions on 20 March 2017; the work plan has been updated to reflect this change.

10. As in previous years, there remains a need to ensure flexibility in terms of emerging issues which come to light through items already on the committee’s agenda. For example, reviews of audit recommendations and progress on their implementation may highlight a need to request the attendance of individuals at a future meeting to help explain action taken. The draft programme therefore still includes a standing item relating to review of the committee’s work plan. There may also be a need to review the work programme to take account of any changes which may be agreed to the council’s constitution during the year.

11. Training will continue to be provided for members on the role of the committee, and development needs will continue to be monitored to enable appropriate training to be provided as opportunities arise.

12. The committee is asked to consider whether the attached revised work programme reflects its priorities for the next year or whether there are other amendments which it would wish to see included.

Policy implications

13. This report is not considered to have direct policy implications.

Community impact statement

14. The decision to agree a work programme for next year is considered not to have a significant impact on any particular community or group.

Resource implications

15. There are no direct resource implications in this report.

Consultation

16. There has been no consultation on this report.

SUPPLEMENTARY ADVICE FROM OTHER OFFICERS

17. None required.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Revised work programme for 2017-18Report 11 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 19 attended
PF
Councillor Paul FlemingChair, present
JB
Councillor James BarberVice-Chair, apologies, sent representative
CD
Councillor Catherine DaleCommittee Member, present
ND
Councillor Nick DolezalCommittee Member, apologies due to council business
RH
Councillor Renata HamvasCommittee Member, present
HM
Councillor Hamish McCallumCommittee Member, apologies
AS
Councillor Andy SimmonsCommittee Member, present
DH
Councillor David HubberReserve, present as substitute
CS
Councillor Cleo SoanesReserve, present as substitute
JA
Jo AnsonOfficer, present
JS
Jennifer SeeleyOfficer, present
VF
Victoria ForemanClerk, present

All 19 on the meeting page

On this subject at Southwark

Search all
  1. Revised work programme for 2017-18This decision
  2. Response to the Report of the Housing Scrutiny Commission:The Council's work with social landlord partners; the Fair Street/Devon Mansions, Canada and Kirby Estates QHIP major works projects; the revised resident engagement strategy; and temporary accommodation in properties awaiting demolitionNoted
  3. Report of the Housing Scrutiny Commission: The Council's work with social landlord partners; the Fair Street/Devon Mansions, Canada and Kirby Estates QHIP major works projects; the revised resident engagement strategy; and temporary accommodation in properties awaiting demolitionNoted
  4. Revised work programme for 2016-17Noted

More from Southwark Audit, Governance and Standards Committee

All decisions
MeetingDecisionOutcome
13 Jul 2026 Corporate Anti-Fraud Team and Special Investigations Team Year End Report 2025-26That the audit, governance and standards committee noted the Corporate Anti-Fraud Team (CAFT) and the Special Investi... Noted Open
13 Jul 2026 Southwark360: Six-month progress update on the Enterprise Resource Planning (ERP) Replacement programmeThat the Audit, Governance and Standards Committee noted the six-month progress update on delivery of the Southwark36... Noted Open
13 Jul 2026 External Audit Plan - Southwark Council & Pension FundThat the Audit, Governance and Standards committee: a. Noted the Southwark Council External Audit plan attached at Ap... Noted Open
13 Jul 2026 Internal audit progress report for 2025-26That the audit, governance and standards committee noted the update reports, as attached at Appendix A, including app... Noted Open
13 Jul 2026 Internal Audit - Annual Report & Opinion 2025-26That the audit, governance and standards committee note the update reports, as attached at Appendix A. Noted Open