That planning permission for application number 15/AP/2624 be granted, subject to the conditions set out in the report and addendum report, and with an additional condition stipulating that access to the site be controlled as follows: 1. With a gate at the Howden Street entrance, which is to be kept closed at all times, but allows for appropriate emergency access/egress. 2. With a gate at the Nutbrook Street entrance which is to be open during the hours of operation of the remaining commercial property which are currently conditioned (07:30 to 19:00 Mon to Fri and 07:30 to 13:00 Sat); and closed with an appropriate entry system outside these conditioned hours.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Planning Sub-Committee A (decommissioned, for planning committees after, 38 pages
Recommendation
1. Grant planning permission, subject to conditions.
BACKGROUND INFORMATION
2. The application is reported to Planning Sub-Committee following a referral request by Members.
Site location and description
3. The application site is located to the centre of the residential area bordered by Howden Street, Nutbrook Street, Maxted Road and Waghorn Street. The existing site is occupied by two separate commercial buildings, with a height of one storey. The main building however, has a large parapet surrounding its roof, giving the impression of a building that is 1.5 storeys in height. The site has no direct frontage to the highway, however vehicular and pedestrian access is available through two crossovers, one from each of Nutbrook Street and Howden Street.
4. The site forms part of an existing commercial complex which sits in this backland location surrounded by residential properties on the four roads that border the site. The proposal site forms the eastern side of this rectangular portion of land. The existing commercial buildings to the west, which are within the same ownership but do not form part of the development site, are to be retained. These units are understood to be predominantly used as artist’s studios. The area of the development site is approximately 860m², with a depth of approximately 42.5 metres and a width of approximately 19.5 metres.
5. The residential properties that enclose the proposal site are predominantly two storeys in height, with some of these properties having created a third storey through habitable roof space and dormers. These properties also are characterised by two storey outriggers projecting to the rear of the main wall. Each dwelling also has a rear garden with an average depth of 7 metres.
6. The application site is located within an air quality management area, the urban density zone and the Peckham and Nunhead Action Area. The site is not located within a conservation area, nor is the application site within the setting of any Statutory Listed Buildings.
Details of proposal
7. Planning permission is sought for the demolition of the existing two standalone buildings which are currently within a light industrial (Class B1) use. The proposal involves the creation of a residential scheme (Class C3) consisting of three attached dwellings. The proposed building would be two storey in height, set in approximately 1.8m from the boundaries on Howden St and Nutbrook Street and 8.7m to the rear, approximately 5.5m in height at the eaves and cover the footprint of the existing buildings widthways.
8. The proposed development would result in an increase in height of 1.23m on the boundary shared with Nutbrook Street; however there would be a reduction in depth of the proposed building of 7m, increasing the separation between the 3 x houses and the properties on Waghorn Street.
9. It is proposed to move the existing substation from a location at the bottom of the garden of 26 Howden Street to a new location to the rear of 20 Howden Street. The substation will be constructed in accordance with The Electricity Safety, Quality and Continuity (Amendment) Regulations 2009.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning Sub-Committee A (decommissioned, for planning committees after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.