London Borough of Southwark

Tower Bridge Piazza, Shad Thames, London SE1

Decided Planning 3 papers

Planning Sub-Committee A (decommissioned, for planning committees after decided this item on Saturday 20 May 2023. Below is the council's own wording, with the papers it was decided on.

Item7.1

Resolved

That planning permission for application number 16/AP/0515, as outlined in the report and addendum report, be granted subject to the conditions set out in the report and addendum report, and with: 1. the following additional conditions: a. That the playing of music be prohibited in any external area related to the pavilion building or any A3 use that may commence at 3 & 4 Copper Row. b. That all doors to the pavilion building and for any A3 use that may commence at 3 and 4 Copper Row, be closed after 19:00 except for access and egress or in the case of emergencies. 2. An additional informative, that an appropriate service management plan be submitted to the planning authority which: a. has been put together after appropriate engagement with residents to ensure that amenity is not harmed, including within the piazza itself b. takes into account the specific and distinct characters of the piazza and Shad Thames.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Planning Sub-Committee A (decommissioned, for planning committees after, 21 pages

Recommendation

1. That members grant full planning permission, subject to conditions.

BACKGROUND INFORMATION

2. This application is referred to members for decision.

Site location and description

3. The site includes the Tower Bridge Piazza and the surrounding commercial buildings at ground floor level within the court yard. The piazza is accessed from various points, including Shad Thames and Gainsford Street. The surrounding buildings are a mixture of large office and residential buildings with commercial uses on the ground floors. The piazza was initially consented as landscaping for the surrounding development, however, as is noted within the planning history section below, has consent for a three storey building.

4. No buildings subject to this application are listed however the site is within the Tower Bridge Conservation Area. The site is located within the Central Activities Zone, an Air Quality Management Area, Flood Risk Zone 3 and within an Archaeological Priority Zone.

Details of proposal

5. The proposal is for the change of use of 1a, 2, 3, 4 Admiral's Court and 45, 47, 49 Compass Court to a flexible A1/A2/A3 use; the erection of a single storey pavilion building (A1/A3/D1) within the piazza; erection of a way finding totem outside Cooperage Court, hard and soft landscaping, and associated works.

6. The changes of use proposed seek to provide flexible uses for seven commercial units surrounding the square and the erection of a new pavilion structure located within the square itself which would also result in a flexible use as noted above.

7. The proposal also seeks to provide outdoor seating areas for each of the seven changes of use, outdoor seating for the pavilion use and seating being re-provided around the refurbished Anthony Donaldson Statue which would be retained.

8. Wider landscaping works to the square are also proposed including planting and the introduction of a totem 'way finding portal' to advertise the location of the Cooperage Offices.

9. During the course of the application, additional information was submitted in relation to servicing, ventilation, lighting, heritage and further details in relation to the existing uses within the site. The application has been amended since its initial submission in order to remove the originally proposed way-finding portal, in favour of the smaller totem. Following discussions with officers, the proposal to fill the arches within the Eagle Wharf building along Lafone Street was removed from the proposal.

10. Planning history

15/EQ/0226 Application type: Pre-Application Enquiry (ENQ) - Alterations and refurbishment works to Tower Bridge Piazza and surrounding retail units at Compass Court. Decision date 02/02/2016 Decision: Pre-application enquiry closed (EQC) .

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
RecommendationAppendix 4 4 pages Download
PDF
Report: Tower Bridge Piazza, Shad Thames, London SE1Report 21 pages DownloadRead as text
PDF
Site plan: Tower Bridge Piazza, Shad Thames, London SE1Plan 1 pages Download

At this meeting

Whole meeting

Who was there

6 of 10 attended
LP
Councillor Leo PollakChair, apologies
BJ
Councillor Ben JohnsonVice-Chair, present
RB
Councillor Radha BurgessCommittee Member, present
JC
Councillor James ColdwellCommittee Member, present
HD
Councillor Helen DennisCommittee Member, present
ND
Councillor Nick DolezalCommittee Member, present
DN
Councillor David NoakesCommittee Member, apologies
SK
Councillor Sarah KingReserve, present as substitute
GG
Gerald GohlerSecretary, expected
CA
Chidilim AgadaSecretary, expected

On this subject at Southwark

Search all
  1. Tower Bridge Piazza, Shad Thames, London SE1This decision
  2. 82 Tower Bridge Road, London SE1 4TPRefused
  3. Tower Bridge Piazza, Shad Thames, London SE1Decided

More from Southwark Planning Sub-Committee A (decommissioned, for planning committees after

All decisions
MeetingDecisionOutcome
20 May 2023 Introduction and welcomeThat Councillor Nick Dolezal chair the meeting. The chair welcomed councillors , members of the public and officers t... Decided Open
20 May 2023 Items of business that the Chair deems urgentThat the determination of planning applications, or formal observations and comments, the instigation of enforcement ... Agreed Open
20 May 2023 MinutesThat the minutes of the meeting held on the 3 October 2017 be approved as a correct record and signed by the chair. Approved Open
20 May 2023 MinutesThat the minutes of the meeting held on 9 May 2017 be approved as a correct record and signed by the chair. Approved Open
20 May 2023 MinutesThat the minutes of the meeting held on 18 July 2017 be approved as a correct record and signed by the chair. Approved Open