Resolved
That planning permission for application number 17-AP-0234 be granted subject to the conditions outlined in the report.
Planning Sub-Committee B (decommissioned, for planning committees after decided this item on Saturday 20 May 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
That planning permission for application number 17-AP-0234 be granted subject to the conditions outlined in the report.
APPENDIX 3
RECOMMENDATION This document shows the case officer's recommended decision for the application referred to below. This document is not a decision notice for this application.
Applicant [name removed]. Number 17/AP/0234 Friends of Russia Dock Woodlands Application Type Full Planning Application Recommendation Grant permission Case TP/417-A Number Draft of Decision Notice
Planning Permission was GRANTED for the following development: Construction of a community rain shelter in Russia Dock Woodland
At: RUSSIA DOCK WOODLAND, DOWNTOWN ROAD, ROTHERHITHE, LONDON SE16 6QN
In accordance with application received on 06/01/2017
and Applicant's Drawing Nos. Site location plan, 1623-01, 1623-02, 1623-03, Documents setting out funding confirmation for the Cleaner Greener Safer project.
Subject to the following four conditions:
Time limit for implementing this permission and the approved plans
1 The development hereby permitted shall not be carried out otherwise than in accordance with the following approved plans:
1623-01/Rev0, 1623-02/Rev0, 1623-03/Rev0
Reason: For the avoidance of doubt and in the interests of proper planning.
2 The development hereby permitted shall be begun before the end of three years from the date of this permission.
Reason As required by Section 91 of the Town and Country Planning Act 1990 as amended.
Commencement of works above grade - the details required to be submitted for approval by the condition(s) listed below must be submitted to and approved by the council before any work above grade is commenced. The term 'above grade' here means any works above ground level.
3 Before any above grade work hereby authorised begins, details of the biodiversity green roof shall be submitted to and approved in writing by the Local Planning Authority. The biodiversity green roof shall be:
biodiversity based with extensive substrate base (depth 80-150mm); laid out in accordance with agreed plans; and planted/seeded with an agreed mix of species within the first planting season following the practical completion of the building works (focused on wildflower planting, and no more than a maximum of 25% sedum coverage).
The biodiversity roof shall be installed strictly in accordance with the details so approved and shall be maintained as such thereafter.
Discharge of this condition will be granted on receiving the details of the green roof and Southwark Council agreeing the submitted plans, and once the green roof is completed in full in accordance to the agreed plans. A post completion assessment will be required to confirm the roof has been constructed to the agreed specification.
Reason: To ensure the development provides the maximum possible provision towards creation of habitats and valuable areas for biodiversity in accordance with policies: 2.18, 5.3, 5.10, and 511 of the London Plan 2011, saved policy 3.28 of the Southwark Plan and Strategic Policy 11 of the Southwark Core strategy. Compliance condition(s) - the following condition(s) impose restrictions and/or other requirements that must be complied with at all times once the permission has been implemented.
4 The materials to be used in the implementation of this permission shall not be otherwise than as described and specified in the application and on the drawings hereby approved unless the prior written consent of the local planning authority has been obtained for any proposed change or variation.
Reason To ensure that the new works blend in with the existing building in the interest of the design and appearance of the building in accordance with The National Planning Policy Framework 2012, Strategic Policy 12 - Design and Conservation of The Core Strategy 2011 and Saved Policies 3.12 Quality in Design and 3.13 Urban Design of the Southwark Plan 2007
Statement of positive and proactive action in dealing with the application
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 2: Recommendation (17AP0234)Report | 2 pages | DownloadRead as text |
PDF |
Item 2: Report (17AP0234)Report | 7 pages | Download |
PDF |
Item 2: Site plan (17AP0234)Plan | 1 pages | Download |
Follow Planning Sub-Committee B (decommissioned, for planning committees after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 May 2023 | MinutesThat the minutes of the meeting held on the 10 March 2015 be approved as a correct record and signed by the chair | Approved | Open |
| 20 May 2023 | Items of business that the Chair deems urgentThat the determination of planning applications, or formal observations and comments, the instigation of enforcement ... | Decided | Open |
| 20 May 2023 | MinutesThat the minutes of the meeting held on the 13 December 2017 be approved as a correct record and signed by the chair. | Approved | Open |
| 20 May 2023 | MinutesThat the minutes of the meeting held on the 11 September 2017 be approved as a correct record and signed by the chair. | Approved | Open |
| 20 May 2023 | MinutesThat the minutes of the meeting held on 31 October 2017 be approved as a correct record and signed by the chair. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.