Audit, Governance and Standards Committee, Monday 5 February 2024 at 6.30pm

Southwark Construction - Retrospective contract variations

Noted Finance 1 paper

Audit, Governance and Standards Committee noted this item on Monday 5 February 2024. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

That the Audit, Governance and Standards Committee noted that the current governance process that is in place is not wholly aligned to the construction routes being undertaken, nor are they aligned to the current construction contracts which are the overriding legal context to which the council (the employer) needs to adhere to with the Contractor. Thus the Audit, Governance and Standards Committee noted that Southwark Construction has sought to exercise contract standing orders clause 6.7 to confirm additional costs, following their initial approvals as per the relevant JCT building contract, so as not to unduly delay the works on site and risk incurring additional costs as a result. 2. That the Audit, Governance and Standards Committee noted the actions taken by the Southwark Construction as set out in paragraphs 20-22 of the report to review and enhance the operational and governance arrangements for new build projects to mitigate against the risk of incurring additional unforeseen costs within their building programme in the future. 3. That the Audit, Governance and Standards Committee noted that Southwark Construction will move to a centrally managed contingency fund that covers all programme schemes, or sectional part thereof, such that localised spend is prevented and, instead, a more stringent route to managing contingency spend is established. This is likely to incorporate higher levels of control whereby the Managing Director of Southwark Construction will need to satisfy themselves that any additional call for expenditure has been thoroughly checked and tested with a view to cost prevention and only when that has been exhausted that a recommendation for use of the global contingency may be passed to the Strategic Director for final approvals. An expenditure monitoring tool will be established accordingly.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Audit, Governance and Standards Committee, 13 pages

Recommendations

1. That the Audit, Governance and Standards Committee note that the current governance process that is in place is not wholly aligned to the construction routes being undertaken nor are they aligned to the current construction contracts which are the overriding legal context to which the council (the employer) needs to adhere to with the Contractor. Thus the Audit, Governance and Standards Committee note that Southwark Construction has sought to exercise contract standing orders clause 6.7 to confirm additional costs, following their initial approvals as per the relevant JCT building contract, so as not to unduly delay the works on site and risk incurring additional costs as a result.

2. That the Audit, Governance and Standards Committee note the actions taken by the Southwark Construction as set out in paragraphs 20-22 to review and enhance the operational and governance arrangements for new build projects to mitigate against the risk of incurring additional unforeseen costs within their building programme in the future.

3. That the Audit, Governance and Standards Committee note that Southwark Construction will move to a centrally managed contingency fund that covers all programme schemes, or sectional part thereof, such that localised spend is prevented and, instead, a more stringent route to managing contingency spend is established. This is likely to incorporate higher levels of control whereby the Managing Director of Southwark Construction will need to satisfy themselves that any additional call for expenditure has been thoroughly checked and tested with a view to cost prevention and only when that has been exhausted that a recommendation for use of the global contingency may be passed to the Strategic Director for final approvals. An expenditure monitoring tool will be established accordingly.

1 BACKGROUND INFORMATION

4. As part of the Council’s strategy to deliver 11,000 new homes by 2043, Southwark entered into JCT Design and Build Contracts to deliver on the Corporate Delivery Plan target to achieve 2,500 new homes on site by May 2022, one of the most ambitious programmes of any local authority.

5. Since August 2018 this has meant there have been between 30-50 live schemes on site at any given time and a total investment programme of £1,792m over 15 years to seek to meet local housing need. To date the programme has delivered 1,516 homes, which includes 1,401 social rent homes and 115 intermediate rent, benefited from £254.8m grant funding as well significant investment in wider community benefits.

6. The procurement of contractors to deliver new homes adheres to the council governance procedures through gateways and approvals in line with the Housing Scheme of Management. In addition, the programme has a range of monitoring and programme governance to ensure effective management. This report is required to comply with CSO 6.7.1 in relation to retrospective approvals whereby an approval to a contract variation was not sought at the time and has an estimated value of more than £100,000.

7. This report sets out the circumstances and manner in which the decision was taken and sets out a number of considerations for the purpose of obtaining guidance to inform future decision making. In summary, the reasons for contract variations sought retrospectively are;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Southwark Construction: Retrospective Approval ReportReport 13 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Southwark

Search all
  1. Southwark Construction - Retrospective contract variationsThis decision
  2. Southwark Construction New Homes UpdateNoted

More from Southwark Audit, Governance and Standards Committee

All decisions
MeetingDecisionOutcome
13 Jul 2026 Corporate Anti-Fraud Team and Special Investigations Team Year End Report 2025-26That the audit, governance and standards committee noted the Corporate Anti-Fraud Team (CAFT) and the Special Investi... Noted Open
13 Jul 2026 Southwark360: Six-month progress update on the Enterprise Resource Planning (ERP) Replacement programmeThat the Audit, Governance and Standards Committee noted the six-month progress update on delivery of the Southwark36... Noted Open
13 Jul 2026 External Audit Plan - Southwark Council & Pension FundThat the Audit, Governance and Standards committee: a. Noted the Southwark Council External Audit plan attached at Ap... Noted Open
13 Jul 2026 Internal audit progress report for 2025-26That the audit, governance and standards committee noted the update reports, as attached at Appendix A, including app... Noted Open
13 Jul 2026 Internal Audit - Annual Report & Opinion 2025-26That the audit, governance and standards committee note the update reports, as attached at Appendix A. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies