London Councils Grants Scheme 2011/12

Noted Executive 3 papers

AI summaryCabinet agreed a £485,614 grants levy, subject to February 2011 budget proposals, and directed officers to keep exploring commissioned services. [D] [P2] [P3]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBudget proposals go to the Council Assembly in February 2011. [D] [P2]
Money£485,614 proposed levySouthwark's 2011/12 contribution, subject to budget proposals. [D] [P2] [P31]
What happens nextBudget and service decisionsSubmit budgets and explore commissioned service options. [D] [P2] [P3]
Who it affectsFunded organisations and residentsAlmost 200 funded organisations have Southwark beneficiaries. [P43]

What was decided

Cabinet noted the issues arising from the London Councils Grants Review. Report P1

Cabinet agreed the proposed levy of £485,614, subject to budget proposals going to the Council Assembly in February 2011. Report P2

Cabinet agreed that officers would continue exploring whether commissioned services should continue or stop, with relevant boroughs and London Councils. Report P3

Why

The scheme was created after the Greater London Council was abolished to maintain support for voluntary organisations serving at least two boroughs. Report P5

Devolution of powers and pressure on public finances prompted the review, with aims to repatriate funds or reduce the levy. Report P10

The managed transition allowed more time to establish arrangements, gave boroughs flexibility and limited binding financial commitments to the statutory scheme. Report P29

What happens next

Submit budget proposals to the Council Assembly in February 2011 and provide a formal response ideally by Friday 21 January 2011 and no later than 31 January 2011. Report P2, P40

Continue exploring continuation or discontinuation of commissioned services with relevant boroughs and London Councils. Report P3

Decide which Category B and C services to terminate or continue and how continuing commissions should be managed; complete full equalities impact assessments before terminating funding. Report P41, P46, P75

The money

  • £485,614 Southwark's proposed levy for 2011/12. Report P31, P62
  • £475,007 Reduction from the 2010/2011 levy. Report P31
  • £960,621 Southwark's 2010/11 contribution. Report P31, P61
  • £17,691,000 Overall proposed expenditure, including £838,000 administrative expenditure. Report P32, P34
  • £16,793,000 Grants within the proposed expenditure. Report P33
  • £13.175 million Continuing funding for Category A pan London services. Report P33
  • £3.16 million Three months of transition funding for Category B and C services. Report P33
  • £118k Prudent savings estimate included in the budget process. Report P78

Options considered

  • Rejected: Option 1. This would decommission Category B and C services from 1 April 2011, release the most resources and cause the most disruption, with risks of legal challenge. Report P24
  • Rejected: Option 2. This would let all Category B and C services run their full course, reduce disruption, but slow the transfer of decisions to boroughs and limit budget change in 2011/12. Report P25
  • Chosen: Option 3. Boroughs would choose services commission by commission, while London Councils could manage existing commissions in relevant boroughs. Funding would be agreed borough by borough outside the scope of section 48. Report P26, P27

Implications

  • Financial: The levy reduction is £475,007, and total borough contributions fall by 49.7%. Report P31
  • Financial: Without two thirds approval before 1 February 2011, expenditure stays at the previous year's approved level. Report P40, P69
  • Financial: A prudent 25% savings estimate across years one and two has put £118k into the budget process, subject to review. Report P78
  • Legal: Under section 48, Southwark is bound to contribute and cannot withdraw unilaterally. Report P67, P70
  • Legal: Funding agreements may have contractual force, but ongoing grants depend on adequate funding. Report P50, P51, P52
  • Equalities: Full equalities impact assessments must be completed before any decision to terminate funding. Report P46, P75
  • Equalities: Discontinuing services could significantly affect Southwark's deprived and vulnerable communities. Report P46
  • Risk: Early termination could harm organisations' sustainability and result in lost match or other funding. Report P45

Who and where

  • Southwark residents benefiting from funded services Report P57
  • Almost 200 voluntary sector organisations with Southwark beneficiaries Report P43
  • Southwark based London Councils funded organisations Report P57, P81
  • Other London boroughs involved in commissioning decisions Report P41, P47
  • Constituent councils contributing to and approving the scheme Report P68, P69
  • Southwark's deprived and vulnerable communities Report P46
  • Southwark Law Centre; Southwark Citizens Advice Bureaux Service; Southwark Refugee Project Limited; Age Concern London; Homeless Link; Victim Support Report P58

Timeline

  • 8 June 2010: The grants scheme review was announced at the London Councils Annual General Meeting. Report P10
  • 14 December 2010: Leaders Committee approved Option 3, a managed transition. Report P27
  • 12 January 2011: The final version of the report was dated. Report P84
  • Friday 21 January 2011: Ideal deadline for boroughs' formal response to the recommendation. Report P40
  • 31 January 2011: Latest date for boroughs' formal response. Report P40
  • February 2011: Budget proposals are to go to the Council Assembly. Report P2
  • before 1 February 2011: Two thirds of constituent councils must agree the expenditure budget. Report P40, P69
  • 30 June 2011: All commissions continue while boroughs agree their own options. Report P28

Plain English for the jargon

  • London Councils Grants Scheme: Support for voluntary organisations serving at least two boroughs. [P5]
  • Levy: Southwark's population based contribution to the scheme. [P31] [P68]
  • Category A: London wide services, third sector support, or a London wide sector voice. [P16] [P18]
  • Category B: Sub regional services delivered across more than one London borough. [P19] [P20]
  • Category C: Local services delivered within a single London borough. [P21] [P22]
  • Managed transition: Boroughs choose commissions; London Councils manages them temporarily. [P26] [P27]
  • Constituent councils: London borough councils that contribute to and approve the scheme. [P68] [P69]
  • Section 48: The Local Government Act 1985 provision governing the scheme. [P48] [P67]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

That the issues arising from the London Councils Grants Review be noted. 2. That the proposed levy of £485,614 be agreed subject to the budget proposals to be submitted to the council assembly in February 2011. 3. That officers continue to explore the options for continuation/discontinuation of commissioned services in consultation with relevant boroughs and London Councils. (Attached to the report as appendix 1 is a list of Southwark based London Councils funded organisations and appendix 2, a list of organisations with beneficiaries in Southwark.)
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 10 pages

Recommendations

4. That the Cabinet note the issues arising from the London Councils Grants Review

5. That the Cabinet agree the proposed levy of £485,614 subject to the budget proposals to be submitted to the Council Assembly in February 2011.

6. That the Cabinet agree that officers continue to explore the options for continuation/discontinuation of commissioned services in consultation with relevant boroughs and London Councils. Attached as Appendix 1 is a list of Southwark based London Councils funded organisations and Appendix 2 is a list of organisations with beneficiaries in Southwark.

BACKGROUND INFORMATION

7. The London Council Grants Scheme was created following the abolition of the Greater London Council as a means of maintaining support to voluntary organisations providing London-wide services. Organisations supported by the scheme are required to provide services across at least two London boroughs in order to qualify for support.

1 8. Since the first grants commenced in April 1986, the funding provided by the Scheme has addressed a range of social issues such as discrimination, domestic violence, homelessness and creating opportunities for all those living in London.

9. The Scheme was reviewed in 2005 as a consequence of concerns in many boroughs that, whilst accepting that benefits should be targeted on need, the actual benefits were not distributed across London in proportion to those needs. That review resulted in a complete change in approach of the Scheme and adoption of revised themes.

10. London Councils Leaders’ Committee agreed the revised funding priorities in November 2006 based upon 12 broad themes and an annual budget of £26.4 million for each of the four years starting in 2007/8. The first funding decisions under the revised scheme were taken in spring 2007, and the final funding decisions were taken in late 2008; these have four-year end dates ranging from July 2011 to March 2013.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
London Councils Grants Scheme Southwark based orgs funded by London councilsAppendix 1 2 pages Download
PDF
London Council's Grants SchemeAppendix 2 5 pages Download
PDF
Report: London Council Grants Scheme 2011-2012Report 10 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
JF
Councillor John FriaryCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
AM
Councillor Abdul MohamedCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
AS
Annie ShepperdOfficer, expected
DC
Deborah CollinsOfficer, expected

On this subject at Southwark

Search all
  1. London Councils Grants Scheme 2011/12This decision
  2. London Councils Grants Scheme 2012/13Approved
  3. London Councils Grants Scheme 2013/14Approved
  4. London Councils Grants Scheme 2015-2016Approved
  5. London Councils Grants Scheme 2016/17Approved

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies