CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Public Question Time (15 Minutes)

Agreed Executive

AI summarySouthwark Cabinet answered a question on Elephant & Castle governance, confirming a joint management board and planning a public Regeneration Forum for the end of May. [D]

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeAgreedCabinet answered on governance and public involvement. [D]
MoneyNot stated
What happens nextLaunch Regeneration Forum [D]Launch: end of May. Talks: 3 May. [D]
Who it affectsElephant & Castle community [D]Local groups would receive launch invitations. [D]

What was decided

Cabinet agreed that the responses would be recorded in the minutes and provided to the questioners. [D]

The answer confirmed that a strategic management board of senior council and Lend Lease officers had been fully operational since the summer 2010 agreement was signed. [D]

The answer set out a proposed Regeneration Forum to involve the wider public and community in consultation. [D]

Why

The steering group was proposed to review project progress and provide a public forum for discussion and debate about the regeneration and its impact on the wider community. [D]

A feedback mechanism would raise and discuss the steering group's views with the management board. [D]

The aim was to ensure the views and opinions of all interested parties were considered throughout the development of the project. [D]

What happens next

Lend Lease representatives and council officers were to attend Walworth and Borough & Bankside Community council meetings on 3 May to discuss the forum launch. [D]

The Regeneration Forum was planned for launch at the end of May. [D]

Invitations to the launch event were to be issued in early May to groups within the area. [D]

Implications

  • Governance: Senior council and Lend Lease officers share strategic oversight through the board, and officers report project progress to Cabinet. [D]
  • Other: The proposed steering group was intended to provide feedback and a public forum for project progress and debate. [D]
  • Governance: The steering group's views would be discussed with the management board so interested parties' views could be considered. [D]
  • Other: The proposed Regeneration Forum would broaden consultation to the wider public and community. [D]

Who and where

  • The wider public and community
  • Groups within the area
  • All interested parties in the project
  • Lend Lease representatives and council officers
  • Cabinet

Timeline

  • 2026-05-28: Cabinet agreed to minute the responses and provide them to the questioners. [D]
  • summer 2010: The regeneration agreement with Lend Lease was signed, including governance arrangements for the strategic management board. [D]
  • early May: Invitations to the launch event were due to be issued to groups within the area. [D]
  • 3 May: Lend Lease representatives and council officers were to attend two Community council meetings to discuss the launch. [D]
  • end of May: The Regeneration Forum was planned to launch. [D]

Plain English for the jargon

  • Regeneration agreement: Agreement with Lend Lease signed in summer 2010, including governance arrangements. [D]
  • Strategic management board: Board of senior council and Lend Lease officers, fully operational since the agreement was signed. [D]
  • Steering group: Proposed feedback group for reviewing progress and public discussion. [D]
  • Regeneration Forum: Proposed forum for wider public and community involvement in consultation. [D]
  • Master regeneration plan: Plan whose consultation strategy proposed the steering group. [D]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

It was agreed that the responses would be recorded in the minutes and provided to the questioners. Public question from Luke Miller, Elephant Amenity Network “Major changes to the Elephant & Castle regeneration/shopping centre were announced informally in April. When will the reference group for Elephant & Castle be established and what are the governance mechanisms for decision making and public involvement now and once the reference group has been established?" Answer of the Cabinet Member for Regeneration and Corporate Strategy: When the regeneration agreement with Lend Lease was signed in summer 2010, the governance arrangements included a strategic management board made up of senior officers from the council and Lend Lease. This board has been fully operational since the regeneration agreement was signed and officers report progress to cabinet. In addition, as part of the consultation strategy within the master regeneration plan a steering group was proposed. The aim of setting up the steering group was to put in place an appropriate feedback mechanism to review progress of the project and provide a public forum for discussion and debate in respect of the regeneration and its impact on the wider community. Similarly, a feedback mechanism will be put in place to ensure that the views of the steering group are raised and discussed with the management board in order to ensure that the views and opinions of all interested parties are considered throughout the development of the project. The proposed regeneration forum expands on the concept of a steering group to more fully involve the wider public and community in the consultation process. Representatives of Lend Lease along with council officers will be attending Walworth and Borough & Bankside Community council meetings on 3 May to talk about the launch of the Regeneration Forum which is planned for the end of May. Invitations to attend this event will be issued in early May to groups within the area and there will be information about it on ... view the full minutes text for item 4.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

Who was there

9 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
AM
Councillor Abdul MohamedCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
AS
Annie ShepperdOfficer, expected
DC
Deborah CollinsOfficer, expected

On this subject at Southwark

Search all
  1. Public Question Time (15 Minutes)This decision
  2. Public Question Time (15 Minutes)Agreed
  3. Public question timeDecided
  4. Public Question TimeDecided

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies