AI summaryLondon Borough of Southwark Cabinet approved £62,500 for Creation Trust’s 2011/12 Business Plan and up to £937,500 in quarterly tranches, subject to a 4 year funding agreement [D]. The finance cabinet member will agree the agreement within the paragraph 19 principles [D].
Written from the decision and the officer reportPDF Pro
OutcomeApproved2011/12 Business Plan payment and 4 year agreement [D]
Money£62,500 plus up to £937,500 [D]Quarterly payments subject to a 4 year agreement [D]
What happens nextSign 4 year agreement [P25]Target: prior to 30 June 2011 [P25]
Who it affectsCreation Trust and residents [P30]Aylesbury Estate regeneration and community services [P30] [P16]
What was decided
Cabinet approved a £62,500 grant payment to New Aylesbury Trust Ltd. “Creation Trust”, based on Creation Trust’s Business Plan for 2011/12 [D].
Cabinet approved grant funding of up to a maximum of £937,500, paid in quarterly tranches of £62,500, subject to a 4 year funding agreement [D].
Responsibility for agreeing the 4 year funding agreement was delegated to the Cabinet Member for Finance, Resources and Community Safety [D]. The agreement must follow the principles in paragraph 19 [D].
Why
Officers found the 2011/12 business plan significantly stronger than the 2010/11 plan, with more robust financial projections [P20] [P21]. Report P20, P21
The plan commits to added value, tighter project selection and monitoring, better value for money and additional funding sources [P21]. Report P21
Regeneration of the Aylesbury Estate is a key council priority, and the funding agreement supports delivery of the council’s vision for the area [P42]. Report P42
What happens next
The council would seek to enter into the 4 year funding agreement prior to 30 June 2011 [P25]. Report P25
Further quarterly payments require a signed agreement, satisfactory performance and the general conditions [P34]. The Cabinet Member must separately agree payments beyond the initial £62,500 [P43]. Report P34, P43
A separate future report will address the financial implications of the Trust’s permanent location [P46]. Report P46
The money
£62,500 Initial grant payment based on the 2011/12 Business Plan Report P23
up to a maximum of £937,500 Further grant funding over the 4 year agreement, in quarterly tranches of £62,500 Report P27
up to £250,000 per annum Grant income for four years from financial year 2011/12 Report P32
£1,000,000 Four year grant income total from financial year 2011/12 Report P32
£250,000 Already paid in financial year 2010/11 Report P12, P32
£1,250,000 Maximum total from financial year 2010/11 under the earlier in principle recommendation Report P32
up to £18 million Historic capital funding for leaseholder buy outs and Burgess Park improvements Report P8, P9
£1.25 million Historic revenue support commitment to Creation Trust Report P9
Options considered
Chosen: Approve the £62,500 payment for the 2011/12 Business Plan. Officers found the plan stronger, with more robust financial projections and tighter project monitoring. Report P20, P21
Chosen: Approve up to £937,500 in quarterly tranches. The 4 year agreement provides a funding mechanism up to 2015, with annual reporting, action plans and sanctions. Report P26, P28
Chosen: Delegate agreement of the 4 year funding agreement. Delegation allows further payments after the Cabinet Member separately agrees them. Report P41, P43
Implications
Financial: The business plan relies on council grants of up to £250,000 per annum for four years [P32]. Budget provision covers the first £62,500, while the remaining £937,500 depends on a signed agreement, satisfactory performance and general conditions [P34]. Report P32, P34
Risk: Poor performance can lead to payment being withheld, recovery of grant funding and termination of property leases [P28]. Report P28
Legal: The funding agreement will incorporate standard equality and safeguarding terms [P28]. Section 2 of the Local Government Act 2000 enables the council to act for an area's economic, environmental and social wellbeing [P42]. Report P28, P42
Staffing: The council intends to provide up to 0.5 days per month from Finance where capacity exists [P36]. Other support depends on agreement with service heads, capacity and availability [P36]. Report P36
Financial: Creation Trust must cover actual property costs, including utilities and maintenance, while the council forgoes market rent [P28]. The council will not make duplicate payments for those costs [P35]. Report P28, P35
Equalities: The shared vision includes homes affordable to local residents, a mixed community, families, elderly people, vulnerable people, schools, transport and community facilities [P28]. Report P28
Legal: The permanent location of the Trust is not yet determined, and its financial implications require a separate future report [P46]. Community space details would be covered by a later lease or licence [P28]. Report P28, P46
Risk: Government Office for London funding may be recovered if a project default cannot otherwise be resolved [P11]. Report P11
Who and where
Creation Trust, formally New Aylesbury Trust Ltd. Report P7
Local people benefiting from community services Report P30
Finance Department staff supporting business plan monitoring Report P36
Other council service departments giving agreed support Report P36
Local businesses involved in regeneration partnerships Report P16
Service providers involved in regeneration partnerships Report P16
Private sector developers, housing associations and national government Report P16
Timeline
27 February 2009: Government Office for London approved the funding application Report P11
19 October 2010: Council approved the first year plan and a 1 year agreement with a £250,000 commitment Report P12
28 February 2011: Cabinet agreed next steps for regeneration of the Aylesbury Estate Report P16
11 March 2011: Council received the 2011/12 business plan Report P19
1 April 2011: The grant agreement would cover the funding window from this date Report P33
prior to 30 June 2011: Council seeks to enter the 4 year funding agreement Report P25
2026-05-28: Cabinet decided the Creation Trust funding package
up to 2015: Commitment to continue financial support ceases Report P26
Plain English for the jargon
Creation Trust: A company limited by guarantee, formally New Aylesbury Trust Ltd., and successor to the Aylesbury NDC and Aylesbury Steering Group.
New Deal for Communities: A programme delivered through a community led board to help transform residents' lives on the Aylesbury Estate for 10 years.
Government Office for London: The government office that approved the Aylesbury funding application on 27 February 2009.
Funding agreement: A four year agreement setting grant amounts, duration, conditions, performance monitoring and business plan review arrangements.
Peppercorn rent: The community space arrangement in which Creation Trust covers utilities and maintenance while the council forgoes market rent.
Area Action Plan: The plan establishing the shared vision for physical redevelopment of the Aylesbury Estate.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
Decisions of the Cabinet 1. That a grant funding payment of £62,500 to New Aylesbury Trust Ltd. “Creation Trust” on the basis of Creation Trust’s Business Plan for 2011/12 be approved. 2. That grant funding of up to a maximum of £937,500 be paid to the Creation Trust in quarterly tranches of £62,500 subject to the terms of a 4 year funding agreement signed in accordance with the principles set out in paragraph 19 of the report. Decision of the Leader of the Council 3. That the responsibility for agreeing a 4 year funding agreement between the council and Creation Trust be delegated to the cabinet member for finance, resources and community safety, within the principles set out in paragraph 19 of the report.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 7 pages
Recommendations
Recommendations for the Cabinet
1. To approve a grant funding payment of £62,500 to New Aylesbury Trust Ltd. “Creation Trust” on the basis of Creation Trust’s Business Plan for 2011/12.
2. To approve grant funding of up to a maximum of £937,500 to be paid to the Creation Trust in quarterly tranches of £62,500 subject to the terms of a 4 year funding agreement signed in accordance with the principles set out in paragraph 19.
Recommendation for the Leader of the Council
3. To delegate the responsibility for agreeing a 4 year funding agreement between the council and Creation Trust to the Cabinet Member for Finance, Resources and Community Safety, within the principles set out in paragraph 19.
BACKGROUND INFORMATION
4. The Creation Trust (a company limited by guarantee and whose formal name is New Aylesbury Trust Ltd.,) is the successor body to the Aylesbury NDC and the Aylesbury Steering Group. The NDC, which was managed by a community led board, was established in 1999 to help transform the lives of residents of the Aylesbury Estate for a period of 10 years.
1 5. The council’s Major Projects Board, at its meeting on 27 January 2009, agreed that, in return for up to £18 million New Deal for Communities (NDC) capital funding for leaseholder buy-outs and improvements to Burgess Park, the council would:
(a) Bring forward the development of the Amersham site including social, community and other non-residential facilities (up to 2,500 m2) to be held in trust by the Creation Trust, for which the Creation Trust would be granted a long-lease at a peppercorn rent. (b) Provide revenue support (totalling £1.25 million) to the Creation Trust, in accordance with an approved business plan for Creation’s activities.
6. On 10 February 2009, an agreement was signed between Southwark Council, the Aylebsury New Deal for Communities and Creation Trust. This Memorandum of Agreement formally set out the party’s intention to collaborate in the manner set out in the council’s Major Project Report, which formed a schedule to the agreement. This Memorandum of Agreement was then used by the ANDC to apply formally for the funding approval of the Government Office for London (GOL).
7. On 27 February 2009, GOL approved the ANDC’s funding application. In giving their approval, GOL noted that the council’s commitment to providing community spaces and support for the Creation Trust formed a key part of their decision to approve the project. As with all GOL funds, in the event that there is a default in the commitment to the project and its delivery, which cannot otherwise be resolved, the funds can be clawed back.
8. On 19 October 2010, the council approved the Trust’s first year business plan (2010/2011), and agreed to enter into a 1 year funding agreement, with a total funding commitment of £250,000. This funding agreement ended in March 2011, and the total commitment of £250,000 has been paid to the Creation Trust.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.