London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Aylesbury Regeneration - Next Steps

Noted Executive 2 papers

AI summarySouthwark Cabinet directed officers to seek a development partner for Aylesbury phases 1b and 1c, consult on sites 8 and 9, explore improvements to the Thurlow Street hub and prepare a housing strategy. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted
MoneyNot stated
What happens nextNot stated
Who it affectsAylesbury estate residents [D]Sites 1b, 1c, 7, 8, 9 and 10 are affected. [D][P4]

What was decided

The previous decision to progress land transactions for sites 7 and 10, Wolverton and Missenden, and its associated issues was noted. [D][P3] Officers were asked to consider an appropriate route for seeking a development partner, initially focused on phases 1b and 1c at Bradenham, Chartridge, Arklow House and Chiltern. [D][P4] This must take account of lessons from Aylesbury Phase 1a and similar Southwark projects. [D][P4] Report P3, P4

Officers will continue consultation with residents, the Aylesbury Health Centre, Creation and other stakeholders while alternatives for sites 8 and 9 are explored. [D][P4] They will explore options to enhance the Thurlow Street community hub and prepare a housing management and investment strategy with residents, taking account of the Area Action Plan timetable and the council's Decent Homes programme. [D][P5][P6] The Leader delegated agreement of the sites 7 and 10 development brief to the Cabinet Member for Regeneration and Corporate Strategy, after officer discussions with the Primary Care Trust and Creation Trust. [D][P9] Report P4, P5, P6, P9

Why

The loss of PFI funding and changes to government funding arrangements leave a significant financial shortfall and no immediate alternative external funding for the likely deficits on sites 1b, 1c, 8 and 9. [P71][P77][P79] Report P71, P77, P79

There is no practical do nothing option because maintenance costs would escalate rapidly, especially for lifts and heating, and the estate would not achieve the sustainable mixed community envisaged in the Area Action Plan. [P56] Report P56

A single development partner or consortium would add expertise, give the council greater control over target vacant possession dates and provide a clearer long term shift in ownership and management responsibility. [P64][P66] Report P64, P66

What happens next

Officers will consider the route for seeking a development partner, initially focused on phases 1b and 1c. [D][P4] More detail on partnership arrangements is to be reported to a future Cabinet. [P69] Before the sites 7 and 10 brief is finalised, officers will discuss requirements with the Primary Care Trust, Health Centre and Creation Trust, and the Cabinet Member will agree its details. [D][P9][P58] Report P4, P9, P58, P69

Consultation on alternative options for sites 8 and 9 will continue with residents, the Aylesbury Health Centre, Creation and other stakeholders. [D][P4][P84] Officers will also explore enhancements to the Thurlow Street community hub with residents, Creation and local partners. [D][P5] Report P4, P5, P84

A housing management and investment strategy will be prepared with residents, taking account of the Area Action Plan regeneration timetable and the council's Decent Homes programme. [D][P6] Report P6

The money

  • around £250m Modelled scheme deficit across all phases. Report P77
  • £181m PFI credits curtailed, leaving no immediate alternative external funding for sites 1b, 1c, 8 and 9. Report P79
  • £120m Estimated upfront land assembly costs for the programme. Report P78
  • £26m Further funding identified for land assembly and site clearance. Report P71
  • around £4m Likely upfront land assembly costs for sites 7 and 10. Report P79
  • approximately £6m Estimated cost of upgrading lifts and district heating. Report P44
  • £5m to 10m Possible programme management costs over the next 4 to 5 years. Report P81
  • around £1m Likely added maintenance costs if sites 8 and 9 are deferred. Report P79

Options considered

  • Chosen: Appoint a single development partner or consortium. The partner would bring development and phasing expertise, greater council control of vacant possession dates and clearer long term management arrangements. The initial focus is phases 1b and 1c. Report P64, P66, P68
  • Rejected: Make individual open market marketing the main longer term route. Long term individual marketing could produce disjointed redevelopment, uncertain delivery times and multiple housing providers. Report P62
  • Rejected: Transfer management, maintenance and regeneration to a third party. It was unlikely to attract housing providers, would delay the programme and reduce opportunities to rehouse residents. Local residents rejected it in 2001 with a 73% No vote. Report P63
  • Rejected: Do nothing. Costs would escalate rapidly, particularly for lifts and heating, and the Area Action Plan vision would not be achieved. Report P56

Implications

  • Financial: The scheme is modelled to run at a deficit of around £250m across all phases. The council does not have sufficient resources to meet the deficit alone. Report P77
  • Risk: HCA grant funding for the regeneration programme is expected to be removed or severely curtailed. Report P36
  • Financial: Deferring sites 8 and 9 would reduce the immediate deficit and delay land assembly costs, but would add around £1m in maintenance costs. Report P79
  • Risk: Delays would increase maintenance and investment and extend the enhanced neighbourhood service. Residents cannot yet be given certainty about returning to the Aylesbury because delivery and funding remain unsettled. Report P45, P52
  • Legal: Section 105 Housing Act 1985 requires consultation with secure tenants, and the likely rehousing impact on sites 8 and 9 is expected to engage this duty. Report P86
  • Legal: Any development partner appointment or future delivery strategy is likely to be subject to EU procurement tendering requirements. Legal officers will advise and prepare Gateway reports for Cabinet approval. Report P87
  • Staffing: The council has committed to an enhanced neighbourhood housing management service with dedicated officers throughout the regeneration programme. Report P30
  • Other: Detailed proposals must reflect existing site constraints and the Area Action Plan. Planning Committee would consider whether the overall benefits justify the approach. Report P39

Who and where

  • Residents and secure tenants across the Aylesbury estate Report P47, P86
  • Residents in sites 8 and 9 Report P84, P86
  • Residents in Bradenham, Chartridge, Arklow House and Chiltern Report P4, P28, P29
  • Residents in Wolverton and Missenden Report P3, P49
  • Aylesbury Health Centre Report P4, P58
  • Creation Trust Report P9, P58
  • Primary Care Trust Report P58
  • Potential strategic development partners Report P64, P65

Timeline

  • 26 September 2006: The option to return was agreed for tenants rehoused from the SW corner of phases 1a, 1b and 1c. Report P52
  • 2 November 2010: Cabinet agreed to offer sites 7 and 10 on the open market to secure development partners. Report P23
  • 14 December 2010: Cabinet received the consequences of the curtailed PFI funding and requested an Outline Business Case, alternative funding and further rehousing. Report P11, P12
  • 2010: Rehousing starts were listed for Wolverton, Missenden, Bradenham and Chartridge. Report P49
  • 2011: Rehousing starts were listed for Arklow House, the remainder of Chartridge and Chiltern. Report P49
  • early 2011: Sites 7 and 10 were due to be released through land transfer. Report P79
  • March 2011: The first four Phase 1a sites were expected to reach practical completion with 37 social rent homes, 15 intermediate rent homes and a resource centre. Report P22
  • TBA: Rehousing start dates for Taplow, Northchurch and East Street were still to be confirmed. Report P49

Plain English for the jargon

  • Area Action Plan: The adopted plan covering policies, phasing and design guidance for the Aylesbury estate. [P38]
  • PFI: The housing delivery project whose government funding was curtailed. [P11][P27]
  • HCA: The Homes and Communities Agency, which provided social housing grant support for Phase 1a. [P22]
  • PCT: The Primary Care Trust, consulted on development brief requirements. [D][P58]
  • OBC: The Outline Business Case for the PFI housing project. [P11][P14]
  • HRA: The Housing Revenue Account. [P34][P50]
  • Decent Homes: The council programme and housing requirements referred to in the housing strategy. [P6][P43]
  • Gateway reports: Reports for Cabinet approval, supported by legal advice. [P87]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Decisions of the Cabinet 1. That the previous decision to progress land transactions for sites 7 and 10 ( Wolverton and Missenden) and the associated issues set out in paragraph 45 of the report be noted. 2. That officers consider an appropriate route for seeking a development partner for the Aylesbury, with initial focus on phase 1b and 1c ( Bradenham , Chartridge , Arklow House and Chiltern), taking into account lessons learned on Aylesbury Phase 1a and other similar projects within Southwark, as indicated in paragraphs 50 to 54 of the report. 3. That in relation to the redevelopment of sites 8 and 9 (East Street, Taplow and Northchurch ), officers continue to consult with residents, the Aylesbury Health Centre, Creation and other stakeholders, as alternative options are explored. 4. That officers also explore with residents, Creation and other local partners, options to enhance the existing community hub located on Thurlow Street, near to the junction with East Street, ahead of the longer term regeneration. 5. That officers prepare a housing management and investment strategy for the Aylesbury, in consultation with residents, taking into account (a) the regeneration timetable set out in the Area Action Plan and (b) the council’s Decent Homes programme. Decision of the Leader of the Council 6. That the responsibility for agreeing the detail of the development brief for sites 7 and 10, following officer discussions with the Primary Care Trust and Creation Trust be delegated to the cabinet member for regeneration and corporate strategy.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 15 pages

Recommendations

Recommendations for the Cabinet

That the Cabinet:

6. Notes the previous decision to progress land transactions for sites 7 and 10 (Wolverton and Missenden) and the associated issues set out in paragraph 45.

7. Requests officers to consider an appropriate route for seeking a development partner for the Aylesbury, with an initial focus on phase 1b and 1c (Bradenham, Chartridge, Arklow House and Chiltern), taking into account lessons learned on Aylesbury Phase 1a and other similar projects within Southwark, as indicated in paragraphs 50 to 54. 8. In relation to the redevelopment of sites 8 and 9 (East Street, Taplow and Northchurch), requests that officers continue to consult with residents, the Aylesbury Health Centre, Creation and other stakeholders, as alternative options are explored.

9. Requests that officers also explore with residents, Creation and other local partners, options to enhance the existing community hub located on Thurlow Street, near to the junction with East Street, ahead of the longer term regeneration.

10. Requests that officers prepare a housing management and investment strategy for the Aylesbury, in consultation with residents, taking into account (a) the regeneration timetable set out in the Area Action Plan; and (b) the council's Decent Homes programme.

Recommendations for the Leader of the Council

That the Leader

11. Delegates responsibility for agreeing the detail of the development brief for sites 7 and 10 to the Cabinet Member for Regeneration and Corporate Strategy, following officer discussions with the PCT and Creation Trust.

BACKGROUND INFORMATION

12. The cabinet received a report on 14 December 2010 on the consequences of the government’s decision to curtail the proposed £181m funding for the Aylesbury PFI Housing Project, as one of 13 housing PFI pipeline projects nationally. The cabinet reaffirmed its commitment to regenerating the Aylesbury Estate and requested officers to complete and submit the Outline Business Case (OBC) for the PFI project and to review possible alternative funding sources, reporting back to cabinet in February 2011.

13. To keep up the momentum for regeneration, the cabinet also requested officers to commence the re-housing of tenants in the remainder of Chartridge (Nos 106– 149), in line with the indicative housing plans set out in the report.

14. Since the cabinet meeting on 14 December:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Aylesbury Regeneration: Next StepsAppendix 1 2 pages Download
PDF
Report: Aylesbury Regeneration: Next StepsReport 15 pages DownloadRead as text

At this meeting

Whole meeting
4Aylesbury Regeneration - Next StepsThis decision

Who was there

7 of 9 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, apologies
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, apologies
AM
Councillor Abdul MohamedCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present

On this subject at Southwark

Search all
  1. Aylesbury Regeneration - Next StepsThis decision
  2. Amending the Rehousing Policy for Homeowners affected by the Regeneration of the Aylesbury EstateDecided
  3. Aylesbury Regeneration - Phase 1: sites 7 & 10 Revised Delivery RouteDecided
  4. Gateway 1: Procurement Strategy Approval Aylesbury Regeneration: Development PartnershipApproved
  5. Selection of a Preferred Partner to Work with the Council to Deliver the Regeneration of the Aylesbury EstateApproved
  6. Phase 1b and 1c Aylesbury RegenerationAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open