AI summarySouthwark Cabinet approved a cemetery strategy and phased burial space at Camberwell Old and New Cemeteries, with an estimated £4.7m capital cost [D][P114]. It also approved work on an Act change, outside burial procurement and an Honor Oak review [D].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedLocal burial continues with phased Camberwell works [D][P4].
Money£4.7m [P114]Estimated short and medium term cost [P114].
What happens nextNot stated
Who it affectsResidents and cemetery users [P40][P120]Burial, faith needs, fees and green space [P40][P110][P117].

What was decided

Cabinet noted the 2011 consultation outcomes, agreed the cemetery service vision, and confirmed both local burial space and adoption of the Cemetery Strategy. Report P1, P2, P3, P37

Cabinet approved short and medium term burial space in Camberwell Old and New Cemeteries, subject to the Council capital programme. Sites H1 and D2 will return for consideration after investigations in 2014. Report P4

Cabinet agreed to seek an amendment to the London Local Authorities Act 2007, noted regional work with LEDNET and the Greater London Authority, and directed further procurement work outside the borough. Honor Oak Recreation Ground and borough cemeteries were referred to the parks and open spaces strategy review. Report P5, P6, P7

Why

The council had faced a burial space shortage for several years, and current provision was expected to last five and a half years. The proposals could provide sufficient space for twenty eight years. Report P11, P102, P113

Consultation found that 22% of respondents required burial, including faith groups for whom burial was the only acceptable option. Public preference was strongest for reusing public graves. Stopping burial received very little support, and Honor Oak Recreation Ground was least favoured. Report P39, P40, P45

The strategy prioritises unused cemetery land and then lawful reuse of graves, while working with other London authorities for longer term supply. Reuse was viewed as the most sustainable option with the least impact on open space and bereaved relatives. Report P45, P56, P58, P59

What happens next

Submit bids in the next capital funding round and obtain formal approval for the expenditure. Report P114, P141

Officers will explore procurement outside the borough, potentially with other London boroughs. Report P103

The council will seek the Act amendment and continue regional work. Honor Oak Recreation Ground and borough cemeteries will be considered in the parks and open spaces strategy review. Burial figures will be reviewed at critical stages, with public consultation and reports to Cabinet. Report P6, P76, P90

The money

  • £410k Capital allocation for immediate term works at Camberwell New and Camberwell Old Cemeteries Report P22, P113
  • £1.70m Estimated cost of the short term burial sites Report P63
  • £3m Estimated cost of the medium term proposals Report P74
  • £4.7m Total estimated cost of the short and medium term options Report P114
  • £738k Cemetery income target for 2011/12 Report P116
  • £813k Cemetery income target for 2012/13 Report P116

Options considered

  • Chosen: Approve short and medium term burial space in Camberwell Old and New Cemeteries. The action plans identified sites in both cemeteries. Approval was subject to capital programme funding, with H1 and D2 returning after investigations in 2014. Report P62, P63
  • Chosen: Reuse public graves and reclaim unused private grave space. Public grave reuse was the most preferred consultation option, while private grave reclamation formed part of the medium term proposals. Both depend on legal powers and permissions. Report P45, P67, P69, P71
  • Chosen: Construct mausoleums at Camberwell Old and New Cemeteries. Mausoleums use less land, protect burial locations and may release space after remains are removed. Report P67, P73
  • Chosen: Seek amendment of the London Local Authorities Act 2007. Southwark lacked private grave reuse powers available to other London boroughs under the 2007 Act. Report P90
  • Chosen: Identify a regional solution with LEDNET and the Greater London Authority. The Greater London Authority report found critical supply in boroughs across London and demand likely exhausted within ten years. Report P6, P95
  • Chosen: Explore procurement of burial space outside Southwark. A private cemetery offered up to fifty burial spaces and other London authorities expressed joint procurement interest, despite limited public support. Report P102, P103
  • Rejected: Use some or all of Honor Oak Recreation Ground for burials. It was the least favoured option and attracted 214 objecting comments. Its future was referred to a later strategy review. Report P45
  • Rejected: Stop burying in Southwark. Stopping burial in Southwark received very little support, and the council confirmed a continuing local burial commitment. Report P45

Implications

  • Financial: The short and medium term programme was estimated at £4.7m. The current capital programme had no provision for it, so bids were needed in the next capital refresh. Report P114, P141
  • Financial: Capital investment may require higher cemetery fees, as fees remain below the London average. If options were not accepted, the service could lose income when space ran out in five and a half years, creating budget pressure. Report P117, P118
  • Legal: Reuse of public graves required Church of England permission. Private grave reclamation depended on the 1975 Act and, in consecrated ground, Faculty approval. Report P69, P71
  • Risk: Short term sites carried planning risks, including tree loss. Sites H1 and D2 were to return for Cabinet consideration after investigations in 2014. Report P63
  • Risk: Overview and Scrutiny said residents closest to three additional Camberwell Old sites might not have known. It recommended a risk assessment and possible further work. Report P9
  • Equalities: An EqIA found the strategy would continue existing service provision and no equality group was disproportionately affected. Report P138
  • Staffing: New record keeping and management procedures were needed, including digitised records and heritage assessment protocols. Regional guidance was expected to support training and reduce the need for external consultants. Report P93, P100
  • Other: The strategy aimed to maintain burial capacity until 2040, depending on burial rates. It included four more Muslim burial spaces at Nunhead Cemetery. Report P65, P74

Who and where

  • Southwark residents who require burial, including faith groups for whom burial was the only acceptable option Report P40
  • Bereaved people and families who value graves close to home and family connections Report P42
  • Muslim residents needing additional burial spaces Report P65
  • Residents near Camberwell Old and New Cemeteries, including site H1 Report P62
  • Cemetery users and local communities affected by new plots, landscaping or grave reuse Report P56, P120
  • Local funeral directors Report P122
  • Cemetery operational staff responsible for records, grave assessment and implementation Report P93, P100
  • Other London boroughs and their residents if regional or joint provision proceeds Report P95, P103

Timeline

  • 4th July to 30th September 2011: Public and stakeholder consultation on future burial options Report P37
  • 8 May 2012: Overview and Scrutiny considered the report and recommended a consultation risk assessment Report P9
  • autumn 2012: Residents near site H1 would be consulted on landscaping Report P62
  • December 2012: Topping up works at Camberwell Old were expected to finish, subject to planning approval Report P32
  • January 2013: Advanced grave space sales were due to restart Report P35
  • 2014: Sites H1 and D2 were to be considered after investigations
  • 2014/15 and 2019/20: Short term capital needed to be available Report P83
  • 2015 to 2022, then 2022 to 2040, and from 2045 onwards: Short term and medium term proposals precede potential grave reuse at Camberwell New, subject to legal resolution and Faculty approval Report P60, P66, P88

Plain English for the jargon

  • LEDNET: London Environmental Directors Network, coordinating work on regional burial provision. [D][P6][P99]
  • Faculty: Church of England permission required to reuse graves in consecrated burial areas. [P69]
  • Grave reuse: Reusing unmarked public graves older than seventy five years, subject to Church of England permission. [P69]
  • Grave reclamation: Recovering unused private grave space after burial rights older than 75 years have been extinguished. [P71]
  • Mausoleum: An above ground vault that can be landscaped. Remains are typically removed after 30 years, allowing the space to be reused. [P73]
  • Pre sales: Advanced sale of grave space. [P35]
  • EqIA: Equalities and Human Rights Impact Assessment, used to assess effects on protected groups. [P138]
  • Short and medium term: Short term covers 2015 to 2022; medium term covers 2022 to 2040. [P60][P66]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

That the outcomes of the public consultation on future burial provision in the Borough undertaken in the summer of 2011(Appendix D of the report) be noted. 2. That the vision for the Cemetery service as set out in paragraphs 34 and 35 of the report be agreed. 3. That the commitment to providing burial space within the Borough and to the adoption of the Cemetery Strategy (Appendix A of the report) be confirmed. 4. That the creation of short and medium term burial space in Camberwell Old and New Cemeteries as identified in the action plans as amended by the proposals for phasing in the supplementary information report be agreed subject to the agreement to the Council capital programme 2012-2022 (Appendices B and C of the report) with the exception that sites H1 and D2 are considered by Cabinet upon completion of investigations in 2014. 5. That the council seek the amendment of the London Local Authorities Act 2007 to provide the Council with the powers to reuse graves currently available to all other London Boroughs. 6. That the additional work being undertaken with the London Environmental Directors Network (LEDNET) and the Greater London Authority to identify a regional solution to the shortage of burial space in London be noted. 7. That officers explore further the procurement of burial space outside the Borough. 8. That the future of Honor Oak Recreation Ground and the Borough cemeteries be referred for consideration within the parks and open spaces strategy review due to report later in the year.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 15 pages

Recommendations

1. That the Cabinet note the outcomes of the public consultation on future burial provision in the Borough undertaken in the summer of 2011(Appendix D).

2. That the Cabinet agrees the vision for the Cemetery service as set out in paragraphs 34 and 35 of this report.

3. That the Cabinet confirm its commitment to providing burial space within the Borough and to the adoption of the Cemetery Strategy (Appendix A)

4. That the Cabinet agree to the creation of short and medium term burial space in Camberwell Old and New Cemeteries as identified in the action plans subject to the agreement to the Council capital programme 2012-2022 (Appendix B and C).

5. That the Cabinet agree that the Council seek the amendment of the London Local Authorities Act 2007 to provide the Council with the powers to reuse graves currently available to all other London Boroughs.

6. That the Cabinet note the additional work being undertaken with the London Environmental Directors Network (LEDNET) and the Greater London Authority to identify a regional solution to the shortage of burial space in London.

1 7. That the Cabinet ask officers to explore further the procurement of burial space outside the Borough.

Comments from Overview and Scrutiny Committee

The Overview and Scrutiny Committee considered the report at its meeting on 8 May 2012. The committee noted that 3 additional potential sites for burial in Camberwell Old Cemetery had been identified after the main consultation was under way, and that residents closest to these sites may not be aware of this. The committee therefore recommended that the Cabinet request officers to carry out a risk assessment on the consultation process and consider whether any additional work was required in respect of these particular sites.

BACKGROUND INFORMATION

8. The need to identify burial space in the Borough has been an issue for the Council for several years. In July 1999, the Honor Oak Nursery Site Steering Group was formed, comprising locally elected members and local representatives drawn from both Southwark and Lewisham (“the Steering Group”) to consider options for burial at Camberwell New Cemetery.

9. In November 1999 the then Regeneration and Environment Committee met to discuss, the Management of Future Burials. The Committee agreed to reaffirm an October 1996 Committee decision on future burial to bring back into cemetery use the 3 acres of Honor Oak Recreation Ground.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(appendices 1-6)Appendix A 38 pages Download
PDF
Southwark Council CemeteryAppendix A 74 pages Download
PDF
Short Term Burial OptionsAppendix B 2 pages Download
PDF
Medium term burial optionsAppendix C 2 pages Download
PDF
Consultation reportAppendix D 37 pages Download
PDF
Report: Future of Cemeteries ServiceReport 15 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
CH
Councillor Claire HicksonCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected

On this subject at Southwark

Search all
  1. Future of Cemeteries ServiceThis decision
  2. Consultation Options for Future Service Strategy for Southwark CemeteriesAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies