Noted Executive 3 papers

AI summarySouthwark Cabinet approved in principle delegating ICT to Brent for a shared service with Lewisham, with an estimated £3m for preparatory and transition work. Final delegation terms will return to Cabinet. [D] [P3] [P4] [P3]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBrent proposed as primary host [P3]
Money£3m [P4]Estimated preparatory and transition cost [P4]
What happens nextFinal report to Cabinet [P3]Further approval of final terms [P3]
Who it affectsSouthwark, Brent and Lewisham [P3]Service duties, liabilities, insurance and asset use [P3]

What was decided

Cabinet approved in principle delegating Southwark's ICT service to Brent as primary host in a shared service with Lewisham. [D] [P3] A further Cabinet report will seek approval of the final terms. [P3] Report P3

Cabinet approved a memorandum of understanding and an interim agreement between the three councils. [D] [P4] The agreement will cover obligations, liabilities, insurance and assets. [P3] [P131] Funding of an estimated £3m was approved for preparatory and transition work, with authority to agree final interim terms delegated to the strategic director of housing and modernisation. [D] [P4] Report P4, P3, P131

Cabinet noted ongoing due diligence and agreement development. [D] [P3] It noted that Brent and Lewisham officers are taking reports to their cabinets. [D] [P5] Officers will discuss extending the existing ITMS contract with Capita. [D] [P6] Report P3, P5, P6

Why

The original procurement stopped after it failed to attract the minimum level of supplier interest. [P14] [P15] Basic cost modelling found the shared service significantly cheaper over five years, with more opportunities for medium-term savings. [P100] Report P14, P15, P100

The shared service included service management and integration across all service areas and third parties, plus finance, procurement, programme and project support. It required a smaller retained Southwark team than the BT option. [P100] Report P100

The service included service requests, a hardware replacement budget, and installation, moves and changes. [P100] The option avoided an estimated 18 months of Capita hosting, and there was officer and political appetite to try a different model. [P100] Report P100

What happens next

The three councils will use the memorandum of understanding to develop delivery details, transition plans and budget allocations. [P130] They also intend to agree an interim agreement covering obligations, liabilities, insurance and assets. [P131] Report P130, P131

Officers will complete due diligence and prepare a further Cabinet report covering scope, finance and final delegation terms. [P3] [P132] Each of the three councils will later approve the permanent governance model. [P124] Report P3, P132, P124

Officers will discuss extending the existing ITMS contract with Capita so preparatory work can finish. [P6] The indicative programme set 31 October 2017 as the target for service commencement. [P160] Report P6, P160

The money

  • £3m Estimated preparatory and transition cost, with provision in the Capital Programme Report P4, P183
  • 45% Estimated Southwark share of core costs Report P52
  • circa £5.5m Shared ICT Service budget, limited to contract elements handled by Brent Report P32

Options considered

  • Chosen: Join the existing Brent and Lewisham shared ICT service. The evaluation concluded it offered the best option for future ICT provision. Report P101
  • Rejected: Use the Westminster City Council Pan London ICT Services Framework with BT. It was viable, but the shared service was significantly cheaper over five years and required a smaller retained team. Report P100
  • Rejected: Direct award through the Pan London framework. It was not among the two options shortlisted for further evaluation. Report P18
  • Rejected: Fully in-sourced ICT service. It was not among the two options shortlisted for further evaluation. Report P18
  • Rejected: New procurement with a variant SIAM model through a framework. It was not among the two options shortlisted for further evaluation. Report P18
  • Rejected: Full EU tender with a variant SIAM model. It was not among the two options shortlisted for further evaluation. Report P18
  • Rejected: Framework direct call off with one supplier. It was not among the two options shortlisted for further evaluation. Report P18
  • Rejected: Further extension of the existing Capita contract as the future service model. It was not shortlisted. The extension discussed is to allow preparatory and transition work to finish. Report P6, P18

Implications

  • Financial: The shared service is expected to deliver better value through efficiencies, economies of scale and possible future growth. [P179] Report P179
  • Financial: Costs would be apportioned by user accounts, consumption and direct attribution. Southwark was estimated to bear 45% of core costs, based on 4,500 of 10,000 service users. [P52] Report P52
  • Legal: The delegation will use the stated statutory powers for local authority shared services. [P117] The memorandum of understanding is not legally binding, and final legal advice will accompany the later approval report. [P130] [P195] Report P117, P130, P195
  • Staffing: Brent would employ all shared service delivery staff, with 46 additional staff needed to take the team to 96. [P171] [P172] Some Capita and Southwark staff may transfer under TUPE, while Capita's applications support function would move into Southwark's team. [P147] [P173] [P174] Report P147, P171, P172, P173, P174
  • Equalities: Recruitment will cover all three boroughs. The structure includes nine apprentice posts shared equally between them. [P168] [P169] Report P168, P169
  • Risk: Cultural and working behaviours may not transfer to the shared service. [P48] The report rates culture, partner conflict, delays and unbudgeted costs as high risks. Shared service arrangements do not use contractual service credits. [P157] [P158] [P196] Report P48, P157, P158, P196
  • Other: An equal partnership board with representatives from all three councils would oversee transition, then the service until permanent governance was approved. [P46] [P123] [P124] Report P46, P123, P124
  • Other: No transformation would take place during transition. After service stabilisation, a transformation programme would follow. [P36] Report P36

Who and where

  • Southwark Council Report P3
  • London Borough of Brent Council Report P3
  • London Borough of Lewisham Report P3
  • Shared ICT Service delivery staff Report P171
  • Southwark ICT staff Report P176
  • Capita staff who may transfer Report P173
  • Shared service apprentices Report P169
  • Council staff using the managed ICT service Report P10

Timeline

  • 7 February 2017: Southwark Cabinet report and decision. Report P160
  • 20 February 2017: Memorandum of understanding and interim agreement between the three councils. Report P160
  • April 2017: Deadline for notice of extension to the Capita contract. Report P160
  • May/June 2017: Prepare the Cabinet report for delegation and brief Cabinet members. Report P160
  • June/July 2017: Delegation and the agreement between the three councils take effect, and interim governance begins. Report P160
  • October 2017: TUPE consultation period and continued transition activities. Report P160
  • 31 October 2017: Target date for service commencement. Report P160
  • Early 2018: Cabinet reports on final governance for all three partner authorities. Report P160

Plain English for the jargon

  • ICT: Information and communications technology. [P3]
  • Shared ICT Service: A joint service in which Brent hosts delivery for Southwark and Lewisham. [P3]
  • MOU: A memorandum of understanding that is not legally binding. [P130]
  • Interim agreement: An agreement between the three councils covering shared service duties and liabilities. [P131]
  • TUPE: Transfer of Undertakings (Protection of Employment) Regulations 2006. Staff may transfer when service operations move. [P173]
  • SIAM: Service integration and management. [P54]
  • Host authority: Brent as the authority employing staff and delivering the shared service. [P171]
  • Joint partnership board: An interim board with equal representatives from the three councils. [P46]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

That the outcome of the original procurement process and the work undertaken to consider alternative options be noted. 2. That the delegation of the delivery of the information and communications technology (ICT) service to London Borough of Brent Council as the primary host authority in a Shared ICT Service with London Borough of Lewisham be approved in principle, and that it be noted that a further report will be brought to cabinet to approve delegation in its final terms. 3. That the ongoing due diligence process and the development of inter-authority agreements for delegation of the ICT service delivery which will cover the 3 boroughs’ obligations, liabilities, insurance arrangements and use of assets in relation to the Shared ICT Service, be noted. 4. That the entering into a memorandum of understanding with the London Borough of Brent and London Borough of Lewisham (as outlined in Appendix A of the report) be approved, and that the funding of preparatory and transition work at an estimated cost of £3m and entering into an interim inter-authority agreement which will cover the 3 boroughs’ obligations with regard to the preparatory and transition activities and as further detailed in paragraph 93b of the report also be approved, and that authority be delegated to the strategic director of housing and modernisation to agree the final terms of the interim inter-authority agreement(s). 5. That it be noted that Brent and Lewisham officers are presenting reports to their respective cabinets in relation to this delegation and future Shared ICT Service. 6. That it be noted that officers will undertake discussions with Capita regarding a further extension of the existing ITMS contract to allow the preparatory and transition activities to be completed.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 26 pages

Recommendations

That Cabinet:

1. Notes the outcome of the original procurement process and the work undertaken to consider alternative options.

2. Approves in principle the delegation of the delivery of the ICT service to London Borough of Brent Council as the primary host authority in a Shared ICT Service with London Borough of Lewisham and notes that a further report will be brought to Cabinet to approve delegation in its final terms. 3. Notes the ongoing due diligence process and the development of inter-authority agreements for delegation of the ICT service delivery and which will cover the 3 boroughs obligations, liabilities, insurance arrangements and use of assets in relation to the Shared ICT Service.

4. Approves the entering into a memorandum of understanding with the London Borough of Brent and London Borough of Lewisham (as outlined in Appendix A) and approves the funding of preparatory and transition work at an estimated cost of £3m and entering into an interim inter-authority agreement which will cover the 3 boroughs obligations with regard to the preparatory and transition activities and as further detailed in paragraph 93b and delegates authority to the strategic director of housing and modernisation to agree the final terms of the interim inter-authority agreement(s).

5. Notes that Brent and Lewisham officers are presenting reports to their respective cabinets in relation to this delegation and future Shared ICT Service.

6. Notes that officers will undertake discussions with Capita regarding a further extension of the existing ITMS contract to allow the preparatory and transition activities to be completed.

BACKGROUND INFORMATION

7. In October 2012 Capita was awarded the contract to provide a fully managed ICT service. The contract initially ran from 1 February 2013 for a period of four years, with an option to extend for further periods up to 31 January 2019.

8. The current ICT managed service covers a range of service elements. These can be divided broadly into:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Overview of Memorandum of UnderstandingAppendix A 1 pages Download
PDF
Partnership principlesAppendix B 2 pages Download
PDF
Report: ICT Shared Service with Brent and LewishamReport 26 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
PJ
Councillor Peter John OBEChair, present
SC
Councillor Stephanie CryanCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
IW
Councillor Ian WingfieldCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, apologies
NC
Norman CoombeOfficer, expected

On this subject at Southwark

Search all
  1. ICT Shared Service with Brent and LewishamThis decision
  2. Shared ICT Service with Brent and LewishamAgreed
  3. Appointments to Outside Bodies 2017-18 and nominations to Shared ICT Service Joint CommitteeAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open