London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Aylesbury Estate: Community facilities at Plot 18 Delivery

Noted Executive 3 papers

AI summaryCabinet approved making a compulsory purchase order for Plot 18 to secure 122 new homes and community facilities, with £35m already approved for the facilities. An update on vacant possession will go to Cabinet before the order is made.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAll land and rights in the Appendix 2 plan
Money£35mApproved in February 2017 for community facilities
What happens nextCabinet update before CPOFurther report on vacant possession progress
Who it affectsNorthchurch residents and estate usersHousing, health, library and early years services

What was decided

Cabinet resolved to make a compulsory purchase order under Section 226 (1)(a) of the Town & Country Planning Act 1990 for all land and rights in the Appendix 2 plan. Report P3

The order is intended to secure new homes and community facilities under the existing planning consent and advance the Aylesbury Estate regeneration in line with the adopted Aylesbury Area Action Plan. Report P3

Cabinet required an update on progress towards vacant possession before the compulsory purchase order is made. Report P4

Why

Full delivery of the consented scheme requires vacant possession of the block at 57 to 76 Northchurch so it can be demolished and redeveloped. Report P39

Negotiations for the three remaining leasehold interests have stalled. A compulsory purchase order alongside negotiations gives impetus and certainty within the Plot 18 construction programme. Report P42, P48

The scheme has outline and reserved matters consent, strong policy support and is considered to improve social, economic and environmental well being for the estate. Report P50, P54, P72

What happens next

Cabinet will receive a further report on progress towards vacant possession before the compulsory purchase order is made. Report P4

The council will continue negotiations with all three remaining leaseholders while promoting the compulsory purchase order in parallel. Report P42, P48

A contractor is to be procured competitively through Notting Hill Housing Trust, with the contract intended for summer 2018. Initial service diversion works will be completed in 2018. Report P2, P19, P36

The money

  • £35m Approved funding towards the Plot 18 community facilities, including an infrastructure contribution and section 106 funding. Report P12
  • 10% Home loss payment for resident leaseholders. Report P63
  • 7.5% Home loss payment for non resident leaseholders. Report P63

Options considered

  • Chosen: Promote a compulsory purchase order alongside negotiated acquisitions. Negotiations have stalled, so the order gives further impetus and certainty. Report P48
  • Rejected: Continue relying on negotiated acquisitions alone. Three leasehold interests remain and voluntary acquisition does not provide the required certainty. Report P42, P48
  • Chosen: Bring a further vacant possession update before making the order. Cabinet will receive the update before the compulsory purchase order is made. Report P4

Implications

  • Legal: Section 226(1)(a) permits compulsory acquisition, but the council must consider whether the redevelopment is likely to improve the area's economic, social or environmental well being. Report P70, P88, P90
  • Legal: Any interference with Convention rights caused by the order is considered justified and proportionate in the wider public interest. Report P71
  • Financial: Remaining leaseholders are eligible for market value, a home loss payment of 10% for resident leaseholders or 7.5% for non resident leaseholders, and disturbance payments. Report P63
  • Equalities: Rehousing assistance, location choices and support are intended to mitigate disruption and any disproportionate impacts on affected households. Report P57, P64, P78
  • Equalities: The council received no occupier survey responses and relies on broader data while continuing to monitor disproportionate impacts. Report P78
  • Financial: Compulsory purchase promotion and acquisition costs are met from existing Aylesbury regeneration budgets, with no additional financial implications from this report. Report P79, P81
  • Staffing: Delivery is undertaken by Notting Hill Housing Trust under the Development Partnership Agreement, with no additional resource implications. Report P69
  • Other: Plot 18's revised mix is 17 social rent, 6 intermediate shared ownership and 99 private sale homes. Across both sites, the revisions add 15 social rent and 105 intermediate shared ownership homes, with a loss of 108 private sale homes. Report P28, P29

Who and where

  • The three remaining leaseholders at 57 to 76 Northchurch Report P42
  • The remaining household on a secure tenancy Report P41, P59
  • The 13 households in temporary accommodation Report P43, P58
  • Existing and incoming residents of the Aylesbury Estate Report P18, P54
  • Patients using the new GP surgery and community health service Report P23
  • Children aged 0 to 5 using the early years facility Report P25
  • Children, families and young people using the new library Report P20, P21
  • Creation Trust and other community groups using the new spaces Report P17, P22

Timeline

  • Before a Compulsory Purchase Order is made: Cabinet receives a further update on progress towards vacant possession. Report P4
  • August 2015: Outline consent for redevelopment of the site was granted. Report P2
  • March 2016: Vacant possession of 300 to 313 Missenden and the blue huts was achieved. Report P2
  • December 2016: Detailed reserved matters planning consent for Plot 18 was granted. Report P2
  • February 2017: Cabinet approved the funding package for delivery of Plot 18. Report P2, P12
  • May 2017: An application was submitted to amend the consented tenure mix for Plot 18. Report P2
  • June 2017: Demolition of 300 to 313 Missenden to ground level was completed. Report P36
  • 2018: Initial service diversion works will be completed. The construction contract is intended to be let in summer 2018. Report P2, P19, P36

Plain English for the jargon

  • Aylesbury Area Action Plan (AAAP): Adopted council plan setting policy for the estate redevelopment
  • Compulsory Purchase Order (CPO): Council power to acquire land and property interests
  • Development Partnership Agreement (DPA): Agreement between the council and Notting Hill Housing Trust
  • MUGA: Multi use games area
  • NHHT: Notting Hill Housing Trust, the council's development partner
  • PSED: Public Sector Equality Duty
  • Section 226(1)(a): Power under the Town & Country Planning Act 1990
  • GP: General practice
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item22

Resolved

That the current position in relation to the delivery of new homes and a range of new community facilities at Plot 18 of the Aylesbury regeneration programme be noted as follows: · Outline consent for the redevelopment of the site was granted in August 2015 · Cabinet approved the submission of a detailed scheme for Plot 18 for planning consent in October 2015 · Detailed reserved matters planning consent was granted in December 2016 · Cabinet approved the funding package for the delivery of Plot 18 in February 2017 · An application has been submitted to amend the consented tenure mix for Plot 18 in line with the revised tenure mix reported to cabinet in May 2017 · Vacant possession of 300-313 Missenden and the blue huts was achieved in March 2016 and demolition was completed in June 2017 · The council has successfully acquired 2 resident leasehold properties within 57-76 Northchurch by agreement and successfully rehoused 13 households on a secure tenancy · Initial service diversion works have commenced and will be completed in 2018 · The council is continuing to negotiate with all 3 remaining leaseholders within 57-76 Northchurch with the intention to acquire these remaining interests by agreement. 2. That a Compulsory Purchase Order under Section 226 (1)(a) of the Town & Country Planning Act 1990 is made for all land and rights within the area of land identified within the plan at Appendix 2 of the report for the purposes of securing the delivery of new homes and community facilities on the site in line with the existing planning consent and thereby securing the regeneration of the Aylesbury Estate in line with the adopted Aylesbury Area Action Plan. 3. That it be noted that an update report on further progress towards obtaining vacant possession of the site will be brought to cabinet before a Compulsory Purchase Order is made.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 16 pages

Recommendations

1. That Cabinet notes the current position in relation to the delivery of new homes and a range of new community facilities at Plot 18 of the Aylesbury regeneration programme:

 Outline consent for the redevelopment of the site was granted in August 2015;  Cabinet approved the submission of a detailed scheme for Plot 18 for planning consent in October 2015;  Detailed reserved matters planning consent was granted in December 2016;  Cabinet approved the funding package for the delivery of Plot 18 in February 2017;  An application has been submitted to amend the consented tenure mix for Plot 18 in line with the revised tenure mix reported to cabinet in May 2017;  Vacant possession of 300-313 Missenden and the blue huts was achieved in March 2016 and demolition was completed in June 2017;  The council has successfully acquired 2 resident leasehold properties within 57-76 Northchurch by agreement and successfully rehoused 13 households on a secure tenancy;  Initial service diversion works have commenced and will be completed in 2018;  The council is continuing to negotiate with all 3 remaining leaseholders within 57-76 Northchurch with the intention to acquire these remaining interests by agreement.

2. That Cabinet resolves to make a Compulsory Purchase Order under Section 226 (1)(a) of the Town & Country Planning Act 1990 for all land and rights within the area of land identified within the plan at Appendix 2 for the purposes of securing the delivery of new homes and community facilities on the site in line with the existing planning consent and thereby securing the regeneration of the Aylesbury Estate in line with the adopted Aylesbury Area Action Plan.

3. That cabinet notes that an update report on further progress towards obtaining vacant possession of the site will be brought to Cabinet before a Compulsory Purchase Order is made.

BACKGROUND INFORMATION

4. The background to the regeneration of the Aylesbury Estate has been covered extensively in previous reports but is summarised here for context.

5. Having spent a number of years investigating plans for refurbishing the estate, it became apparent that the extent and cost of works required to refurbish the estate to an acceptable standard would be prohibitive and would not overcome the fundamental design flaws of the layout of the estate, the Council took the decision in 2005 to redevelop the estate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Plot 18: Scheme BoundaryAppendix 1 1 pages Download
PDF
Plot 18: Appendix 2: CPOAppendix 2 1 pages Download
PDF
Report: Aylesbury Estate: Community facilities at Plot 18 DeliveryReport 16 pages DownloadRead as text

At this meeting

Whole meeting
3Notice of Intention to conduct business in a closed meeting, and any representations receivedOn the agenda 6MinutesApproved 7Deputation RequestsAgreed 82017 Primary and Secondary School Place Planning Strategy UpdateNoted 9Motion of AdjournmentDecided 9Response to Southwark Schools Scrutiny in a DayApproved 10Gateway 1: Procurement strategy approval - Special Educational Needs and Disability (SEND) taxis for children, young people and vulnerable young peopleAgreed 11Introduction of Public Space Protection Orders (PSPOs) to tackle dog related anti-social behaviour (ASB)Approved 12Safe as Houses ? Independent Social Research into Early Impacts of Universal Credit (UC) among Social Housing Tenants in SouthwarkNoted 13Annual Workforce ReportNoted 14New Commissioning Model and Common Outcomes Framework for the Voluntary and Community SectorApproved 15Consideration of Options for Broadband in Rotherhithe and Improving Connectivity in the Borough as a WholeApproved 16New Southwark Plan: Proposed Submission VersionAgreed 17Community Infrastructure Levy and Section 106 Planning Obligations and Community Infrastructure Levy Supplementary Planning DocumentApproved 18A Review of Further Education and Skills Provision in the London Borough of Southwark - Response to Overview and Scrutiny CommitteeNoted 19Gateway 2: Contract Award Approval - Care at Home ContractsAgreed 20Acquisition of Affordable Housing at Longville Road, SE11Approved 21The Outcome of the Consultation Exercise on changes to Day Centre Provision at Queens Road and Riverside and the Development of a Disability HubNoted
22Aylesbury Estate: Community facilities at Plot 18 DeliveryThis decision
23Aylesbury Estate: Approved premises facility (APF) deliveryApproved 25Exclusion of the press and publicDecided 24MinutesPrivate

Who was there

8 of 13 attended
PJ
Councillor Peter John OBEChair, present
SC
Councillor Stephanie CryanCommittee Member, present
MA
Councillor Maisie AndersonCommittee Member, apologies
FC
Councillor Fiona ColleyCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
IW
Councillor Ian WingfieldCommittee Member, apologies
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

All 13 on the meeting page

On this subject at Southwark

Search all
  1. Aylesbury Estate: Community facilities at Plot 18 DeliveryThis decision
  2. Proposed Amendment to Interim Outline Business Case for Aylesbury Estate Private Finance InitiativeDecided
  3. Amending the Rehousing Policy for Homeowners affected by the Regeneration of the Aylesbury EstateDecided
  4. Selection of a Preferred Partner to Work with the Council to Deliver the Regeneration of the Aylesbury EstateApproved
  5. Aylesbury Estate Regeneration Phase 2Agreed
  6. Aylesbury Estate: Approved premises facility (APF) deliveryApproved

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies