What was decided
Cabinet agreed a framework for allocating strategic CIL, with 50% ringfenced for the Bakerloo Line Extension and the rest for match funding of transport projects and infrastructure in the Council Delivery Plan. Report P1, P16, P17
Cabinet allocated £350,000 of strategic CIL as a grant to Network Rail for design work on Elephant and Castle overground station, where total scheme cost is estimated at £18m. Report P2, P21, P44
Cabinet allocated £250,000 of strategic CIL as a grant to TfL for a station design study on the Bakerloo Line Extension, expected to cost £750,000 in total with LB Lewisham contributing £250,000. Report P3, P22, P43
Why
The council has now met its full commitment to the new step free tube station at Elephant and Castle, leaving a surplus of strategic CIL for further transport investment. Report P8, P9, P10, P15
Officers say the framework supports social and economic growth, helps the council's response to the climate emergency, and aligns with Southwark Plan and London Plan policies. Report P18, P19
CIL regulations and section 216(2) of the Planning Act 2008 permit spending on a broad range of infrastructure, including transport, and the council has the discretion to choose what to fund. Report P6, P60, P61, P62
What happens next
Planning and Growth will maintain a running total of strategic CIL allocations to ensure the 50% Bakerloo limit is not breached, with allocations reported in the Annual Infrastructure Funding Statement. Report P23
Further reports will come to Cabinet if later stages of the Bakerloo or Elephant and Castle overground projects need more funding. Report P45
Equalities and health impacts, including under the Public Sector Equality Duty, will be considered further as each project is developed and delivered. Report P22, P34, P58
The money
- £350,000 Strategic CIL grant to Network Rail for Elephant and Castle overground station design work Report P2, P21, P44
- £250,000 Strategic CIL grant to TfL for Bakerloo Line Extension station design study Report P3, P22, P43
- £600,000 Total strategic CIL allocation covered by this decision, per finance officer advice Report P64
- £12.345m Current balance of strategic CIL funds available for allocation Report P15
- £71.5m Total strategic CIL invested to date in the new step free tube station at Elephant and Castle Report P8
- £18m Estimated total scheme cost for Elephant and Castle overground station Report P21, P44
- £750,000 Anticipated total cost of the Bakerloo Line Extension station design study Report P22, P43
- £1m Strategic CIL previously allocated in July 2023 to Southwark Pensioners Centre for refurbishment Report P11
Options considered
- Chosen: Adopt proposed framework: 50% for Bakerloo Line Extension, with balance for match funding of transport projects and Council Delivery Plan infrastructure. Supports borough growth, climate emergency response, and aligns with Southwark Plan and London Plan policies Report P16, P17, P18, P19
Implications
- Financial: Allocations represent an increase in council capital expenditure and will be reflected in the next capital budget monitoring report; both proposals fit within existing strategic CIL balances. Report P45, P46, P66
- Legal: Officers conclude the council may lawfully exercise discretion to allocate strategic CIL to these projects under regulation 59 of the CIL Regulations 2010 and section 216(2) of the Planning Act 2008. Report P60, P61, P62
- Equalities: Officers find the allocations and framework will not have an adverse impact on people with protected characteristics; further equalities assessment will be carried out as projects progress. Report P22, P34, P35, P58
- Climate: Allocations are expected to support the council's climate emergency response by encouraging shift from cars to public transport and enabling sustainable energy solutions in new transport infrastructure. Report P18, P39
- Other: Match funding contributions to partners such as Network Rail and TfL will not exceed 25% of overall scheme cost and are expected to deliver improved design, faster delivery and greater social value. Report P19, P44
Who and where
- Southwark residents and borough-wide transport users, including passengers with mobility issues, heavy luggage or prams using Elephant and Castle overground station Report P21, P28
- Future passengers on the Bakerloo Line Extension Report P22
- People sharing protected characteristics under the Equality Act 2010, including age, disability, race, sex and others Report P33, P35
Timeline
- 14 July 2021: Council Assembly approved a constitution change requiring all decisions to consider climate and equality consequences Report P53
- July 2023: Cabinet previously agreed £1m of strategic CIL for Southwark Pensioners Centre refurbishment Report P11
- 22 February 2024: Final version of this report dated Report P72
- 2026-05-28: Cabinet meeting at which the decision was made
Plain English for the jargon
- CIL: Community Infrastructure Levy, a charge on new development to fund infrastructure
- Strategic CIL: 70% of CIL receipts, used by the council for borough-wide infrastructure projects
- Neighbourhood CIL: 25% of CIL receipts allocated to neighbourhood areas
- PSED: Public Sector Equality Duty under section 149 of the Equality Act 2010
- TfL: Transport for London
- BLE: Bakerloo Line Extension