Draft Annual Governance Statement 2025-26

Noted Finance 2 papers

AI summarySouthwark's Audit, Governance and Standards Committee noted the draft Annual Governance Statement 2025-26 and agreed it should be updated to cover the role of anchor institutions through the anchor network.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAnnual Governance Statement 2025-26 with anchor network reference
MoneyNot stated
What happens nextUpdate the AGS for anchor institutionsReflect role of anchor institutions through the anchor network
Who it affectsCouncil's governance reportingAnnual Governance Statement 2025-26 and its final content

What was decided

The committee noted the draft Annual Governance Statement 2025-26 set out in Appendix A of the report. Report P4

The committee agreed the Annual Governance Statement 2025-26 would be updated to reflect the role of anchor institutions through the anchor network.

Why

The report records that no consultation was carried out on this item. Report P1

The item was a routine governance reporting matter, not a key decision, presented by the Director of Corporate Finance. Report P6

What happens next

The draft Annual Governance Statement 2025-26 is to be revised to add coverage of the role of anchor institutions through the anchor network.

Implications

  • Governance: The final Annual Governance Statement 2025-26 will include a reference to the role of anchor institutions and the anchor network.

Who and where

  • London Borough of Southwark's governance reporting for 2025-26 Report P4
  • The Audit, Governance and Standards Committee, as the body noting the draft Report P6

Timeline

  • 25 June 2026: Final report sent to the Constitutional Team Report P6
  • 13 July 2026: Audit, Governance and Standards Committee considered the draft Annual Governance Statement 2025-26

Plain English for the jargon

  • AGS: Annual Governance Statement, the council's draft statement for 2025-26
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

That the audit, governance and standards committee: 1. note the draft Annual Governance Statement (AGS) 2025-26 as attached at Appendix A of the report. 2. agree that the Annual Governance Statement 2025-26 be updated to reflect the role of anchor institutions through the anchor network.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Audit, Governance and Standards Committee, 3 pages

Meeting Name: Audit, Governance and Standards Committee

Date: 13 July 2026

Report title: Draft Annual Governance Statement 2025-26

Ward(s) or groups affected: All

Classification: Open

Reason for lateness (if n/a applicable):

RECOMMENDATION(S)

1. That the audit, governance and standards committee note the draft Annual Governance Statement (AGS) 2025-26 as attached at Appendix A.

BACKGROUND INFORMATION

2. The Accounts Audit Regulations 2015 require that the annual governance statement be presented to and approved by an appropriate committee of the council. Under the constitution, the audit, governance and standards committee is the body that formally receives the annual governance statement.

3. The 2015 Regulations require the annual governance statement to accompany the signed and dated accounts and to be approved at the same time as the statement of accounts. It is expected that the accounts and final annual governance statement will be presented to the committee for approval in October.

4. Following this approval, the annual governance statement should be signed by the most senior member of the council and most senior officer, who are the leader of the council and the chief executive.

KEY ISSUES FOR CONSIDERATION

5. Every year, each local authority is required by law to conduct a review of the effectiveness of its system of internal control and to publish a statement reporting on the review, the annual governance statement, with its financial statements. The annual governance statement is therefore a mandatory statement that recognises, records and publishes the council’s governance arrangements as defined in the CIPFA/SOLACE framework for good governance in local authorities. It reflects how the council conducts its business, both internally and in its dealings with others. Its objective is to provide assurance on the effectiveness of the corporate governance arrangements and to identify significant governance issues requiring management action.

1 6. The statement is produced following a review of the council’s governance arrangements and system of internal control. The review consists of an evaluation of the council’s governance arrangements against the best practice described in the CIPFA guidelines. This includes an assessment of the systems and processes for:

 establishing the council’s principal statutory obligations and organisational objectives and applying the six CIPFA/SOLACE core principles of good governance  identifying the principal risks to the achievement of the council’s objectives  identifying and evaluating key controls to manage the council’s principal risks  obtaining assurances on the effectiveness of key controls.

7. The assurances on the effectiveness of key controls are obtained throughout the year in the form of internal and external audit and inspection reports, risk management and performance activities. The corporate management team (CMT) formally reviewed the draft statement in May and agreed the draft (appendix 1) to be considered by the audit, governance and standards committee. It will be brought back to a future audit, governance and standards committee for further consideration and final approval. Subject to this approval, it will need to be signed by the leader of the council and the chief executive.

Policy framework implications

8. There are no policy implications in the proposals in this report.

Community, equalities (including socio-economic) and health impacts

Community impact statement

9. This report is not considered to contain any proposals that would have a significant impact on any particular community or group

Equalities (including socio-economic) impact statement

10. There are no direct equalities implications in the proposals in this report.

Health impact statement

11. There are no direct health implications in the proposals in this report.

Climate change implications

12. There are no direct climate change implications in the proposals in this report.

2 Resource implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Annual Governance statement cover reportReport 3 pages DownloadRead as text
PDF
Annual Governance Statement 2025-26Appendix Draft 41 pages Download

At this meeting

Whole meeting

On this subject at Southwark

Search all
  1. Draft Annual Governance Statement 2025-26This decision
  2. Annual Governance Statement 2017-18Agreed
  3. Draft Annual Governance Statement 2017-18Noted
  4. Annual Governance Statement (Final)Approved
  5. Annual governance statement 2015-16Approved
  6. Draft annual governance statement 2015/16Noted

More from Southwark Audit, Governance and Standards Committee

All decisions
MeetingDecisionOutcome
13 Jul 2026 Corporate Anti-Fraud Team and Special Investigations Team Year End Report 2025-26That the audit, governance and standards committee noted the Corporate Anti-Fraud Team (CAFT) and the Special Investi... Noted Open
13 Jul 2026 Southwark360: Six-month progress update on the Enterprise Resource Planning (ERP) Replacement programmeThat the Audit, Governance and Standards Committee noted the six-month progress update on delivery of the Southwark36... Noted Open
13 Jul 2026 External Audit Plan - Southwark Council & Pension FundThat the Audit, Governance and Standards committee: a. Noted the Southwark Council External Audit plan attached at Ap... Noted Open
13 Jul 2026 Internal audit progress report for 2025-26That the audit, governance and standards committee noted the update reports, as attached at Appendix A, including app... Noted Open
13 Jul 2026 Internal Audit - Annual Report & Opinion 2025-26That the audit, governance and standards committee note the update reports, as attached at Appendix A. Noted Open