Southwark Executive approved a £35,375,849 Ledbury Estate contract to convert 65 former private sale homes into council homes, extended APCOA's parking and traffic enforcement contract for three years at £31,500,000 in total, and noted a £40.8m council budget overspend forecast, alongside a new housing allocations scheme and a higher levy on purpose-built student housing.
What the committee will consider, in order, with every paper attached to its item. Community Safety Partnership Strategy 2025-2030 is the main business.
To receive apologies for absence.
In special circumstances, an item of business may be added to an agenda within five clear working days of the meeting.
To note the items specified which will be considered in a closed meeting.
Members to declare any interests and dispensations in respect of any item of business to be considered at this meeting.
To approve as a correct record the minutes of the open section of the meeting held on 20 July 2026
To receive any questions from members of the public which have been submitted in advance of the meeting in accordance with the executive procedure rules. The deadline for the receipt of public questions is, 11:59pm Wednesday 9 September 2026.
To consider any deputation requests. To consider any deputation requests. The deadline for the receipt of deputation requests is 11:59, Wednesday 9 September 2026.
Decision: St James Estate That the deputation request from Sophia McAllister, Gary Danks and Mary Knight residents of St Jame’s Estate, South Bermondsey, be heard. The above resident addressed the Executive and raised their concerns regarding the long term residents being displaced as the consequence of the sale of the of their homes by Notting Hill Genesis (NHG) to BMR. Councillor Reginald Popoola, Executive Member for Council Homes responded to the deputation. Working Housing Group, of the Southwark... Decision page
To approve of the procurement strategy for delivery of The Nest (Open Access Mental Health Service for Children and Young People).
Decision: That the following recommendations as amended be approved; That the Executive: 1. Approves the procurement strategy for The Nest (Open Access Mental Health Service for Children and Young People), involving single supplier negotiation with Groundwork London in the sum of £479,000 per annum for a period of three years, plus a one-year extension option, with a maximum lifetime contract value of £1,916,000, commencing on 1 November 2026. 2. Delegates the award decision to the Strategic Director of... Decision page
To approve the activation of the final contract extension.
Decision: That the following recommendations be approved; That the Executive; 1. Approves the activation of the final contract extension within the ‘parking and traffic and associated services’ contract with APCOA Parking UK Ltd, under which the term of the contract will be extended for a period of three years from 1 June 2027 to 31 May 2030 in the sum of £10,500,000 p.a. and £31,500,000 across the three-year extension period. 2. Delegates authority to the Head of Parking Services and Network Management... Decision page
To Note the adoption of the Southwark Community Safety Partnership Strategy.
Decision: That the following recommendation be noted; That the Executive; 1. Notes the adoption of the Southwark Community Safety Partnership Strategy 2025-2030 by the Southwark Community Safety Partnership Executive, attached as Appendix 1 to the report, and support its implementation across relevant council services and partnership structures. Decision page
To approve Phase 2 of Ledbury Estate Renewal Section 8-12
Decision: That the following recommendations be approved: That the Executive; Approves the variation of the Ledbury Estate Regeneration Contract with Higgins Partnerships 1961 PLC (Higgins) by a total of £35,375,849, from a current contract value of £179,960,999, to a revised contract sum of £215,336,848 (see paragraphs ? 90 to ? 106 for details) in order to meet both contractually required inflationary uplifts and comply with legal requirements as mandated by the Building Safety Act 2022. Approves the... Decision page
To approve the new Southwark Housing Allocations Scheme 2026
Decision: RESOLVED That the following recommendations be approved: That the Executive: 1. approves the new Southwark Housing Allocations Scheme 2026 for implementation, including the following key changes: 2. removing “working in the borough” as an automatic qualification criterion; 3. introducing a five-band structure, with homeless households without additional preference placed in Band D and a new Band E created for households with low housing need; 4. allowing Band E applicants to bid for advertised... Decision page
To approve a revised Community Infrastructure Levy (CIL) Charging Schedule for purpose-built student accommodation.
Decision: That the following recommendations be approved: That the Executive; 1. Accept the recommendations of the Regulation 23 Inspector’s report for a revised student CIL rate for purpose-built student accommodation (PBSA) following the Examination in Public. 2. Adopt the updated CIL Charging Schedule which includes the increased student CIL rate for purpose-built student accommodation for CIL zones 1 and 2 with immediate effect. The CIL Charging Schedule is in Appendix 1 of the report. Decision page
To note the financial position of the General Funding.
Decision: That the following recommendations be noted: 1. The adverse variance of £40.8m forecast for the General Fund (GF) in 2026-27 subject to the application of reserves (paragraphs 14-81) 2. The key adverse General Fund variations and budget pressures and mitigating actions underlying the position (paragraphs 14-16) 3. The Housing Revenue Account (HRA) forecast of an adverse variance of £0.5m. (Paragraphs 82-103) 4. The Dedicated Schools Grant (DSG) in-year adverse variance of £5.9m (paragraphs... Decision page
To note the forecast position of the capital programme
Decision: That the following recommendations be noted: 1. The Month 4 2026-27 forecast spend and financing for the General Fund and the Housing Investment Programme (HIP), together with the ten-year capital programme forecasts. 2. The borrowing requirement of £479.7m for the HIP to be fully delivered over the remaining term of the programme as detailed in Table 1 of this report. 3. The borrowing requirement of £221m for the General Fund to be fully delivered over the remaining term of the programme, as... Decision page
To consider the Education and Local Economy Scrutiny Commission report and recommendations.
Decision: That the following recommendations be noted: 1. That the Executive notes the recommendations from the Education and Local Economy Scrutiny Commission arising from its 2025–26 scrutiny work on education (pupil place planning), youth services, Southwark Safeguarding Children Partnership (SSCP), Special Education Needs and Disabilities (SEND) transport and school organisation, as set out in the report. 2. That the Executive considers the recommendations from the education and local economy... Decision page
To consider the Education and Local Economy Scrutiny Commission report and recommendations.
Decision: That the following recommendations be noted: 1. That the Executive notes the recommendations from the Education and Local Economy Scrutiny Commission arising from its 2025–26 scrutiny work on East Street Market, Commercial Property Management, CTW, Support for Businesses and Apprenticeships , as set in the report. 2. That the Executive considers the recommendations from the education and local economy scrutiny commission and request that the relevant Executive member reports back to Executive... Decision page
Item 10 is where most of this meeting's papers sit: 3 papers, about 6.1 MB.
To Note the adoption of the Southwark Community Safety Partnership Strategy.
This committee has dealt with the subject before.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 36 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 20 July 2026. 7 of its items lead into this meeting; 5 items are new. Point at any item to follow a thread. Procedural items are left out.
Deputation requests, Affordable, safe and green- The Joint Administration's ambition for Southwark, Local Plan Timetable 2026-2029, Appointments to Outside Bodies 2026-27 and 3 more do not return this time.
See the 20 July meetingEvery Executive meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Southwark, Executive
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Executive, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.