Resolved
Resolved that the Committee Work Programme for the forthcoming Municipal year 2016-17, be approved.
Audit Committee approved this item on Thursday 24 March 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the Committee Work Programme for the forthcoming Municipal year 2016-17, be approved.
WORK PROGRAMME 2016 – 2017
AUDIT COMMITTEE – 24 MARCH 2016
Resolution Required
1. Work Programme 1.1 This report covers the Work Programme for the current and forthcoming municipal year 2015/16 and 2016/17. 1.2 The Committee’s terms of reference are set out at the front of the agenda. 2. Current Work Programme 2.1 This is the last meeting of the Committee scheduled for the municipal year 2015/16.
2.2Meetings of this Committee have been scheduled in the Council’s Diary for 2016/17 on the following dates:- June 2016 (date to be amended) 29 September 2016
2.3Details of the Work Programme for the next meetings are as follows:
March 2016 Corporate Risk Management Audit Manager Review Corporate Risk Register Head of Service - as appropriate Updates on target dates missed Anti-fraud, corruption and Internal Audit Manager Review bribery policy Committee’s Work programme Internal Audit Manager / Chief Report for 2015/2016 Finance Officer/Audit Committee External Audit Annual Audit External Audit Report Letter Internal Audit Annual Plan Internal Audit Manager Report Confidential Reporting Code Internal Audit Manager Review Committee’s Work programme Internal Audit Manager / Chief Report for 2016/2017 Finance Officer/Audit Committee
June 2016 External Audit Plan External Audit Report Corporate Risk Management Audit Manager Review Corporate Risk Register Head of Service - as appropriate Updates on target dates missed Audit Services Annual Report Internal Audit Manager Report Committee’s Work programme Internal Audit Manager / Chief Report for 2016/2017 Finance Officer/Audit Committee
September 2015 Corporate Risk Management Internal Audit Manager Review Corporate Risk Register Head of Service - as appropriate Updates on target dates missed Annual Governance Chief Finance Officer Approval Statement External Audit report on Audit Internal Audit Manager Report and Statement of Accounts Report on The Effectiveness Internal Audit Manager Report of the System of Internal Audit External Audit Annual Audit External Audit Report Letter Internal Audit Interim Report Internal Audit Manager Report Committee’s Work programme Internal Audit Manager / Chief Report for 2015/2016 Finance Officer/Audit Committee
2.4Any topics identified during consideration of the business at this meeting, will need to be included in the above Work Programme. 2.5 Other issues Members wish to raise for consideration at the next or any future meeting and agreed by the Committee, may be included in the Work Programme. 2.6 External audit may have one or two reports that arise from time to time which are not possible to predict in advance but will be incorporated into the Work Programme or appear on the agenda as appropriate. 2.7 Managers may be required to attend the Committee, similarly to that resolved in Minute No. 227/06, to explain why they have not implemented the recommendations of the Head of Audit Services. It is not possible to predict these circumstances but they will be dealt with as and when they arise either by incorporating into the Work Programme or appearing on the agenda as appropriate. 3. Resolution The Committee is asked to consider and approve the Work Programme as submitted and/or amended at the meeting.
Contact: Punita Talwar, Internal Audit Manager (01784) 446454.
Report Author: Samuel Nicholls, Committee Manager (01784) 446240
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Committee Work ProgrammeReport | 223 KB | DownloadRead as text |
Follow Audit Committee at Spelthorne and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jul 2026 | Committee Forward PlanThat the forward plan be agreed. | Agreed | Open |
| 23 Jun 2026 | External Audit PlanThat the 2026/27 be noted. | Noted | Open |
| 23 Jun 2026 | Internal Audit ConclusionThat the Annual Internal Audit Opinion and Report be noted. | Noted | Open |
| 23 Jun 2026 | Monitoring of Revised Improvement and Recovery PlanThat the update and the governance arrangements in place to monitor delivery of the Improvement and Recovery Programm... | Noted | Open |
| 23 Jun 2026 | Draft Annual Governance StatementThat the Annual Governance Statement 2024/25 be approved for inclusion within the draft Statement of Accounts, subjec... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.