Resolved to: Note the forecast outturn for 2020/21 as at 31 March 2021, and approve the following: 1. Appropriation of the special projects underspend to an earmarked reserve of £0.497m to enhance the Budget provision available to support Green/Climate Change initiatives. 2. Appropriation of the special projects underspend to an earmarked reserve of £0.9m to enhance the Budget provision available to support Green Belt Fighting Fund initiatives. 3. The £0.453m revenue carry forwards for 2021/22 as detailed in Appendix C. 4. Transfer of £0.538m surplus from retained business rates to business rates equalisation reserve. 5. Transfer £0.776m to the general fund. 6. To set aside £0.094m for Sunbury Swimming Pools repairs. Noting that by approving items 1 to 6 above the surplus for the year would be reduced to £0, in other words a balanced outturn, and that the total useable reserves were £55m as at 31 March 2021. Reasons for decision: To utilise the forecast underspend of £3.48m and deliver a balanced outturn.
Word for word from the decision Spelthorne published for this meeting.Source: democracy.spelthorne.gov.uk
Title Revenue Monitoring Report 2020/21 as at 31 March 2021 Purpose of the report To note and to make a decision Report Author Paul Taylor – Chief Accountant Cabinet Member Councillor Sati Buttar Confidential No Corporate Priority Financial Sustainability Recommendations Cabinet to note the forecast outturn for 2020/21 as at 31 March 2021 and approves the following recommendations 1. appropriation of the special projects underspend to an earmarked reserve of £0.497m to enhance the Budget provision available to support Green/Climate Change initiatives. 2. appropriation of the special projects underspend to an earmarked reserve of £0.9m to enhance the Budget provision available to support Green Belt Fighting Fund initiatives. 3. the £0.453m revenue carry forwards for 2021/22 as detailed in Appendix C. 4. transfer of £0.538m surplus from retained business rates to business rates equalisation reserve. 5. transfer £0.776m to the general fund 6. set aside £0.094m for Sunbury Swimming Pools repairs
Noting that by approving items 1 to 6 above the surplus for the year would be reduced to £0.0m, in other words a balanced outturn and that our total useable reserves will be £55m as at 31 March 2021.
Reason for Not applicable Recommendation
Key issues 1.1. This report provides a summary of the forecast outturn position for the financial year 2020-21 as at 31 March 2021, which is an underspend of £3.26m, this is an increase of £1.92m on the December 2020 forecast underspend of £1.36m. This is in large part due to the (£1.39m) under spend on the Projects Delivery fund and (£0.5m) under spend on the set aside.
Version: 1, Last saved: 11/05/21 18:44 1.2. The report considers the Council’s financial position in the light of the COVID- 19 pandemic. It should be noted that the COVID-19 pandemic has created a dynamic environment leading to continuous change to plans and figures. The current environment is constantly changing in relation to events, plans and programmes. As a result of this it is inevitable that there will be changes over time in financial information, forecasts and reports to Members.
1.3The key variances are summarised in the table below, with a more detailed information on the variances by portfolio shown in section 2.
1.4The impact of COVID-19 is shown as an underspend of £1.492m, this considers the Supplementary Revenue Estimate which was approved by Council. This means that the Council will not need to apply any of the £2.2m supplementary estimate, funded from reserves, that was approved by Council on 21st May and a recommendation has been made to establish an earmarked reserve for COVID-19 in 2021/22 with the unused funds. Non COVID-19 expenditure is showing an underspend of £1.990m. 1.5. COVID-19 Uncertainties – The table shows the impact of COVID-19 on those areas affected. Appendix A and B show an additional breakdown of the forecast impact of COVID-19 on each area within the Council’s General Fund budget. The forecast overspends are based on discussions with Budget Managers and are based on knowledge available to Budget Managers and should be a realistic and prudent assessment. However, it should be recognised that it is difficult for Managers to form a judgement on circumstances which are currently very fluid. There are several unknowns such as when the lockdown and measures on social distancing will end and importantly when a return to normal activity will occur.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.