The Committee resolved to agree to support in principle progressing a solar canopy scheme for the ‘Eclipse Leisure Centre’ car park.
Corporate Policy and Resources Committee agreed this item on Monday 8 July 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee resolved to agree to support in principle progressing a solar canopy scheme for the ‘Eclipse Leisure Centre’ car park.
Corporate Policy and Resources Committee
8th of July 2024
Title Implementation of a Solar Canopies over the ‘Eclipse’ Leisure Centre Carpark Purpose of the report To make a decision Report Author Timothy Snook, Sustainability and Flood Risk Officer Ward(s) Affected Staines Exempt Report and Appendix D – No Appendices A-C - Yes Exemption Reason Appendices A-C contain exempt information within the meaning of Part 1 of Schedule 12A to the Local Government Act 1972, as amended by the Local Government (Access to Information) Act 1985 and by the Local Government (Access to Information) (Variation) Order 2006 Paragraph 3 – Information relating to the financial or business affairs of any particular person (including the authority holding that information) Corporate Priority Resilience Environment Services Recommendations Committee is asked to: 1. To support progressing a solar canopies scheme 2. To confirm whether the preference is for steel or glulam structure. 3. To authorise proceeding with the procurement of a solar canopy scheme and to authorise the Group Head of assets to carry out the procurement in accordance with Contract Standing Orders. 4. To recommend to Council that the expenditure be funded by one of the options and if a capital expenditure option is preferred that a supplementary capital estimate of £1.4m to £1.8m (depending on option) be approved by Council. 5. Depending on 4 above authorise officers to progress application for Community Infrastructure Levy (CIL) funding and explore other potential funding routes, for example Capital borrowing or through a PPA as specified in section 4. 6. To authorise the Group Head of Assets to apply for planning permission in accordance with Regulation 3 of the Town and Country Planning General regulations 1992. 7. To authorise the Group Head of Corporate Governance to enter into any necessary documentation in connection with the project. Reason for The Solar Canopy will realise a potential carbon saving of 137 Recommendation tCO2e/annum (tonnes of CO2 equivalent) and through either financing option selected will represent a considerable cost saving to the operation of the ‘Eclipse’ Leisure Centre over its lifetime. Additionally, it could form an avenue of revenue generation through the selling of electricity generated to the leisure centre operator.
1. Summary of the report
What is the situation Why we want to do something
• The current leisure centre plans • This will enable the generation of include a carpark of around 300 clean, renewable, local energy to spaces. power the ‘Eclipse’ centre. • There is the potential to construct • This will represent an electricity cost an array of solar panels above this an annual saving of an estimated carpark, without losing spaces. £5,520,000 over its lifetime and a • There is opportunity to create a carbon saving of 137 tonnes/annum. complementary project to the • It will be in keeping with the Passivhaus leisure centre, that Council’s commitment to tackling the supports the sustainability climate emergency and would neatly credentials. complement the standards set by the Passivhaus development.
This is what we want to do about it These are the next steps
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Additional Information /24Appendix D | 337 KB | Download |
PDF |
Implementation of Solar Canopies Over the 'Eclipse' Leisure Centre Car ParkReport | 701 KB | DownloadRead as text |
PDF |
MAT and Committee Report Solar Carpark Leisure Centre Final amended /24Report | 702 KB | Download |
Follow Corporate Policy and Resources Committee at Spelthorne and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2026 | Write Offs - Sundry Debts and Housing BenefitsCommittee resolved to approve the write-offs set out in the Appendix 1 and 2 of the report which totalled £52,026 and... | Approved | Open |
| 12 Oct 2026 | Proposed ICT Server ProcurementThe Committee resolved to: 1. Authorise the Council’s ICT Manager to commence a procurement process for the purchase ... | Decided | Open |
| 12 Oct 2026 | Governance Assurance Update - EDI and Financial ManagementThe Committee resolved to: 1. Note the current overall assurance level for the Governance Assurance Areas under the r... | Noted | Open |
| 12 Oct 2026 | Annual Commercial Property Report for Financial Year 2025/26The Committee received the Annual Commercial Property Report for Financial Year 2025/2026. The Committee resolved to:... | Approved | Open |
| 12 Oct 2026 | Procurement of resource to support the LGR transition and transformation processThe Committee resolved not to approve the procurement to modify the contract of the Head of LGR and Special Projects ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.