Corporate Policy and Resources Committee agreed this item on Tuesday 15 October 2024. Below is the council's own wording, with the papers it was decided on.
The Committee resolved to agree to allow a local business sponsor to carry out repairs and maintenance at no cost to the Council for a minimum of three years; and Delegate authority to the Group Head of Corporate Governance to agree the terms and enter necessary documentation
Word for word from the decision Spelthorne published for this meeting.Source: democracy.spelthorne.gov.uk
Report to Corporate Policy and Resources Committee
Corporate Policy and Resources Committee
Tuesday 15 October 2024
Title Reflections water feature Purpose of the report To make a decision Report Author Jackie Taylor Group Head Neighbourhood Services Ward(s) Affected All Wards Exempt No Exemption Reason Not applicable Corporate Priority Community Recommendations Committee is asked to: Agree one of the four options listed at point three within this report under the heading of “options analysis.” Delegate authority to Group Head Corporate Governance to agree the terms and enter necessary documentation should members agree to move forward with Option 2. Reason for The Reflections water feature which forms an extension to the Recommendation Staines War Memorial is not operational due to the plant room being flooded. A potential business sponsor has indicated that his company is willing to repair and then maintain the feature for at least the next three years at no cost to the Council. Councillors are asked to decide on the future maintenance of the Reflections water feature which is in market square Staines-upon Thames.
1. Summary of the report
What is the situation Why we want to do something
• The Reflections water feature provides an • A business sponsor has come forward additional feature to the War Memorial in offering to carry out repairs and finance market square Staines-upon-Thames. The ongoing maintenance on the feature at no water tables in this area are extremely cost to the Council. The Councill needs to high due to its proximity to the River decide if this is an appropriate course of Thames. The plant room that runs the action. This offer is for a minimum of three feature is underground and suffered from years. flooding in 2020, since then it has not been in operation. This is what we want to do about it These are the next steps
• This report will provide the detail to • Detailed information on the status of the members allowing them to make a fully feature is provided within this report for informed decision on whether to allow the members to decide on the future of the feature to be managed by an external water feature. sponsor with no cost to the Council.
1.1This report seeks to provide information on the sponsorship offered by a Spelthorne property owner. The owner has offered to carry out repairs and pay for ongoing maintenance for at least the next three years on the Reflections water feature which is situated within market square Staines- upon-Thames. 2. Key issues 2.1 The water feature has been in a non-operational state since flooding occurred resulting in a significant rise of water in the River Thames. This rise in water levels flooded the underground plant room of the water feature. 2.2 The water feature until this time had been managed and maintained via an external contractor by the Building Services team within Assets. 2.3 Due to the high repair and maintenance costs and the Council’s challenging budget situation the feature has not been repaired and subsequently does not work as a water feature. 2.4 A company who owns land adjacent to market square and near the water feature have offered to sponsor the repairs & ongoing maintenance for at least the next three years with no cost to the Council. 2.5 Councillors are asked to consider the contents of this report and decide if this is an appropriate way to manage this feature. 2.6 The table below provides further details of the work and costs associated with the repair and future yearly maintenance of the feature. Estimated repair Plant room & water feature repairs costs £16,000 Pumping out and cleaning the plant room Replace the glass reinforced plastic (GRP) tank. Clean & service pumps/float valves etc. Associated electrical works £5000-£10,000 Repairs to surface and edging blocks Repair leaks between blocks £21,000 to £26,000 Total estimated repair costs Annual maintenance Plant room & water feature maintenance costs schedule
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate Policy and Resources Committee at Spelthorne and we tell you when its next papers are published, before the meeting rather than after it.
Proposed ICT Server ProcurementThe Committee resolved to: 1. Authorise the Council’s ICT Manager to commence a procurement process for the purchase ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.