Spelthorne Borough Council
Corporate Policy and Resources Committee, Monday 9 December 2024 at 7.00pm

Replacement of Mechanical & Electrical Plant at Sunbury Leisure Centre

Approved Committee 3 papers

Corporate Policy and Resources Committee approved this item on Monday 9 December 2024. Below is the council's own wording, with the papers it was decided on.

Item147/24

Resolved

The Committee resolved to: 1. Approve a net budget of up to £739,000 to undertake improvement mechanical and electrical plant replacement works at Sunbury Leisure Centre, 2. Approve a contingency budget in the amount that equals 10% of the total project cost, 3. Delegate authority to the Group Head of Assets in consultation with the Chair and Vice Chair of the Corporate Policy & Resources Committee to agree requests for expenditure from the contingency budget, 4. Delegate authority to the Group Head of Assets in consultation with the Chair and Vice Chair of Corporate Policy & Resources Committee to appoint the preferred bidder as set out in this report to undertake the mechanical and electrical plant works; and 5. Delegate authority to the Group Head of Corporate Governance to enter into necessary legal documentation to formalise the appointment of the Contractor.
Word for word from the decision Spelthorne published for this meeting. Source: democracy.spelthorne.gov.uk

Follow this further

Built from Spelthorne's papers

What the report saysPro

Report to Corporate Policy and Resources Committee

Tender Stage - Outline Programme - 18/11/24 Sunbury Leisure Centre - AHU, BMS Replacement and Electrical Upgrades

Week No. Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 1 C lients’ instruction to proceed. 2 Contractor’s site set up / lead in period. 3 Surveys, validations and reporting period. 4 Detailed design period. 5 Agreement of final scope of works 6 Procurement period. 7 Preperation Works prior to delivery of AHUs 8 Delivery of AHU's 9 Enabling Works for Pool AHU Replacement 10 Replacement of Pool & Wet Changing AHUs & Associated MCCP 11 Commissioning/Testing of Pool MCCP 12 Enabllnig Works for remaining AHUs replacement 13 Replacement of remaining AHU's and Associated MCCP 14 Commissioning/Testing of AHUs and Associated MCCP 15 Replacement of Boiler Room MCCP 16 Testing and Commissioning of Boiler Room MCCP 17 Issue of O&M’s and record drawings. 18 Client training 19 Snagging / De-Snagging. 20 Project Completion. 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Confidential 19/11/2024 Page 1

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2440 Outline Programme /24Report 63 KB DownloadRead as text
PDF
Replacement of Mechanical & Electrical Plant at Sunbury Leisure CentreAgenda 467 KB Download
PDF
View item 147/24 as HTML 62 KBAgenda 62 KB Copy on its way

At this meeting

Whole meeting

Who was there

15 of 22 attended
JS
Councillor Joanne SextonChair, present
CB
Councillor Chris BatesonVice-Chair, present
MB
Councillor Malcolm BeecherCommittee Member, present
JB
Councillor John BoughtflowerCommittee Member, present
JB
Councillor Jon ButtonCommittee Member, present
SD
Councillor Sue DoranCommittee Member, present
RG
Councillor Rebecca GeachCommittee Member, present
MG
Councillor Michele GibsonCommittee Member, present
KG
Councillor Kathy GrantCommittee Member, present
KH
Councillor Karen HowkinsCommittee Member, present
NI
Councillor Naz IslamCommittee Member, present
ML
Councillor Matthew LeeCommittee Member, apologies

All 22 on the meeting page

More from Spelthorne Corporate Policy and Resources Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Write Offs - Sundry Debts and Housing BenefitsCommittee resolved to approve the write-offs set out in the Appendix 1 and 2 of the report which totalled £52,026 and... Approved Open
12 Oct 2026 Proposed ICT Server ProcurementThe Committee resolved to: 1. Authorise the Council’s ICT Manager to commence a procurement process for the purchase ... Decided Open
12 Oct 2026 Governance Assurance Update - EDI and Financial ManagementThe Committee resolved to: 1. Note the current overall assurance level for the Governance Assurance Areas under the r... Noted Open
12 Oct 2026 Annual Commercial Property Report for Financial Year 2025/26The Committee received the Annual Commercial Property Report for Financial Year 2025/2026. The Committee resolved to:... Approved Open
12 Oct 2026 Procurement of resource to support the LGR transition and transformation processThe Committee resolved not to approve the procurement to modify the contract of the Head of LGR and Special Projects ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies