Corporate Policy and Resources Committee, Monday 13 October 2025 at 7.00pm

Procurement support from Runnymede Borough Council

Agreed Committee 4 papers

AI summarySpelthorne's Corporate Policy and Resources Committee agreed in principle to accept procurement support from Runnymede Borough Council. The initial six-month phase will cost up to £33,000, paving the way for a full shared service by April 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedPhase 1 in principle, delegation to officers
Money£33,000 initial call offUp to 60 days at about £550 per day
What happens nextPhase 1 then full shared serviceSeptember 2025 to March 2026, then April 2026
Who it affectsProcurement service and buyersSBC procurement team, buying managers, RBC Head of Procurement

What was decided

The Committee agreed in principle to enter into a relevant agreement to support Phase 1 as set out in Appendix A. Report P1

Authority was delegated to the Group Head Corporate Governance and S151 Officer, with the Chair and Vice Chair, to finalise the proposal details.

Authority was delegated to the Group Head Corporate Governance to enter into the agreement and all ancillary documentation for Phase 1.

Why

SBC contacted RBC in early June 2025 after the resignation of SBC's corporate procurement manager, seeking joint working options. Report P3, P4

Both councils are expected to fall within the same unitary under Local Government Reorganisation, making a single aligned procurement service logical. Report P6

Previous consultancy advice indicated that aligning processes and policies must come before amalgamation for a shared service to succeed. Report P6

What happens next

Phase 1 will run from September 2025 to March 2026, covering policy review, staff training, contracts register work and ongoing technical support. Report P18, P7, P9, P10

A progress review in month 3 and further reviews will lead to preparation for full service delivery from 1 April 2026. Report P18, P21, P25

Clear gateways must be agreed before progression to Phase 2, including decentralised model transition, full CSO alignment, and use of the In-Tend e-tendering system. Report P14

The money

  • £550 per day Indicative day rate for RBC Head of Procurement work Report P15
  • £33,000 Initial call off sum for up to 60 days over 6 months, invoiced quarterly in arrears Report P15
  • 60 days Suggested maximum number of days over the first 6-month period, capped at 3 per week Report P15

Options considered

  • Chosen: Phased approach with groundwork before full amalgamation. Allows building blocks such as aligned CSOs, upskilled staff, and standardised templates to be put in place first Report P5, P6
  • Rejected: Immediate full service integration. Consultancy advice indicated that aligning processes and policies must come first to ensure success Report P6
  • Chosen: Adopt RBC's recently revised Contract Standing Orders as a quick win. They are consistent with the Procurement Act 2023 Report P15

Implications

  • Financial: SBC will pay a proportion of costs for Phase 1 via a fixed day rate and tracked days, with possible extra cost from changing e-tendering systems. Report P15
  • Staffing: Spelthorne retains day-to-day line management of its two existing procurement staff; RBC's Head of Procurement provides technical and professional oversight. Report P12
  • Legal: Each party must hold appropriate public liability, employee liability and professional indemnity insurance. Report P17
  • Risk: SBC is likely to continue needing additional external support for procurement exercises until wider staff are upskilled. Report P12
  • Other: SBC will move to the In-Tend e-tendering system used by RBC to align processes and guidance. Report P12, P14

Who and where

  • SBC procurement team (2 members of staff) Report P12
  • Buying managers across Spelthorne who will be trained in decentralised procurement Report P9
  • RBC's Head of Procurement, who will spend up to 3 days per week on SBC work Report P11, P13

Timeline

  • 3rd July 2025: Initial meeting between SBC and RBC officers to discuss support options Report P3
  • 8th July 2025: Draft outline proposal shared Report P4
  • 11th July 2025: Comments on the draft outline proposal received Report P4
  • Sept 25 to Mar 26: Phase 1 delivery period Report P18
  • Jan 26, Mar 26: Preparation for Phase 2 Report P18
  • 1st April 26: Full service delivery to be in place Report P18

Plain English for the jargon

  • LGR: Local Government Reorganisation
  • CSOs: Contract Standing Orders
  • S151 Officer: Statutory Chief Finance Officer, designated under section 151 of the Local Government Act
  • BAU: Business as usual
  • e-tendering: Electronic system for managing procurement tender processes
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item100/25

Resolved

Committee resolved to: 1. Agree in principle to enter into a relevant agreement to support Phase 1 of the proposal as set out in Appendix A, 2. Delegate authority to the Group Head Corporate Governance and S151 Officer, in consultation with the Chair and Vice Chair of the Corporate Policy and Resources Committee, to finalise the details of the proposal; and 3. Delegate authority to the Group Head Corporate Governance to enter into the agreement and all ancillary documentation relating to Phase 1 of the proposal set out in Appendix A.
Word for word from the decision Spelthorne published for this meeting. Source: democracy.spelthorne.gov.uk

Follow this further

Built from Spelthorne's papers

What the report saysPro

Report to Corporate Policy and Resources Committee

Outline proposal for the provision of Procurement support from Runnymede Borough Council to Spelthorne Borough Council

Outline proposal for discussion / agreement Date: 26th August 2025 Purpose: To provide an outline scope of proposed working arrangements for the provision of Procurement Support from Runnymede Borough Council (RBC) to Spelthorne Borough Council (SBC), setting out a phased approach to integration of Procurement services, high level objectives of the proposal, and the key responsibilities of each party.

Background: SBC contacted RBC in early June 2025 to explore joint working opportunities following the resignation of SBC’s corporate procurement manager. An initial meeting was held to share information and discuss possible support on 3rd July (Attendees: Linda Heron, Group Head Corporate Governance and Monitoring Officer (SBC), Amanda Fahey, Assistant Chief Executive and s151 Officer (RBC) and Amy Gibson, Head of Procurement (RBC)).

Based on the conclusions arrived at during the meeting, a draft outline proposal was shared 8th July, to which comments were received 11th July. RBC staff commenced drafting of a fuller proposal during which time requirements were clarified that the end product of the collaboration would be to see RBC delivering the procurement function for SBC.

A further meeting was held (same attendees as above) to discuss the approach. A phased approach was considered which would allow for all the building blocks to be put in place to enable RBC to take on the procurement service for SBC. This would involve much of what was in the original proposal but with a move to full service provision once the prerequisites were in place, such as aligning contract standing orders (CSOs), upskilling buying managers to ensure decentralisation of procurement up to certain financial limits, standardisation of templates and procedures and provision of technical support to SBC’s current procurement team.

In all scenarios, Spelthorne and Runnymede would lie within the same unitary under Local Government Reorganisation (LGR) so it makes sense to align to a single service. Consultancy advice previously received by RBC when looking at the potential for a shared procurement service elsewhere in Surrey, which was not progressed, was that it is essential for success to lay this groundwork first, aligning process and policies before amalgamation.

The Proposal: Phase 1: 1. Review of policies / intranet pages / proformas / toolkit  Alignment of CSOs to RBC’s which were revised in May 2025.  RBC are in the process of introducing a Procurement Toolkit and updating all templates. These should be adopted across both authorities, with as little variation as possible.

1  Review Procurement Strategy and associated policies and align to RBC.

2. Training/Upskilling of staff to fully employ decentralised procurement model up to agreed financial limits and enable buying managers to run their own procurement exercises  Training on e-tendering system, including user guides  Training on Procurement Act changes, Contract Standing Orders and processes.  Rollout of Procurement Toolkit and standard templates including Request for Quote template  Training in Contract Management

3. Procurement Team  RBC to provide technical support to SBC team for procurement issues.  RBC to support a review of the Contracts Register – essential both for internal processes and in preparation for LGR.  RBC / SBC staff to ensure opportunities for joint procurement are identified and progressed  Support spend analysis to identify where spend is not on contract or not included in the Contracts Register. Determine frequency of review for contracts register / spend analysis  SBC team to provide details of staff to be trained, assist in creation of documents and provide feedback on policies and templates.

4. BAU/Project support  RBC’s Head of Procurement to provide support for higher value/more complex procurement projects.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement Proposal August 2025 /25Report 256 KB DownloadRead as text
PDF
Procurement support from Runnymede Borough CouncilReport 460 KB Download
PDF
View as HTML (100/25/2) 50 KBReport 50 KB Copy on its way
PDF
View item 100/25 as HTML 64 KBReport 64 KB Copy on its way

At this meeting

Whole meeting

Who was there

14 of 27 attended
JS
Councillor Joanne SextonChair, present
CB
Councillor Chris BatesonVice-Chair, present
MA
Councillor Maureen AttewellCommittee Member, present
MB
Councillor Malcolm BeecherCommittee Member, present
JB
Councillor John BoughtflowerCommittee Member, apologies
JB
Councillor Jon ButtonCommittee Member, present
DC
Councillor Darren ClarkeCommittee Member, present
SD
Councillor Sue DoranCommittee Member, present
RG
Councillor Rebecca GeachCommittee Member, present
MG
Councillor Michele GibsonCommittee Member, present
KG
Councillor Kathy GrantCommittee Member, present
KH
Councillor Karen HowkinsCommittee Member, apologies

All 27 on the meeting page

On this subject at Spelthorne

Search all
  1. Procurement support from Runnymede Borough CouncilThis decision
  2. Procurement of resource to support the LGR transition and transformation processApproved
  3. Procurement of resource to support the preparation of an evidence-based Housing Delivery PlanApproved
  4. Procurement of Environmental Health Senior Management SupportApproved

More from Spelthorne Corporate Policy and Resources Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Write Offs - Sundry Debts and Housing BenefitsCommittee resolved to approve the write-offs set out in the Appendix 1 and 2 of the report which totalled £52,026 and... Approved Open
12 Oct 2026 Proposed ICT Server ProcurementThe Committee resolved to: 1. Authorise the Council’s ICT Manager to commence a procurement process for the purchase ... Decided Open
12 Oct 2026 Governance Assurance Update - EDI and Financial ManagementThe Committee resolved to: 1. Note the current overall assurance level for the Governance Assurance Areas under the r... Noted Open
12 Oct 2026 Annual Commercial Property Report for Financial Year 2025/26The Committee received the Annual Commercial Property Report for Financial Year 2025/2026. The Committee resolved to:... Approved Open
12 Oct 2026 Procurement of resource to support the LGR transition and transformation processThe Committee resolved not to approve the procurement to modify the contract of the Head of LGR and Special Projects ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies