Corporate Policy and Resources Committee, Tuesday 17 February 2026 at 7.00pm

Q3 Capital Monitoring Report

Approved Committee 4 papers

AI summarySpelthorne's Corporate Policy and Resources Committee approved the Q3 2025/26 capital programme monitoring report, noting a £0.238m overspend to be covered by earmarked reserves, with no borrowing required.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedQuarter 3 2025/26 Capital Programme Budget Monitoring Report
Money£0.238m overspendTo be covered by earmarked reserves, no borrowing
What happens nextFinal outturn report at year endFigures subject to change until year end
Who it affectsCouncil's Capital ProgrammeRevised gross programme budget of £9.145m

What was decided

The Committee approved the Q3 2025/26 Capital Programme Budget Monitoring Report, showing a £0.238m overspend to be covered by earmarked reserves.

No part of the capital programme is to be funded by borrowing; funding comes from grants, capital receipts, Community Infrastructure Levy and earmarked reserves. Report 3.3, 5.2

Why

The Council has a statutory duty to make arrangements for proper administration of its financial affairs and to monitor capital expenditure. Report 4.1

The Committee has a responsibility under the Constitution to keep the budget under review and make recommendations concerning the budget to the Council. Report 4.2

Regular monitoring and reporting enable timely decisions and improve financial control within the Council. Report P17

What happens next

A final outturn report will be provided at year end, as figures remain subject to change. Report 5.2

Risks of slippage and increased costs will continue to be managed through regular programme reviews led by a senior officer.

The money

  • £0.238m Overspend on the capital programme to be covered by earmarked reserves
  • £238k Net overspend against revised budget Report 5.1
  • £0.169m Net gross projected decrease in expenditure since Q2 Report 5.1
  • £9.145m Revised Capital Gross Programme budget Report 5.1

Options considered

  • Chosen: Cover the £0.238m overspend using earmarked reserves. No external borrowing is forecast; reserves, grants, capital receipts and Community Infrastructure Levy are used instead Report 5.2
  • Rejected: Fund the capital programme through borrowing. The report states there is no request to fund any part of the capital programme by use of borrowing Report 3.3

Implications

  • Financial: An overspend of £0.238m against the revised capital budget is to be met from earmarked reserves, with no borrowing required. Report 5.2
  • Risk: Key risks relate to rising construction costs from inflation on materials and labour; contracts are being monitored and corrective action taken where needed. Report 2.1
  • Risk: Risk of failing to deliver the Capital Programme is mitigated through regular reviews led by a senior officer, with slippage the main cause.
  • Legal: The decision supports the Council's statutory duties under the Local Government Act 1972 and the Local Government Act 2003. Report 4.1
  • Climate: The Programme includes projects supporting energy efficient buildings, sustainable and green infrastructure, and energy efficient street lighting. Report 9.2
  • Equalities: Equality, diversity and inclusion are central to the Council's work and are woven throughout its Corporate Plans. Report P14
  • Other: Underspend on completion of a project can be reinvested to generate treasury management income or support further capital schemes. Report 3.2

Who and where

  • Spelthorne Borough Council's Capital Programme
  • Council service project leads managing capital schemes
  • The Management Team (MAT), for escalated scheme risks

Timeline

  • 27 February 2025: Detailed Capital Programme Report for 2025-26 approved at Council meeting Report P19
  • End of December 2025: Q3 monitoring position (to this date) reported to Committee
  • Year end: Final outturn report to be provided Report 5.2
  • 29/01/26: S151 Officer commentary completed Report P24
  • 10/02/26: Monitoring Officer commentary completed Report P24

Plain English for the jargon

  • Capital Programme: The Council's planned spending on long-term assets such as buildings and infrastructure, funded from grants, capital receipts, Community Infrastructure Levy, reserves or borrowing.
  • Earmarked reserves: Money the Council has set aside for a specific purpose, used here to cover the £0.238m overspend.
  • Community Infrastructure Levy (CIL): A charge on new development used to fund infrastructure.
  • S151 Officer: The senior officer with statutory responsibility for the Council's financial administration.
  • Outturn: The actual final spending or income at the end of a financial period, compared with the budget.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item24/26

Resolved

The Committee resolved to approve the quarter 3 2025/226 Capital Programme Budget Monitoring Report for 2026/27 for the Council, showing a £0.238m overspend to be covered by earmarked reserves.
Word for word from the decision Spelthorne published for this meeting. Source: democracy.spelthorne.gov.uk

Follow this further

Built from Spelthorne's papers

What the report saysPro

Report to Corporate Policy and Resources Committee

Corporate Policy & Resources Committee Date of meeting – 17 February 2026

Title Quarter 3 (31 December 2025) Capital Monitoring Report Purpose of the report To make a decision and a recommendation to Council Report Author Altin Bozhani, Deputy Chief Finance Officer (Interim) Ward(s) Affected All Wards Exempt No Corporate Priority Community Addressing Housing Need Resilience Environment Services Recommendations Committee is asked to: 1. Review and approve the Quarter 3 2025/26 Capital Programme budget monitoring report for 2026/27 for the Council, showing a £0.238m overspend to be covered by earmarked reserves; and

Reason for Capital expenditure carries significant risks and Recommendation uncertainties, as large and complex projects are often susceptible to cost variations, delays, and changes in scope or specification. It is therefore important that progress against budget is monitored and emerging issues identified on a timely basis.

1 Executive summary of the report

What is the situation Why we want to do something

 The Council is projecting a gross Capital • To ensure that Committee is expenditure outturn for the year of £9.1m, alerted on a timely basis to £3.0m of this is funded from Government any emerging issues relating grant, or 33% of total. Please see Table 3 to capital projects (paragraph 3.2) for summary of funding and • Ensuring the financial stability Appendices A and B for full details. of the Council  Report also reflects £0.995m of Sports • To aid the cashflow and the England grant carried forwards from 2024/25 Council’s treasury  There is no projection for borrowing to be management activities. required to finance any of the expenditure in 2025/26. This is what we want to do about it These are the next steps • Regular monitoring and reporting of Capital • Reassessment of 2025/26 Programme and funding enable timely and future Capital Programme decision-making, which can generate long assumptions term revenue benefits and improve the • Council to approve requested Council’s financial control. supplementary estimate of £0.096m.

2 Key issues 2.1 This report provides a summary of Capital Programme expenditure as at the end of December 2025. Detailed supporting information is included in Appendices A/B and Tables 1 and 2. 2.2 Any material changes to project scope, or any forecast increase in project costs exceeding the approved budget, must receive prior approval from the Corporate Policy and Resources Committee (CPRC) before any further funds are released. 2.3 The quarter 3 forecast shows that the capital programme will be short of using the allocated budget by £0.142m, which will be transferred to be used in 2026/27. Table 1 Qtr3 Capital Budget Forecast

Managers Projected Budget vs Actuals Outturn at Forecast Budget YTD 31 MARCH Variance Committee 2025/26 2025/26 2026 Over/(Under) COMMENTS £000 £000 £000 £000

Corporate Policy and 1,430 326 1,288 (142) Variance due to General Hardware - Annual Resources Programme. Actual year to date spend as % of forecast is low. Please see Appendix B for details. Community, Welbeing and 6,455 3,930 6,803 348 Actual year to date spend as % of forecast Housing is low. The budget holder has confirmed the (Disabled Facilities Grant project's full allocation will be spent by Annual Programme) 31.03.2026. Please see Appendices A/BB for details. Business Infrastructure - 322 103 322 0 Actual year to date spend as % of forecast Growth is low. The budget holder has confirmed the project's full allocation will be spent by 31.03.2026. Please see Appendices A/B for details. Environment & Sustainability 700 199 732 32 Actual year to date spend as % of forecast is low. The budget holder has confirmed the project's full allocation will be spent by 31.03.2026. Please see Appendices A/B for details. TOTAL 8,907 4,557 9,145 238 Reserve balances still to be (380) (380) applied at year end GRAND TOTAL 8,907 4,557 8,765 (142)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Detailed Report Q3 2025-26 Capital Monitoring /26Appendix A 240 KB Download
PDF
Capital Project Details and Funding for 2025-26 /26Appendix B 426 KB Download
PDF
Q3 Capital Monitoring ReportReport 382 KB DownloadRead as text
PDF
View item 24/26 as HTML 98 KBReport 98 KB Copy on its way

At this meeting

Whole meeting

Who was there

15 of 26 attended
JS
Councillor Joanne SextonChair, present
CB
Councillor Chris BatesonVice-Chair, present
MA
Councillor Maureen AttewellCommittee Member, present
JB
Councillor John BoughtflowerCommittee Member, present
MB
Councillor Med BuckCommittee Member, present
JB
Councillor Jon ButtonCommittee Member, present
DC
Councillor Darren ClarkeCommittee Member, present
SD
Councillor Sue DoranCommittee Member, present
MG
Councillor Michele GibsonCommittee Member, present
ML
Councillor Matthew LeeCommittee Member, present
SM
Councillor Sinead MooneyCommittee Member, present
LN
Councillor Lawrence NicholsCommittee Member, present

All 26 on the meeting page

On this subject at Spelthorne

Search all
  1. Q3 Capital Monitoring ReportThis decision
  2. Q2 Capital Monitoring Report as at 30 September 2025Approved
  3. Quarter 2 (30 September 2024) Capital Monitoring ReportNoted
  4. Q1 Capital Monitoring ReportNoted
  5. Capital Monitoring Report (Qtr. 1 April - June)Agreed
  6. Interim Capital Monitoring Report 2020/21 - 31 March 2021Noted

More from Spelthorne Corporate Policy and Resources Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Write Offs - Sundry Debts and Housing BenefitsCommittee resolved to approve the write-offs set out in the Appendix 1 and 2 of the report which totalled £52,026 and... Approved Open
12 Oct 2026 Proposed ICT Server ProcurementThe Committee resolved to: 1. Authorise the Council’s ICT Manager to commence a procurement process for the purchase ... Decided Open
12 Oct 2026 Governance Assurance Update - EDI and Financial ManagementThe Committee resolved to: 1. Note the current overall assurance level for the Governance Assurance Areas under the r... Noted Open
12 Oct 2026 Annual Commercial Property Report for Financial Year 2025/26The Committee received the Annual Commercial Property Report for Financial Year 2025/2026. The Committee resolved to:... Approved Open